    Pearl GTLProject

    LINDE ENGINEERING

    Contractor Project No:5887Shell Project No: HP-3000-QAT

    Project Document Number: T- 4.251.042 Project Rev.: O Page 2 of 12

    Purchase Order Number: 2MH127

    N/ATag/Item Number(s):

    ASUUnit(s):

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    4/13

    Doc. Title : Method statement for Installation of Earthing System onRCC structure

    Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR

    QATAR SHELL GTL PROJECT (PEARL)

    C2 AIR SEPARATION UNITS CONSTRUCTION

    C O 23.12..2007 Issued for Company comments BR AU/MC ZG ICC

    B 09.12.2007 Issued for Review BR AU/MC ZG IFR

    A 25.11.2007 BR AU/MC ZG IIRIssued for Internal Review

    ApprovedBy

    GAMA ProjectRevRev.

    Date DescriptionPrepared

    ByChecked

    ByStatus

    No. No. ORIGINATOR

    Document Title:

    LINDE ENGINEERING AG

    METHOD STATEMENT FOR INSTALLATION OFEARTHING SYSTEM ON RCC STRUCTURE

    Document No.ContractorLOC470

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    5/13

    Doc. Title : Method statement for Installation of Earthing System onRCC structure

    Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR

    T BLE OF CONTENTS

    1. PURPOSE _____________________________________________________________________5

    2. SCOPE ________________________________________________________________________5

    3. HSE __________________________________________________________________________5

    4. REFERENCES _________________________________________________________________5

    5. DEFINITIONS _________________________________________________________________6

    6. RESPONSIBILITY ______________________________________________________________6

    6.1. SITE MANAGER _________________________________________________________________6

    6.2. CONSTRUCTION MANAGER______________________________________________________6

    6.3. EQUIPMENT MANAGER__________________________________________________________6

    6.4. SITE ENGINEER _________________________________________________________________6

    6.5. SUPERVISOR ____________________________________________________________________7

    6.6. QA/QC INSPECTOR ______________________________________________________________77. EQUIPMENT & MANPOWER ____________________________________________________7

    7.1. EQUIPMENT_____________________________________________________________________7

    7.2. MANPOWER_____________________________________________________________________8

    7.3. MATERIALS_____________________________________________________________________8

    8. METHOD OF EXECUTION ______________________________________________________8

    8.1. PRIOR TO INSTALLATION _______________________________________________________8

    8.2. INSTALLATION__________________________________________________________________8

    8.3. INSPECTIONS ___________________________________________________________________8

    9. QUALITY ASSURANCE _________________________________________________________9

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    6/13

    Doc. Title : Method statement for Installation of Earthing System onRCC structure

    Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR

    1. PURPOSE

    This document describes the methods proposed to be used for the installation of earthingsystem for the inside RCC structure at the Ras Laffan Industrial City in Qatar for the C2 ASUPEARL GTL Project by GAMA-QATAR.

    2. SCOPEThe scope of this method statement is to define the procedure that will be followed at site forthe installation of earthing systems.

    3. HSE

    All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan

    Industrial City and International standards, codes, LINDE/SHELL (OR) PMC requirements andinstructions.

    In addition all employees and GAMA employees on site will have through LINDE/SHELL (OR)PMC Site Safety Induction and GAMA Qatar Safety induction for site safety, health,environmental and security prior to work activities. Other training courses will be attended asrequired by LINDE/SHELL (OR) PMC as required.

    The job safety analysis combined with risk assessment, shall be prepared and attached to thisdocument.Each work scope or task will have a completed and approved Job Safety Analysis (JSA)identifying the potential hazards and control measures that will be implemented to protectpeople and environment.

    The JSA will be used by Supervisor as the basis of conducting his daily Pre-Task meeting and

    his weekly Tool Box Talk (TBT).

    For additional safety requirements for a particular or specific task please refer to the JSAprepared for that task.

    In the event of a release, fire or explosion, employees will secure their area and evacuate to

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    7/13

    Doc. Title : Method statement for Installation of Earthing System onRCC structure

    Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR

    5. DEFINITIONS

    Company : QSGTL or its PMC

    Contractor : LINDE ENGINEERING AG

    Sub Contractor : GAMA QATAR

    Contract : QSGTL Pearl Plant - C2 ASU Project

    ITP : Inspection and Test Plan

    QCP : Quality Control Procedure

    QCR : Quality Control Record

    6. RESPONSIBILITY

    6.1. SITEMANAGER

    The site manager will provide inputs to the project execution plan to ensure that strategies &philosophy are properly addressed.

    6.2. CONSTRUCTIONMANAGER

    The construction manager is responsible for the overall management of the projectconstruction team to ensure that safe and effective operations are conducted and properlydocumented.

    6.3. EQUIPMENTMANAGER

    The equipment manager will be responsible for the transporting equipments availability andgood order.

    6.4. SITEENGINEER

    He shall be overall responsible for safe execution of the whole job including:

    Confirming the installation location from schedule of approved construction drawings

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    8/13

    Doc. Title : Method statement for Installation of Earthing System onRCC structure

    Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR

    6.5. SUPERVISOR

    He shall be responsible for safe execution of the following activities:

    Conduct START talk with the concerned work force prior to start the work which ismandatory requirement of LINDE/SHELL (OR) PMC.

    Ensure that relevant work permits for the job are obtained prior to start the work.

    Conduct daily toolbox talks for the entire work force prior to start day work.

    Assigning a competent work crew for specific activities, details of activities and taskinformation shall be given to the work crew.

    Organizing tools and equipment needed to the work site.

    Inspection and supervision of work.

    Ensure all LINDE/SHELL (OR) PMC safety regulations are followed as applicable.

    Coordination of the work together with the Site Engineer

    6.6. QA/QCINSPECTOR

    He shall be responsible for:

    Assurance of approved methods and materials are being used and conformance ofthe specifications.

    Stage inspections and surveillance in accordance with ITP and assurance of qualityof work as per specification and erection procedures.

    Incoming material inspection and review of test certificates.

    7. EQUIPMENT & MANPOWER

    When materials and equipments are delivered on site, it shall be checked againstmanufacturers drawing and packing list which provided by vendor. Ensure that allitems are received in good condition with respect to packing list with test certificates.

    Materials/equipments shall be stored at inside the storage area with plastic/nylon cover

    on top.Materials/equipments that shall be used for the purpose are as follows:

    7.1. EQUIPMENT

    Cable cutter

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    9/13

    Doc. Title : Method statement for Installation of Earthing System onRCC structure

    Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR

    7.2. MANPOWER

    Supervisor

    Foreman

    Electricians

    Helpers

    7.3. MATERIALS

    Earthing Bus-bars

    Earthing cables

    Earthing rods

    8. METHOD OF EXECUTION

    8.1. PRIORTOINSTALLATION Check the availability of latest revision of drawings.

    Surveying and marking location of earthing location

    Check visual for any damage

    8.2. INSTALLATION

    Installation of the earthing conductors shall be properly identified at the side ofmain earth busbar, as per installation drawing.Install fixed earthing terminal to the reinforcement bar by bolting with clampAll earth connections shall be protected against corrosionProtect the fixed earth conductor threaded portion during concrete.

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    10/13

    Doc. Title : Method statement for Installation of Earthing System onRCC structure

    Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR

    9. QUALITY ASSURANCE

    A Quality Assurance System shall be operated conforming to related standards. Controls andchecks shall be established and documented.

    10. ATTACHMENTS

    JSA

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    11/13

    JOB SAFETY ANALYSIS FORM

    JSA Number: T.4.251.042 Page No: 1 of 2

    Job being analysed: Installation of Junct ion Boxes

    Department/Section doing JSA:HSE & Construct ion JSA Members:

    Job Performers:

    Normal Approvals: Name Signature Date General job requirements / Common

    Personnal Protective Equipment.JSA by:

    Job Supervisor: 1. The following Personal Protective

    Equipment shall be worn while installing

    junction boxes: Approved coveralls, safety

    glasses, safety helmet, safety shoes and

    gloves.

    Additional Approvals (Determined by Job Supervisor in correlation withLINDE/SHELL (or) PMC SHES Manager).

    Name Signature Date

    Discipline Superindent(LINDE/SHELL (or)

    SHES Representative(LINDE/SHELL (or) PMC)

    OTHERS(List Below): 2.Permit To Work.

    Approval required for hazardous work detailed in the LINDE/SHELL (or) PMC work permi t procedure.

    Changing conditions and emergency procedures

    Stop work. Switch of equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees. Missing

    employees are reported to LINDE/SHELL (or) PMC HSSE Dept. When all clear is given check with LINDE/SHELL (or) PMC HSSE before returning to work.

    LINDE/SHELL (or) PMC EMERGENCY RLIC: 474 88 88LINDE HSSE MANAGER: 583 40 72

    Note: 1) If any of the tasks involves biological, physical or chemical hazards, then The LINDE/SHELL (or) PMC Industrial Hygienist must also approve the work.

    2)Use additional sheets as necessary.

    3)Details on safety (PPE,Hazard etc) and environmental requirements can be found in LINDE/SHELL (or) PMC Safety and Environment Procedures.

    NEW REVISED

    QQQ AAA TTT AAA RRR

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    12/13

    HAZARD / POTENTIAL RISK CURRENT ADDITIONALCONSEQUENCES RANK CONTROLS CONTROLS

    1 1.1.1 Ensure employee wear approved hand

    gloves.

    1.1.1.1

    1.1.2 Keep away hand and fingers to any

    pinch point hazard during frominstallation of junction boxes.

    1.2.1 Ensure all tools shall be inspected and

    color coded.

    1.2.1.1

    1.2.2 Do not use wrenches if the jaws are

    sprung when tightening bolts.

    1.2.3 Do not use tools with loose, cracked,

    splintered.

    1.2.4 Use the right tool for the job during

    tightening of bolts.1.3.1 Ensure all electrical power tools have

    a 3 wire cord plugged into a grounded

    receptacles & must be double

    insulated.1.3.2 Insulate yourself from work and

    ground.

    1.3.3 Dont allow any live electrical parts to

    touch the ground.

    1.3.4 Ensure all cables must be kept clear ofany standing water.

    1.3.5 Ensure good electrical connection.

    1.4 Eye injury.B 2 MED

    1.4.1 Ensure employee wear a approved

    eye protection.

    1.5.1 Ensure employee are trained and

    competent to carry out task.

    1.5.2 Wear approved working gloves.

    1.5.3 Removed all sharp edges on the steel

    junction box using roughed pile.

    1.5.1.1

    MED3

    Cut injury due to

    presence of sharp edges

    in the steel boxes.B LOW3A

    Supervisor/foreman shall ensure

    that the TSTI is properly executed

    at the work front and hazards

    discussed.

    1.5

    LOW4AMED

    Ensure all auxiliary power

    receptacles shall be protected by

    an ELCB set to trip at 30mA.

    Dont touch electrically live parts

    with skin or wet clothing.

    1.3.1.1

    1.3.1.2

    1.3

    4

    Electric shock.

    Improper use of hand &

    power tools.

    Hand & Finger Injury.

    MED

    Operate according to

    manufacturers instructions.

    3B

    1.2

    1.1

    RP C

    Ensure Supervisor to supervised all

    works at all times as per Work

    Method Statement. LOW3A

    JOB SAFETY ANALYSIS / RISK ASSESSMENT

    T.4.251.042SCOPE: Installation earth Systems

    Residual RiskInitial Risk

    ITEM ACTIVITY CP

    Installation of Earth

    Systems.

    B

    MED3B

    QQQ AAA TTT AAA RRR

  • 7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf

    13/13

    HAZARD / POTENTIAL RISK CURRENT ADDITIONALCONSEQUENCES RANK CONTROLS CONTROLS

    RP C

    JOB SAFETY ANALYSIS / RISK ASSESSMENT

    T.4.251.042SCOPE: Installation earth Systems

    Residual RiskInitial Risk

    ITEM ACTIVITY CP

    QQQ AAA TTT AAA RRR

    1.6.1 Employees shall wear clear lens safety

    glasses.

    1.6.2 All access should be cleared of all

    materials.

    1.6.3 Lighting shall be set up to prevent

    shadows.

    1.6.4 Lighting shall be set up in such a way

    that it does not blind employees.

    1.6.5 Provide adequate lighting ( Light

    Towers or Flood Lights) around the

    work fronts, access roads and welfare

    facilities.

    MED3

    1.6

    LOW3A

    Refer to Lighting Plan.

    Obtained Extended Work

    Hours/Night Work Request with

    LINDE approval prior to night work.

    1.6.1.1

    1.6.1.2

    B

    Poor illumination.