Upload
tshawky
View
219
Download
0
Embed Size (px)
Citation preview
7/21/2019 003 Estimating Material
1/38
1
AACE 022 R 01NL 1
welcomes you to the world of
TOTAL COST MANAGEMENT
Arabian Gulf Section
AACE 022 R 01NL 2
Cost Estimating - Session # 03
Chapters 09, 10 & 11
Prepared & Compiled by :
Nihmathullah K. Lebbe CC E, MACostE, AIQS(Affil.)
Arabian Gulf Section
7/21/2019 003 Estimating Material
2/38
2
AACE 022 R 01NL 3
Profile of Subject Matter Expert
Nihmathullah K. Lebbe CCE, MACostE, AIQS(Affil)Manager - Quantity Surveying
MUSHRIF Trading & Contracting Co WLL
Telephone Nos : +973-39781001, +973-36629165
E-mail ID : [email protected], [email protected]
Nihmathullah Kalanther Lebbeis a Professional Quantity Surveyor & Cost Engineer
with a Bachelors Degree in Architectural Engineering- USA, Civil Engineering
Technology from University of Moratuwa - Sri Lanka, various PG studies in Construction
Cost & Contract Management
Nihmathullahis a Certified Cost Engineer (CCE), Professional Quantity Surveyor who is
also member of various International professional associations such as AACEI, RICS,
PMI, ACostE (UK), AIQS, NCMA.
Nihmathullahhas more than 17 years of experience in the fields of Construction Cost &
Contract Management. His expertise covers various Mega Projects such as Power
Plants, Process Plants, Oil&Gas, Industrial, High-rise Buildings, Infrastructure projects.
He is currently the Director Education (Bahrain) for the AACEI- Arabian Gulf Section.
AACE 022 R 01NL 4
Presented by,
Josue E. Garcia, CCE
Estimating Engineer Saudi Aramco
P O Box 5397, Rastanura 31311
Ph. Off : 880 9029
Mob : 0565529730
E-mail: [email protected]
7/21/2019 003 Estimating Material
3/38
3
AACE 022 R 01NL 5
Chapter 9 Estimating
Introduction / Learning Objectives Understand the objectives of generating an estimate.
Understand the various classifications of estimates.
Familiarize the requirements for various estimates.
Understand the timing of the estimate and its importance.
Why qualified resources are essential for a quality estimate.
Why scope definition is important for any estimate.
Understand the application of accuracy ranges for various estimates and itsimportance.
Why corporations set a typical methodology for generating estimates.
The importance of estimate analysis.
Understand the application of allowances within estimates.
Why contingency and risk analysis are undertaken. Understand the need for Work Breakdown Structure.
Importance of estimate and schedule integration.
Importance of basis of estimate.
Importance of estimate reviews.
AACE 022 R 01NL 6
Cost Estimating
A predictive process used to quantify, cost, and price the resources
required by the scope of an asset investment option, activity, or project.
As a predictive process, estimatingmust address risks and uncertainties.
The outputs of estimating are used primarily as inputs for budgeting, cost or
value analysis, decision making in business, asset and project planning, or
for project cost and schedule control processes.
Chapter 9 Estimating
7/21/2019 003 Estimating Material
4/38
4
AACE 022 R 01NL 7
Estimating Methodologies
Conceptual estimating methodologies require significant effort in data
gathering and methods development before estimate preparation begins
Deterministic estimating methods require a high degree of precision in
determination of quantities, pricing, and the completeness of scope
definition.
Chapter 9 Estimating
AACE 022 R 01NL 8
Estimate (AACE):
A compilation of all the costs of the elements of a project or effort includedwithin an agreed upon scope.
Estimate Types:
Chapter 9 Estimating
7/21/2019 003 Estimating Material
5/38
5
AACE 022 R 01NL 9
Order of Magnitude Estimate
An estimate made without detailed engineering data. Some examples would be: an estimatefrom cost capacity curves, an estimate using scale-up or down factors, and an approximateratio estimate. It is normally expected that an estimate of this type would be accurate within(plus) +50 percent or (minus) -30 percent.
Purpose: Feasibility of a project Establishing the probable costs of a program budget; Evaluating cost consequences of proposed design modifications; Selection / Screening from a number of alternative designs/projects Selection from alternative Investments Updating a previously prepared order-of-magnitude estimate; Establishing a preliminary budget for control purposes during the design phase
Order-of-magnitude estimates are based on limited information and are thus subject to
considerable variation. Their accuracy also depends on the amount and quality of information
available as well as the judgment and experience of the estimator.
The order-of-magnitude estimate category encompasses a number of methods.
More commonly used methods are:
End-product units, scale-of-operations, various ratio or factor methods, physical dimensions,
and parametric.
Chapter 9 Estimating
AACE 022 R 01NL 10
Order of Magnitude Estimate
Order-of-magnitude estimates are sometimes referred to as conceptual or ballparkestimates. They have a wide range of accuracy, and have important applications, such asusing them to determine the feasibility of a project quickly or to screen several types ofalternative designs.
Estimates made without detailed engineering data, such as an estimate made from costcapacity curves, an estimate using scale-up or scale-down factors, and an approximate ratioestimate.
These estimates are generally prepared using only basic criteria such as:
desired output, total square meters, or number of units
For Buildings the most typical measure is square meters of floor area or cubic meters ofvolume.Roadways are usually defined by kilometer of a particular type of surface.Process and power plants, the order-of-magnitude may be expressed in plant capacity forinput and/or output.
Chapter 9 Estimating
7/21/2019 003 Estimating Material
6/38
6
AACE 022 R 01NL 11
Budget Estimate
Budget in this case applies to the owner's budget and not to the budget as a project controldocument. A budget estimate is prepared with the use of flow sheets, layouts and equipmentdetails. It is normally expected that an estimate of this type would be accurate within ( plus)+30 percent or (minus) - 15 percent.
Purpose: Establishing probable cost of a budget Evaluating general feasibility of a project Evaluating cost consequences of proposed modifications Establishing preliminary budget for control during design Screening a number of alternative projects
Timing During the planning or development phase of the project. Little or no design completed. Basic criteria such as units of output or area are known.
Why they may failInexperienced Project Managers & EstimatorsLack of Definitive Project ScopeGiving out Off-The-Cuff CostNot employing the Estimating DepartmentLimited Budget for Estimate Preparation
Chapter 9 Estimating
AACE 022 R 01NL 12
Budget Estimate
The wordbudgetapplies to the owners budget and not to the budget as a project controls.
Budget estimates are prepared with the help of flow sheets, layouts, and equipment details.In other words, enough preliminary engineering has taken place to further define the projectscope.
Budget estimates are also called design development, semi-detailed, appropriation, orcontrol estimates.
Since the budget estimate is more definitive than the order-of-magnitude estimate, it is bettersuited for determining project feasibility and establishing definitive budgets.
The accuracy and usefulness of a budget estimate depends, to a large extent, on the amountand quality of information available.
Chapter 9 Estimating
7/21/2019 003 Estimating Material
7/38
7
AACE 022 R 01NL 13
Definitive Estimate
As the name implies, this is an estimate prepared from very defined engineering data. Theengineering data includes as a minimum, nearly complete plot plans and elevations, pipingand instrument diagrams, one line electrical diagrams, equipment data sheets andquotations, structural sketches, soil data and sketches of major foundations, buildingsketches and a complete set of specifications.
This category of estimate covers all types from the minimum described above to themaximum definitive type which would be made from "approved for Construction" drawingsand specifications. It is normally expected that an estimate of this type would be accuratewithin (plus) +15 percent and (minus) -5 percent.
Purposes
Firm Price Bid
Detailed Control Budget Cost Reporting & Control
Final Feasibility Review
Chapter 9 Estimating
AACE 022 R 01NL 14
Definitive Estimate
Prepared from very defined engineering data such as:
Fairly complete plot plans and elevations,
Piping and instrument diagrams,
Single-line electrical diagrams,
Equipment data sheets and quotations,
Structural sketches
Soil data and sketches of major foundations,
Building sketches, and a complete set of specifications.
Thedefinitive estimateincludes various degree of detail estimates which could be madefrom approved for construction drawings and specifications.
These estimates are also known as check, lump sum, tender, and post-contractchange estimates.
Chapter 9 Estimating
7/21/2019 003 Estimating Material
8/38
8
AACE 022 R 01NL 15
Types of Estimates and Applications
There are numerous characteristics that can be used to categorize cost estimate types. Themost significant characteristics are degree of project definition, end usage of the estimate,estimate methodology, as well as the effort and time needed to prepare the estimate.
In 1998, AACE International published a new Recommended Practice 18R-97 CostEstimate Classification System For the Process Industries The primary characteristicused in this practice to define the estimate class is the degree of project definition.
The primary characteristic is based upon percent complete of the project definition (roughlycorresponding to percent complete of engineering).
The new AACE estimate classes and ANSI Standard Chapter 2 addresses Order-of-
Magnitude Estimate, which corresponds to AACE Class 5 estimate.
Chapter 3 focuses on Definitive Estimate, which relates to AACE Class 1 and Class 2
estimates.
Chapter 9 Estimating
AACE 022 R 01NL 16
Cost Estimate Classification Matrix for the Process Industries
Chapter 9 Estimating
7/21/2019 003 Estimating Material
9/38
9
AACE 022 R 01NL 17
Chapter 9 Estimating
Capacity Factored Estimating Method
Use of historical data
Typically used against large project elements such as processplant, utilities and infrastructure
AACE 022 R 01NL 18
Capacity Factored Estimating Method
Chapter 9 Estimating
nC2 = C1
A2
A1
C1 = Historical Capital Cost
C2 = Proposed Capital Cost
A1 = Historical Capacity
A2 = Proposed Capacity
n = Variable (Historical Value)
7/21/2019 003 Estimating Material
10/38
10
AACE 022 R 01NL 19
Capacity Factored Estimating Method
Chapter 9 Estimating
Example
Develop the estimated cost to construct a new 1,200M2 control room in Jizan
A recent project involved the construction of a 1,500 M2
control room at a cost of $ 3.5 MM.
AACE 022 R 01NL 20
Capacity Factored Estimating Method
Chapter 9 Estimating
C1 = $ 3.5 MMA1 = 1,500A2 = 1,200n = 0.6
Develop C2
C2 = $ 3.5MM1,200
1,500
0.6
C2 = $ 3.5MM (0.800)0.6 = $ 3.06 MM
nC2 = C1
A2
A1
The standard value for n is 0.6 (Six Digit Formula)
7/21/2019 003 Estimating Material
11/38
7/21/2019 003 Estimating Material
12/38
12
AACE 022 R 01NL 23
Direct CostsConstructionCost of installed equipment, material and labor directly involved in the physical constructionof the permanent facility .
ManufacturingService and other non-construction industries, the portion of operating costs that isgenerally assignable to a specific product or process area .
Indirect CostsConstruction
All costs which do not become a final part of the installation, but which are required for the
orderly completion of the installation and may include, but are not limited to, fieldadministration, direct supervision, capital tools, startup costs, contractor's fees, insurance,taxes, etc .
ManufacturingCosts not directly assignable to the end product or process, such as overhead and generalpurpose labor, or costs of outside operations, such as transportation and distribution.Indirect manufacturing cost sometimes includes insurance, property taxes, maintenance,depreciation, packaging, warehousing and loading. In government contracts, indirect cost isoften calculated as a fixed percent of direct payroll cost .
Chapter 9 Estimating
AACE 022 R 01NL 24
Types of Overhead
Home Office Overhead (Often called G&A Expenses)
General Overhead-the fixed cost in operation of a business.General overhead is also associated with office, plant, equipment, staffing, and expensesthereof, maintained by a contractor for general business operations. The costs of generaloverhead are not specifically applicable to any given job or project.
Project Overhead (General Conditions)
Field Cost - Engineering and Construction costs associated with the construction siterather than with the home office.
Home Office Cost - Those necessary costs involved in the conduct of everydaybusiness, which can be directly assigned to specific projects, processes, or end products,such as engineering, procurement, expediting, legal fees, auditor fees inspection, estimating,cost control, taxes, travel, reproduction, communications, etc.
Job OverheadThe expense of such items as trailer, toilets, telephone, superintendent, transportation,temporary heat, testing, power, water, cleanup, and similar items possibly including bond andinsurance associated with the particular project.
Chapter 9 Estimating
7/21/2019 003 Estimating Material
13/38
13
AACE 022 R 01NL 25
Construction Job Indirect Checklist
Chapter 9 Estimating
AACE 022 R 01NL 26
Construction
Job Indirect
Checklist
Chapter 9 Estimating
7/21/2019 003 Estimating Material
14/38
14
AACE 022 R 01NL 27
Project Risk
Allowances
Additional resources included in estimates to cover the cost of known, but undefined,requirements for an individual activity, work item, account or subaccount.
Contingency
An amount added to an estimate to allow for items, conditions, or events for which thestate, occurrence, and/or effect is uncertain and that experience shows will likely result, inaggregate, in additional costs. Typically estimated using statistical analysis or judgmentbased on past asset or project experience.
Chapter 9 Estimating
AACE 022 R 01NL 28
Contingency can include:
Planning and estimating errors and omissions,
Minor price fluctuations
Changes within the scope, and
Variations in market and environmental Conditions
Contingency usually excludes;
Major scope changes
Extraordinary events
Management reserves, and
Escalation and currency effects.
Chapter 9 Estimating
7/21/2019 003 Estimating Material
15/38
15
AACE 022 R 01NL 29
Estimate Documentation:
An estimate should always include written documentation on how it was developed, andwhat is included or excluded. Nature of estimate is order-of magnitude, definitive, a bid, ora study, it almost always becomes a benchmark against which future estimates or costsare measured.
If litigation should develop, a court case can be won or lost based on the information thatwas used to develop an estimate;
It is often difficult to know what information was used and what assumptions were madewhen comparing against an estimate that was developed months or even years before.
To avoid such situations, the following should be included in an estimates preparation.
Estimate Purpose
Scope
Assumptions and Exclusions
Time/Cost Association
Contingency Development
Significant Findings
Review Credits
Chapter 9 Estimating
AACE 022 R 01NL 30
The Good Cost Engineer.
7/21/2019 003 Estimating Material
16/38
16
AACE 022 R 01NL 31
Chapter 10 Process Product Manufacturing
Introduction / Learning Objectives
After completing this chapter, the reader should be able to
Understand how to determine the operating and manufacturing costs of a continuousprocess on a conceptual basis,
Distinguish between direct and indirect costs in manufacturing as compared toconstruction,
Relate operating costs at full production to reduced costs at less than full plant capacity,
And
Understand depreciation rules and their relationship to operating and manufacturing costs.
AACE 022 R 01NL 32
Terms to Know Direct costs
Variable costs
Semi-variable costs
Indirect costs or fixed costs
Distribution costs
General and Administrative (G & A) Expenses
Key Points for ReviewPrerequisite of Preparing Operating or Manufacturing Cost Estimate
Process flow sheets with quantity, composition, temperature, pressure etc.
Estimating form serving as a check list,
Obtaining company internal data for similar process
External published data sources but use it with care
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
17/38
17
AACE 022 R 01NL 33
Types of Operating Cost Estimates
The purpose of an operating cost estimate is the controlling factor indetermining the type of estimate to be performed.
Preliminary or order-of-magnitude estimates are often used to screen
projects and to eliminate uneconomical alternatives.
Good judgment is necessary to avoid excessive attention to minor
items, which, even if severely over or underestimated, will not have a
significant effect on the overall estimate.
It is also necessary to calculate costs at reduced production rates as
well as at design capacity.
Operating costs are decidedly nonlinear with respect to production rate.The fact that virtually no plant or process operates all of the time at full
design production rate make it imperative that reduced production ratesbe considered
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 34
Operating Cost Estimates
Operating cost estimates can be performed on a daily, unit of production, or
annual basis. Of these, the annual basis is preferred for the following reasons:
It damps out seasonal variations.
It considers equipment operating time.
It is readily adapted to less-than-full capacity operation.
It readily includes the effect of periodic large costs (scheduledmaintenance, vacation shutdowns, catalyst changes, etc).
It is directly usable in profitability analysis.
It is readily convertible to the other bases, daily cost and unit-of-production, yielding mean annual figures rather
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
18/38
18
AACE 022 R 01NL 35
Variable costs: include the following:
Raw materials,
Utilities,
Royalties (if applicable),
Packaging (if applicable),
Marketing, and
Catalysts and Chemicals.
Semi-variable costs: those which are partially proportional to production level:
Direct labor,
Supervision,
General expense, and
Plant overhead
Fixed-cost items: in addition to royalties if applicable, include the following: Depreciation
Property taxes, and
Insurance.
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 36
Four Ways to Handle Royalties:
Capitalized cost if it is paid in a lump sum,
Fixed cost if it is paid in equal annual increments,
Variable cost if a fee is paid based on per unit of production,
Semi-variable cost if it is paid in a sliding scale (based on per unit of production butdecreases as production increases).
Understand How to Calculate:
Minimum return point
Breakeven point
Shutdown point
Raw Material Costs
External raw material costs
Internal raw material costs transferred at market value or company book value
By Product Credits and DebitsEstimate salable by-product credit from the anticipated selling prices less costs ofprocessing, packaging, selling and transportingto market.
By-product debits include all costs to remove, eliminate, or reduce wastes and pollutants.
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
19/38
19
AACE 022 R 01NL 37
Utility Costs (Total Consumption and Demand) Electricity
Natural gas
Water
Fuel
Equipment losses
Mobile equipment fuels and lubricants
Labor Costs
Straight time
Overtime premium
Supervision
Overhead
Maintenance Costs (Part of Semi-variable Costs)
Direct maintenance labor
Direct maintenance supervision
Maintenance materials
Contract maintenance
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 38
Operating Supplies & Overhead Costs
Operating supplies include lubricant oil, wiping clothes etc
Overhead (burden) costs are associated with payroll or general and administrative expenses.
Expenses of testing and research laboratories
General Work Expense (Factory Overhead)
Indirect cost of operating a plant or factory and is dependent on both investment and labor
Excluding general expense (i.e. marketing or sales cost) and administrative cost.
Depreciation (Treated as Fixed, Indirect Cost) Straight line Method
Double-decline balance method
Accelerated cost recovery system (For US Installation Only)
Modified accelerated cost recovery system (For US Installation Only)
Distribution Costs
Cost of containers
Transportation costs
Applicable labor and overhead for packaging and shipping
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
20/38
20
AACE 022 R 01NL 39
Typical Production
Cost EstimatingForm
AACE 022 R 01NL 40
Cost Effects of Operations at Less Than Full Plant Capacity
Point at which the sales and total costlines cross is the breakeven point for theplant and is equal to the level of output atwhich sales is equal to total cost.
Chapter 10 Process Product Manufacturing
Production Rate/year, % Capacity
7/21/2019 003 Estimating Material
21/38
21
AACE 022 R 01NL 41
Graphically demonstrates the implications of operating at less than full capacity.In this figure, at 100 percent of capacity, the following apply:
Fis the fixed expense;
Vis the variable expense;
Ris the semi-variable expense;
Cis total operating cost;
Sis sales income; and
Nis the income required to achieve the minimum acceptable return on investment before taxes(P) for the capital investment (I).
The variable expense declines to zero at 0 percent of capacity, fixed expense isconstant, and semi-variable expense declines at 0 percent of capacity to from 20to 40 percent of its value at full capacity.
Minimum production rateat which desired return on investment will be achieved (C)
Breakeven point, (point at which income will exactly equal total operating cost) (B)
Shutdown point, or that point at which it is advisable to shut down the plant rather thanoperating at lower production rates (A).
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 42
The plot readily identifies the range of
production rates at which the
following apply:
The return on investment will equal or exceedthe desired minimum (all production rates C);
The return on investment will be less than thedesired value but will be greater than zero(production rates < C b u t > B);
The process will result in a loss, but losses willbe minimized by continuing to operate the plantrather than shutting it down (production rates B but > A);
Losses will become so large that it is lessexpensive to close the plant and pay fixedexpenses out of pocket rather than to continueoperations (production rates A)
The breakeven and shutdown points can alsobe determined mathematically as follows:
B (breakeven point)= (F + nR)
S - V - (1 - n)R
A (shutdown point)= ( nR )
S - V - (1 - n)R
Where
n = decimal fraction of semi-variable costs
incurred at 0 production (usually about 0.3)
Similarly, the total cost line can be expressedas:
Cp = [V + (1 - n)R] p + F + nR
Where
Cp = total cost at production rate pp = actual annual production rate as a
fraction of plant capacity
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
22/38
22
AACE 022 R 01NL 43
Since total annual sales are proportional to production (assuming no stock-piling ofproduction), and, therefore, have no value at zero output, the equation for the sales line is
Sp= ( S x p)
Where
Sp= sales income at production ratep.
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 44
Raw Materials CostsRaw materials costs can constitute a major portion of operating costs.Complete list of all raw materials must be developed using the process flow-sheet as a guide.In developing the raw materials list, the following information must be obtained for each rawmaterial:
Units of purchase (tons, pounds, etc),
Unit cost,
Available sources of the material,
Quantity required per unit of time and/or unit of production, and
Quality of raw materials (concentration, acceptable impurity levels, etc.).
Major factor to be considered in Raw Material CostAppropriate allowance must be made into estimates for:
Losses in handling and storage
Process waste, and
Process yield.
Raw material costs vary with quality (concentration, surface finish of metals, impurities.)
and decrease in unit cost as quantity increases.
Availability of the raw material. Does sufficient productive capacity exist such that the
market can supply the demands of the proposed process?
In pricing raw materials, it must also be remembered that the prices are generally
negotiated & discounts obtained can result in prices substantially less than quoted.
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
23/38
23
AACE 022 R 01NL 45
A Common Notes in Raw materials Cost:
In operating and manufacturing cost estimates is to neglect the cost of raw materialsmanufactured or obtained in-house or from another company division because they arenot purchased.
Fuels that are used as raw materials (eg, natural gas in methane conversion processes)
Periodic makeup of losses to catalysts and other processing materials. In the case ofcatalysts and similar materials
It must be recognized that prices are usually quoted FOB the suppliers plant or basingpoint, not at the point of use.
Thus freight to the point of use & local handling costs must be added to quoted prices.
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 46
Utility CostsRapidly increasing energy costs is a critical area of operating cost estimation.
In estimating utility costs, it is necessary first to determine the requirements for each utilityincluding a reasonable allowance for non-production items, such as plant lighting, sanitarywater, allowance should also be made for miscellaneous usage and contingencies.
Typical utility summary of the nature that is required.
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
24/38
24
AACE 022 R 01NL 47
Utility Costs
If consumption rates fluctuate, utility pricing may be based not only on total consumption,but also in the peak demand rateand, in some cases, the time of day in which the peakoccurs.
Electric power charges are usually based upon a demand factor the maximum power drawduring a 15- to 30-min period in any given month.
A load factor is computed as the ratio of average usage to the demand factor and rates areestablished to give preference to high load factors (i.e., steady consumption).
Natural gas prices depend on quantity required. Steam costs are dependent upon many factors,including pressure, cost of fuel, temperature, credit for heating value of condensate, etc.
Water costs are highly variable depending upon the water quality needed and the quantityrequired. Purification costs, if contamination occurs before disposal, must also be included, asmust cooling costs if the process results in heating of process water.
Water may not be discharged into streams or the natural water table unless it is equal or
better in quality, temperature as when it was withdrawn from the stream
Fuel costs vary with the type of fuel used, Btu value of the fuel, and the source of supply.
Utility consumption generally is not proportional to production due to economies of scale andreduced energy losses per unit of volume or production on larger process units.
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 48
Labor Costs
Chapter 10 Process Product Manufacturing
7/21/2019 003 Estimating Material
25/38
25
AACE 022 R 01NL 49
Supervision and Maintenance Costs
Supervision costs should be established, through astaffing table and tabulation of associated costs.
Costs of supervision can be roughly estimated bytaking a fixed percentageof direct labor costs basedupon company experience. In the absence of prior dataon similar operations, a factor of 15 to 20 percent isgenerally satisfactory.
One front-line supervisor can effectively manage nomore than 8 to 10 workers,
i.e., supervision work-hours of 0.100 to 0.125 per directlabor work-hour.
Frontline supervision (i.e., foremen) at labor ratesapproximately 50 to 60 percent above general laborrates, 15 to 20 percent supervision factor is evident.
Maintenance costs are often estimated as a fixedpercentage of depreciable capital investment per year.
Complex plantsand severe corrosive conditions, thisfactor can be 10 to 12 percentor higher.
Simple plantswith relatively mild, non-corrosiveconditions, 3 to 5 percentshould be adequate.
Maintenance & Depreciation Costs Over the Plant Life
Chapter 10 Process Product Manufacturing
AACE 022 R 01NL 50
Chapter 11 Discrete Product Manufacturing
Introduction / Learning Objectives
Discrete product manufacturing refers to the production of separate, individualproducts.
Whereas continuous manufacturing is concerned with large units to be furtherprocessed.
Discrete manufacturing employs specialized tools for the various products, soset-up and tooling changes are much more frequent in discrete manufacturingthan in continuous manufacturing.
After completing this chapter, the reader should be able to:
Understand the operations, terms and philosophies used in discrete product manufacturing;
Understand basic cost relationships, cost bases, and classification of costs; and
Understand time-based and quantity-based break-even analysis and when it is best to useeach approach.
7/21/2019 003 Estimating Material
26/38
26
AACE 022 R 01NL 51
Terms to Know
Chapter 11 Discrete Product Manufacturing
Administrative expense Indirect costs
Contingency Indirect material costs
Cost Indirect labor costs
Cost estimating Indirect engineering costs
Costing (cost accounting) Indirect burden expenses
Direct costs
Direct material costs
Direct labor costs Mark-up Rate (Profit)
Direct engineering costs 1. Gross Profit
Direct burden expenses 2. Operating Profit Factory expense 3. Net Profit
Production Cost
Marketing, selling and
distribution expense
AACE 022 R 01NL 52
Key Points for Review
Chapter 11 Discrete Product Manufacturing
Introduction Production cost
Concurrent engineering Total cost
Computer aided process planning Selling price
Discrete part manufacturing philosophies Cost estimating guide form
Group technology Break-even analysis
Just-in-time Cost bases
Lean manufacturing Time basedMaterials requirements planning Quantity based
Supply chain management Break-even points
Total quality management Shutdown point
Basic cost relationships Cost point
Prime cost Required return point
Manufacturing cost Required return after taxes point
7/21/2019 003 Estimating Material
27/38
27
AACE 022 R 01NL 53
There are several manufacturing philosophies/techniques introduced during the
last 50 years to assist in reduction of manufacturing costs CAPP Computer aided process planning is able to automatically generate the
process plan to produce component from the component drawing andspecifications
Concurrent engineering is a systematic approach to the integrated, concurrentdesign of products and their related processes, including manufacturing andsupport
Group technology identifies and exploits the underlying sameness of thecomponent parts and manufacturing process
Just-in-time requires the supplies (raw materials) are delivered when required ,and, thus, inventory costs are theoretically driven to zero.
Lean manufacturing leads to shortened lead times, reduced costs and reduceswaste. (Through reducing waste, improving yields, training for employee skills ,improve processes etc)
Material requirements planning uses bills of materials, inventory and open data
order and master production schedule information to calculate requirements formaterials
Supply chain management requires the integration of many different componentsfrom a variety of suppliers to produce complex products.
TQM aims ate continuous improvement in products, services and processes
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 54
Operations in Discrete Part Manufacturing
There are a wide variety of products produced in discrete manufacturing, and, thus, anextreme variety of operations performed to obtain the desired shape and properties requiredof the product.
The operations performed vary considerably depending on the material being used for thespecific component.
Six major groups of component operations and a few of the manufacturing operations of eachgroup are presented in following Table:
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
28/38
28
AACE 022 R 01NL 55
Operations in Discrete Part Manufacturing
Six (06) Major groups of Component Operations Classification for Discrete Manufacturing
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 56
Basic Cost Relationships
Prime Cost* = direct material cost + direct labor cost +direct engineering cost + direct expense
*prime cost is also called direct cost
Manufacturing cost** = prime cost + factory expense
**manufacturing cost is also called factory cost
Production cost = manufacturing cost + administ rative expense
Total cost = production cost + marketing, selling, and distribu tion expense
Selling price = total cost + mark-up (profit and taxes)
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
29/38
29
AACE 022 R 01NL 57
Cost Estimating for Discrete Part Manufacturing
Direct & Indirect Cost
Direct costs are those costs that can be directly related to an specific part and these mostcommonly are direct materials and direct labor.
There can be other direct costs, such as direct engineering or direct burden expenses, butthese are often not separated (even though they should be) and are thus included in theoverhead components.
The direct labor and direct material costs are also referred to as the out-of pocket costs;they are costs which are being directly paid to others and do not cover any of the direct orindirect overhead costs.
The direct labor represents the fully burdened labor costs; that is the benefits as well as thewages.
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 58
Basic Cost Relationship for Discrete Part Manufacturing
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
30/38
30
AACE 022 R 01NL 59
Ladder of Costs for Discrete Part Manufacturing
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 60
General Discrete
Costs Estimating
Form with Illustrative
Example Rates
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
31/38
31
AACE 022 R 01NL 61
Break-Even Analysis
Two critical issues in break-even analysis that must be considered and they are
(a) the cost base and
(b) the various break-even points.
The two different cost bases are the time base and the quantity base.
The quantity-based break-even analysis:
This determines the production quantity at the specific break-even point, and this has workedfor marketing, sales, and top management for forecasting yearly sales and other long-rangeplanning activities. However, it provides little assistance at the plant management level wherethe production quantity is not a variable, but is a quantity specified by the customer.
Time-based break-even analysis:
Focuses on the time to produce the order, which is something under the control of the plant
supervision. Time-based break-even analysis determines the production time for the specificbreak-even point, and this is what can be controlled at the plant level.
The same break-even points can be used in either system, but the costs must be consideredcarefully as the different basestime and quantityresult in different conclusions with respectto the variability of the costs.
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 62
Break-Even Points
The four break-even points that are considered in the profitability evaluation of products oroperations: These points can be evaluated on either the time based or quantity based system.
Shutdown Point (SD)
The shutdown point is the quantity or time where the manufacturing costs equals the revenues.
In the production quantity system the production quantity at which the revenues equal themanufacturing costs.
In the production time system the production time at which the revenues equals themanufacturing costs.
The manufacturing costs include the material costs, tooling costs, labor costs, and plant/shopoverhead costs.
Cost Point (C)
The cost point is the quantity or time where the total costs equals the revenues.
In the production quantity system, it is the production quantity at which the revenues equal thetotal costs
In the production time systemit is the production time at which the revenues equal the totalcosts.
The total costs include the manufacturing costs plus all other costs such as the administrativecosts, selling and marketing, research and development expenses, and etc.
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
32/38
32
AACE 022 R 01NL 63
Break-Even Points
Required Return Point (RR)
The required return point is the quantity or time where the revenues equals the total costs plusthe required return.
In the production quantity systemthe production quantity at which the revenues equal the totalcosts plus the required return.
Required Return after Taxes Point (RRAT)
The required return after taxes point is the quantity or time where the revenues equals the totalcosts plus the required return and the taxes on the required return.
In the production quantity systemit is the production quantity at which the revenues equal thetotal costs plus the required return plus the taxes on the required return.
In the production time system the required return after taxes point is the time at which therevenues equals the total costs plus the required return plus the taxes on the required return.
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 64
Break-Even Points
The quantity-based break-even analysis:
This determines the production quantity at the specific break-even point, and this has worked formarketing, sales, and top management for forecasting yearly sales and other long-rangeplanning activities. However, it provides little assistance at the plant management level wherethe production quantity is not a variable, but is a quantity specified by the customer.
Time-based break-even analysis:Focuses on the time to produce the order, which is something under the control of the plantsupervision. Time-based break-even analysis determines the production time for the specificbreak-even point, and this is what can be controlled at the plant level.
The same break-even points can be used in either system, but the costs must be consideredcarefully as the different basestime and quantityresult in different conclusions with respectto the variability of the costs.
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
33/38
33
AACE 022 R 01NL 65
Break-Even Example ProblemA new job is being considered in the foundry. The order is for 40,000 castings, and the tentativeprice is $ 3.00/casting. The pattern will be designed for 4 castings per mold, and the pattern costhas been quoted at $ 10,000. The molding line is the rate controlling step in the productionprocess in this particular foundry, and the production rate is 125 molds/hr. The estimated timefor the production of the 40,000 castings would be determined by:
(40,000 castings)/(4 castings/mold x 125 molds/hr) = 80 hr
The costs and overheads are included in Table 11.4, and the corporate tax rate is estimated at40 percent.
Production Quantity based Calculations:
The calculations for the four break-even points will be made using X as the variablerepresenting the number of units of production.
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 66
The results from the production quantity
model can be summarized as follows:
If the production quantity is less than 16,068units do not accept the order as themanufacturing costs will not be recovered.
If the production quantity is between 16,068 and26,324 units, the manufacturing costs will berecovered, but not all of the overhead costs.
If production quantity is between 26,424 and
34,530 units, all costs will be recovered, but notall of the required return will be recovered.
If the production quantity is between 34,530 and40,000 units, all of the costs and the requiredreturn will be recovered, but not all of the taxesfor the required return will be recovered. (Thus,the required return will not be recovered aftertaxes as the government will take its share fortaxes).
If the production quantity is more than 40,000units, the required return will exceed the desiredrequired return on an after tax basis.
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
34/38
34
AACE 022 R 01NL 67
Cost Data for Time-Based and Quantity-Based Break-Even Example Problem
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 68
Chapter 11 Discrete Product Manufacturing
Total Cost and Revenues Versus Production Quantity
7/21/2019 003 Estimating Material
35/38
35
AACE 022 R 01NL 69
Chapter 11 Discrete Product Manufacturing
Unit Cost Versus Production Quantity
AACE 022 R 01NL 70
Time Based Calculations The results from the production Timebased model can be summarized as
follows:
If the production time is more than 181.8hours, do not accept the order as themanufacturing costs will not be recovered.
If the production time is between 117.6 and181.8 hours, the manufacturing costs will berecovered, but not all of the overhead costs.
If production time is between 91.7 and 117.6
hours, all of the costs will be recovered, butnot all of the required return will be recovered.
If the production time is between 91.7 and80.0 hours, the costs and the required returnwill be recovered, but not all of the taxes forthe required return will be recovered. (Thus,the required return will not be recovered aftertaxes as the government will take its share fortaxes).
If the production time is less than 80.0 hours,the required return will exceed the desiredrequired return level on an after tax basis.
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
36/38
36
AACE 022 R 01NL 71
Chapter 11 Discrete Product Manufacturing
Total Cost and Revenues Versus Production Time
AACE 022 R 01NL 72
Chapter 11 Discrete Product Manufacturing
Profitability Plot for Time-Based System
7/21/2019 003 Estimating Material
37/38
37
AACE 022 R 01NL 73
The advantage of the time-based break-even analysis is that it can answer questions such as
what is the effect of a 4 hour delay due to a machine breakdown.
The effect is not obvious from the quantity break-even analysis, but the time based break-evenanalysis indicates that 84 hours is between the required return and required return after taxesbreak-even times; that is all costs are recovered and the required return will be exceeded beforetaxes but not after taxes.
This can be evaluated by determining the profit from the following:Profit = Revenues - CostsProfit = $120,000 - ($70,000 + 425$/hr x time (hr))Profit = $50,000 - 225$/hr x 84hrProfit = $14,300Profit after taxes = (1-TR) x 14,300 = 0.6 x 14,300 = 8,580
Since the required return after taxes was 9,600 and the required return before taxes was$16,000, the $ 14,300 amount is between the two expected values. The loss on the time-basesystem could also be evaluated at $ 425 (165 + 110 + 150 = 425) per hour, and for 4 hoursdown the loss would be $1,700.
The loss in the quantity-based system can be obtained by using some of the conversion factors;the loss of 4 hours is equivalent to the production loss of 2,000 units. This loss would be thelabor lost plus the plant overhead and the overhead costs for four hours; thus the loss would be2,000 units x 0.33$/unit + 4hr x (110 + 150) =$660 + $1,040 = $1,700
Chapter 11 Discrete Product Manufacturing
AACE 022 R 01NL 74
The time-based approachis much easier to determine and more straightforward.
Time-based break-even analysis would also be useful in evaluating the cost of bottleneck delaysand provide data for the economic justification of new equipment to improve productivity.
The high cost of delays indicate that one of the factors to consider is the evaluationmanagements performance, and this can be done using a time-based system.
The evaluation of bottlenecks and delays is critical in the theory of constraints and supply-chain management, and the focus is upon time in these situations.
The quantity-based approachis appropriate for marketing and sales forecasting as they needto estimate the revenues obtained and predict the sales quantities. However, at the plant level,where scheduling of the daily operations are concerned, the focus is upon time and time-basedbreak-even analysis is more appropriate.
Chapter 11 Discrete Product Manufacturing
7/21/2019 003 Estimating Material
38/38
AACE 022 R 01NL 75
Questions:
What is the prime cost?
What is the factory cost?
What is the production cost?
What is the selling price?
What is the manufacturing cost?
What is the selling price per unit?