01-18-2010. FORMOSAT-3 / COSMIC IWG Meeting at the 90th AMS Annual Meeting in Atlanta, Georgia. FORMOSAT-3 Follow-On / COSMIC-II NSPO Plan. Nick Yen, NSPO. Follow-On Mission v.s. FORMOSAT-3/COSMIC (1/2). Follow-On Mission v.s. FORMOSAT-3/COSMIC (2/2). Societal Impacts. - PowerPoint PPT Presentation
Citation preview
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
01-18-2010
FORMOSAT-3 / COSMIC IWG Meeting at the 90th AMS Annual Meeting in Atlanta, Georgia
FORMOSAT-3 Follow-On / COSMIC-II NSPO Plan
Nick Yen, NSPO
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Follow-On Mission FORMOSAT-3/COSMIC Mission
Mission
Establish an operational mission for near real-time numerical weather prediction 8,000 (threshold) profiles per day (the objective is 10,000)
Demonstration of near real-time numerical weather prediction 1,600~1,800 profiles per day
Spacecraft
NSPO will design, procure, and integrate 12 satellites at NSPO NSPO will integrate new GNSS P/L provided by JPL & perform P/L system Integration & Test at NSPO
NSPO define system requirement NSPO & Orbital design spacecraft ; UCAR provide P/L suite EDU and FM1 I&T at Orbital FM2 to FM6 I&T at NSPO
MissionPayload
GPS / GALILEO / GLONASS tracking capabilities
GPS tracking capability
Follow-On Mission v.s. FORMOSAT-3/COSMIC (1/2)
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Follow-On Mission FORMOSAT-3/COSMIC Mission
Launch Vehicle
NOAA will provide 2 to 3 (TBR) launches into selected orbits / inclinations
Use the US Air Force MINOTAUR L/V through UCAR’s Acquisition
Ground
NOAA’s strategy to use US, Europe and Asia Ground Networks
Use USN ground stations for the first 2 years, and then supported by NOAA ground stations for the following 3~5 years
Operations
High degree of automated ground system for 12-satellite constellation
6-satellite constellation operations
Data Processing
TACC UpgradeCDAAC UpgradeGPS-ARC II
TACC & CDAAC Implementation GPS-ARC Initiation
Follow-On Mission v.s. FORMOSAT-3/COSMIC (2/2)
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Societal Impacts
Enhance the Capability on Severe Weather
PredictionMonitor Climate Trend
Enhance the Capabilities of Regional and Global
Weather Prediction
Explore Space Weather Sciences
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
FiducialNetwork
GPSGALILEO
Data Processing Center
TT&C stations (overseas)TT&C stations (Taiwan)
Satellite Operations and Control Center Users Users
GLONASS-CDMA
Follow-On
High-inc
Low-inc
Mission Architecture
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Mission Collaboration between NSPO and NOAA
Joint Mission NSPO/NOAA
MissionNSPO/NOAA
Data ProcessNOAA/NSPO
PayloadsNOAA/NSPO
Ground Sys.NOAA/NSPO
ConstellationNSPO/NOAA
Launch Sys.NOAA/TBD
InterfacesNSPO
ClusterLaunch
NOAA/TBD
SOCCNSPO
Taiwan LTSNSPO
US RTSNOAA
Tri-G PLNOAA/JPL
Sci. PLNSPO/NOAA
CDAAC Upgrade
UCAR
TACC Upgrade
CWB
GPS-ARCNCU
S/C BusNSPO/TBD
Bus ComponentsNSPO/TBD
Taiwan ComponentsROC Vendor
System DesignNSPO
Mission OpsNSPO/NOAA
I&T/EDM/GSENSPO
VerificationNSPO/NOAA
2~3 Launches
L&EONSPO/NOAA
Constellation Deployment
NSPO
Normal OpsNSPO
Europe RTSEUMETSAT
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Program Milestone
SDR2010/6
PDR2010/11
CDR2011/9
ITR2012/6
1st PSR2013/12
1st Launch
AdvancedPayload
EM
AdvancedPayload FM
AdvancedBus
Design
FDR2010/2
2nd Launch
FY 2012 FY 2013 FY 2014
MDR/SRR2010/3
CDRCDR
2014/3
FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 FY2015 FY2016 FY2017 FY2018
3rd Launch2016/122015/8
2nd PSR2015/4
3rd PSR2016/8
△ITR2013/7
FOC2018/2
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
任務規劃任務規劃
FORMOSAT-3 FO
FORMOSAT-3
Potential Follow-On Constellation
Courtesy of UCAR
8 high-inclination-angle SCs+ 4 low-inclination-angle SCs
Data is distributed homogenously
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Follow-On Spacecraft Bus Highlight
Item Follow-On Design FORMOSAT-3 Benefit
System5-year [TBR] mission life
2-year mission life
H- Higher reliability- Longer mission life
Attitude Performance
Roll/Pitch/Yaw:+/-1 deg (3σ)
RRoll/Yaw: +/-5 deg (1σ)
PPitch: +/- 2 deg (1σ)
- Improved attitude performance
Computer Architecture
Centralized architecture
Radiation hard
Distributed architecture
- Integrated computing capability
- Reduced harness & mass
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Current Status and Near Term ActivitiesCurrent Status and Near Term Activities
Follow-On Program Proposal and FORMOSAT-7/COSMIC-2 Agreement have reached the final stage for formal approval and signature at NSC.
The Mission Feasibility Design Review at mission level is planned to be held in February.
NOAA is coordinating Level-1 requirement document and NSPO has been drafting mission requirement document. These two documents will become the baselines for the Follow-On mission. The Mission Definition Review is planned to be held in late March.
NSPO has been developing spacecraft straw- man design. The Mission System Requirement Review is planned to be held in late March.
This document contains proprietary and controlled information of National Space Organization (NSPO) of Taiwan and shall not be duplicated in whole or in part for any purpose without permission from NSPO.
Thank You !