Foreword
The commissioning is performed after the hardware
installation and before the services are provided
The OMU operating system is installed before the OMU is
delivered
The commissioning ensures the RNC works properly as
designed
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page2
References
“BSC6900 UMTS OMU Administration Guide”
“BSC6900 UMTS Commissioning Guide”
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page3
Objectives
Upon completion of this course, you will be able to:
Describe BSC6900 commissioning procedure
Outline OMU software functions
Complete BSC6900 commissioning
Complete BSC6900 application software installation
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page4
Contents
1. BSC6900 O&M System Introduction
2. BSC6900 Software Installation
3. BSC6900 Commissioning
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page5
BSC6900 O&M Subsystem Component
LMT
OMUa boards
SCUa boards
OM modules
on other boards
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page6
BSC6900 O&M SubsystemBSC6900 O&M system adopts server and client mode
OMU as a server
LMT as a client
EMS (Element Management System) system
iManager M2000 works for integrated O&M
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page7
OMU IP Address Planning
IP Address Planning Principle
Internal fixed IP
address
The preset IP addresses of the internal Ethernet adapters are:
Active BAM: 80.168.3.50 (255.0.0.0)
Standby BAM: 80.168.3.60 (255.0.0.0)
External fixed IP
address
The preset IP addresses of the external Ethernet adapters are:
Active BAM: 172.121.139.201 (255.255.255.0)
Standby BAM: 172.121.139.202 (255.255.255.0)
The settings can be reconfigured on site based on the actual
networking topology
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page8
OMU IP Address Planning
IP Address Planning Principle
Internal/External
virtual IP address
The virtual IP address is set in the same subnet with the internal/
external fixed IP addresses of the active and standby BAMs
Backup channel
IP addresses
The preset backup channel IP addresses of the active and standby
BAMs are:
Active BAM: 192.168.3.50 (255.255.255.0)
Standby BAM: 192.168.3.60 (255.255.255.0)
The IP address should not be changed
Commissioning IP
address
The preset commissioning IP addresses are:
Active BAM: 192.168.6.50 (255.255.255.0)
Standby BAM: 192.168.6.60 (255.255.255.0)
The IP address should not be changed.
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page9
OMU Internal Network IP Address Planning
Active OMUa
Internalnetworksegment
Standby OMUa
80.168.3.50/880.168.3.50/8 80.168.3.60/880.168.3.60/8
SCUa SCUa
Backboard
Intel Ethernet adapters
Intel Ethernet adapters
192.168.3.50/24192.168.3.50/24 192.168.3.60/24192.168.3.60/24
Dedicated backup channel
BSC6900 FAM
Virtual IP
80.168.3.40/8
Virtual IP
80.168.3.40/8
ETH4-SCU7
ETH5-SCU6
ETH4-SCU7
ETH5-SCU6
ETH3-UPDATE
ETH3-UPDATE
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page10
OMU External Network IP Address Planning
Active OMUa
LMT/M2000
Standby OMUa
ExternalnetworkSegment GE adapter
172.121.139.201/24172.121.139.201/24 172.121.139.202/24172.121.139.202/24
Virtual IP 172.121.139.200/24Virtual IP 172.121.139.200/24
ETH0
ETH1
ETH2
ETH0
ETH1
ETH2
192.168.6.60/24192.168.6.60/24
192.168.6.50/24192.168.6.50/24
Hub
Commissioning Ethernet adapter
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page11
Contents
1. BSC6900 O&M System Introduction
2. BSC6900 Software Installation
3. BSC6900 Commissioning
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page12
BSC6900 Software
Dopra Linux Mysql Database
OMU Application
OMU Server
MPS/EPS
Host Software
ProgramFile
Patch File(optional)
Data File
LMT
Windows XPSP2
Java Environment
LMT Software
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page13
OMU Software
The OMU software
consist of multi-
level service
monitoring entities
and service
processes
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page14
OMU Software Installation Procedure
Obtain the Installation Information on the OMU
Remotely Logging In to the OMU
Uploading the OMU Application Installation Package to
the OMU
Installing the OMU Application in the Active Workspace
Checking the Installation Directory of the OMU
Applications
Checking the Status of omud Process
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page15
Obtain the Installation Information on the OMU
Before the installation, obtain the following information
from Data Sheet of BAM Software Installation
Password of the operating system administrator
Fixed IP addresses of the internal and external networks
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page16
Remotely Logging In to the OMU
On the computer run the
SSH terminal, PuTTY
Enter the IP address of
the OMU
Log in to the OMU as
user root
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page17
Uploading the OMU Application Installation Package to the OMU
Decompress the BSC6900 version software package to the
local drive D
Log in to the OMU through the psftp software
Run the lcd D:\ to set the local directory
Run the mkdir /mbsc/upgrade to create the target directory
Run the cd /mbsc/upgrade to go to the target directory
Run the put -r V900R012C00 to upload the OMU application
installation packet to the OMU
After the loading is complete, enter the exit command to exist the
psftp software
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page18
Installing the OMU Application in the Active Workarea
On the PuTTY terminal, run the following commands
cd /mbsc/upgrade/V900R012C00/install/setup
chmod +x ./install_bam.sh
./install_bam.sh
Enter the run mode
Setting the office name
Setting the language
Setting the admin/FTP password
Setting the external virtual IP address
Setting the OMU system type
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page19
Checking the Installation Directory of the OMU Applications
Log in to the OMU by PuTTY
Run the cd /mbsc/bam
Check whether the OMU
installation directory
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page20
Checking the Status of omudProcess
Log in to the OMU by PuTTY
Run the /etc/rc.d/omud status
The returned information is running, it means the omud is
working normally
The returned information is unused, run the /etc/rc.d/omud
start command to start the omud
The returned information is neither running nor unused,
reinstall the OMU application in the active workspace
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page21
Contents
1. BSC6900 O&M System Introduction
2. BSC6900 Software Installation
3. BSC6900 Commissioning
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page22
Contents
3. BSC6900 Commissioning
3.1 BSC6900 Commissioning Introduction
3.2 BSC6900 Commissioning Procedure
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page23
Introduction to BSC6900 Commissioning
Definition of BSC6900 Commissioning
The commissioning of equipment, BSC6900 board
software and data file loading , interfaces verification ,
and services verification after hardware installation
To ensures that the BSC6900 works properly as designed
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page24
Preparation For BSC6900 Commissioning
Preparation For BSC6900 Commissioning
Verify hardware status
BSC6900 hardware is installed and passed the hardware installation check and powering-on check
OMU is configured before delivery
LMT PC meets the configuration requirements
Software preparation
BAM and LMT application software are ready
License file is ready
MML command script for initial configuration is ready
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page25
Preparation For BSC6900 Commissioning (Cont.)
Verify commissioning network status
At least one BTS and one NodeB are connected to the local BSC6900. The BTS and the NodeB should have passed commissioning and can provide basic functions
At least one set of Core Network (CN) equipment is connected to the local BSC6900. The CN equipment should have passed the commissioning and can provide basic functions
If the BSC6900 is connected to the RNC, then that RNC must have passed the commissioning
Three single-mode UEs, three single-mode MSs and one dual-mode UE are ready for test and are registered in the HLR
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page26
Contents
3. BSC6900 Commissioning
3.1 BSC6900 Commissioning Introduction
3.2 BSC6900 Commissioning Procedure
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page27
BSC6900 Commissioning Procedure
Commissioing Prerequsites
Check hardware operating Status
Verify OMU through USB Disk
Verify OMU Locally
Log in to BSC6900 through LMT
Update OMU Database
Activate and Verify the License
Load BSC6900 Board Software and Data
files
Connect BSC6900 to M2000
Local operation
Local operationRemote operation
based on local coopertation
Remote operation
Remote operation
Continued in the next page
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page28
BSC6900 Commissioning Procedure (Cont.)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page29
Checking the Operating Status of the Hardware
Before verifying the equipment, ensure that the cabinet is
powered on and operates normally
Checklist of the power supply to the cabinet components
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page30
Verifying the OMUVerifying the OMU locally
Log in to the OMU through PuTTY
Checking the operation status of the OMU
Checking the version of the OMU application
Changing the external fixed IP address, the external virtual IP
address
Verify the active OMU and the standby OMU respectively
If OMU application is not installed or abnormal, please
reinstall software
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page31
Verifying the OMU (Cont.)
Verifying the OMU through USB Disk
Preparing the USB disk
Installing the operating system
Verifying the LMT
Log in to the BSC6900 through the LMT
Run the MML command LST VER to check the version of OMU
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page32
Updating the OMU Database
Run the MML command script to update the OMU database
Method 1 : through MML commands
Run the MML command SET CFGDATAINEFFECTIVE repeatedly to
set all the subracks to the ineffective mode
Run the MML command RST DATA. A dialog box is displayed. Click
Yes to initialize the BSC6900 configuration data in the OMU database
Upload the MML command script to the /ftp folder in the OMU active
workspace directory
Run the MML command RUN BATCHFILE to run the MML script file
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page33
Updating the OMU Database (Cont.)
Method 2 : through GUI
Run the MML command SET CFGDATAINEFFECTIVE repeatedly to
set all the subracks to the ineffective mode
Run the MML command RST DATA. A dialog box is displayed. Click
Yes to initialize the BSC6900 configuration data in the OMU database
On the LMT, click the Batch tab to enter the Batch panel
Click Open and open the batch file
Click Go to execute the batch file
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page34
Activating and Verifying the License
Activating and Verifying the License
Downloading license to OMU active workspace directory
/ftp/license (DLD LICENSE)
Querying the detail information of the license file (LST
LICENSE)
Activating the license file (ACT LICENSE)
Checking the license consistency between host and OMU
(CMP LICENSE)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page35
Loading the BSC6900 Board Software and Data Files
Loading the BSC6900 Board Software and Data Files
Generating the Data File
Clear the data in the BAM database (RST DATA)
Generate the data file in ineffective state
– SET CFGDATAINEFFECTIVE
– Batch Commands
– FMT DATA
Setting the Loading Mode (SET LODCTRL)
Loading the MPS/EPS/TCS (RST SUBRACK)
Checking the consistency of the data and the version (ACT CRC &
CMP BRDVER)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page36
Verifying the Iub Interface
Verifying the Iub Interface (over ATM)
Verifying Physical Links at the BSC (DSP E1T1 & DSP OPT)
Verifying the Control Plane on the Iub Interface (DSP
SAALLNK & DSP UIUBCP & DSP ADJNODE)
Verifying the User Plane on the Iub Interface (DSP
AAL2PATH)
Verify the Management Plane on the Iub Interface (DSP
IPOAPVC)
Verifying the Cell Setup (DSP UCELL)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page37
Verifying the Iub Interface (Cont.)
Verifying the Iub Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT & DSP
OPT)
Verifying the Control Plane on the Iub Interface (DSP
SCTPLNK & DSP UIUBCP & DSP ADJNODE)
Verifying the User Plane on the Iub Interface (DSP IPPATH)
Verify the Management Plane on the Iub Interface (DSP
IPOAPVC)
Verifying the Cell Setup (DSP UCELL)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page38
Verifying the Iu-CS Interface
Verifying the Iu-CS Interface (over ATM)
Verifying Physical Links at the BSC (DSP E1T1 & DSP OPT)
Verifying the Control Plane on the Iu-CS Interface
– DSP SAALLNK
– DSP MTP3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-CS Interface (DSP
AAL2PATH)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page39
Verifying the Iu-CS Interface (Cont.)
Verifying the Iu-CS Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT & DSP
OPT)
Verifying the Control Plane on the Iu-CS Interface
– DSP SCTPLNK
– DSP M3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-CS Interface (DSP IPPATH)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page40
Verifying the Iu-PS Interface
Verifying the Iu-PS Interface (over ATM)
Verifying Physical Links at the BSC (DSP E1T1 & DSP OPT)
Verifying the Control Plane on the Iu-PS Interface
– DSP SAALLNK
– DSP MTP3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-PS Interface (PING IP)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page41
Verifying the Iu-PS Interface (Cont.)
Verifying the Iu-PS Interface (over IP)
Verifying Physical Links at the BSC (DSP ETHPORT & DSP
OPT)
Verifying the Control Plane on the Iu-PS Interface
– DSP SCTPLNK
– DSP M3LNK
– DSP SSN
– DSP N7DPC
– DSP ADJNODE
Verifying the User Plane on the Iu-PS Interface (DSP IPPATH)
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page42
Handling the Alarms Generated During the Commissioning
Handling Alarms During RNC Commissioning
Checking alarm on the LMT
Handling the Alarms by LMT online help
Handling alarms by HUAWEI Technical Support
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page43
Verifying the UMTS Services
To be sure BSC can provide services defined in license file
Basic services
Voice service, CS stream service, PS service, mobility
management, and OM management
Feature services
Inter-system handover, HSDPA service, HSUPA service,
MBMS service, and location service
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page44
Connecting the BSC6900 to the M2000
Connect the BSC6900 to the OM network
Configure the IP route from the BSC6900 to the M2000
(ADD OMUIPRT & ADD EMSIP)
Create the BSC6900 on the M2000
iManagerTM M2000
DCN
Copyright © 2010 Huawei Technologies Co., Ltd. All rights reserved. Page45
Creating Scheduled Tasks
Scheduled tasks for backing up system data (ADD
SCHTSK & ADD SUBTSK)
Scheduled tasks for backing up logs (ADD SCHTSK & ADD
SUBTSK)
Thank youwww.huawei.com