Pearl GTLProject
LINDE ENGINEERING
Contractor Project No:5887Shell Project No: HP-3000-QAT
Project Document Number: T- 4.251.042 Project Rev.: O Page 2 of 12
Purchase Order Number: 2MH127
N/ATag/Item Number(s):
ASUUnit(s):
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
4/13
Doc. Title : Method statement for Installation of Earthing System onRCC structure
Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR
QATAR SHELL GTL PROJECT (PEARL)
C2 AIR SEPARATION UNITS CONSTRUCTION
C O 23.12..2007 Issued for Company comments BR AU/MC ZG ICC
B 09.12.2007 Issued for Review BR AU/MC ZG IFR
A 25.11.2007 BR AU/MC ZG IIRIssued for Internal Review
ApprovedBy
GAMA ProjectRevRev.
Date DescriptionPrepared
ByChecked
ByStatus
No. No. ORIGINATOR
Document Title:
LINDE ENGINEERING AG
METHOD STATEMENT FOR INSTALLATION OFEARTHING SYSTEM ON RCC STRUCTURE
Document No.ContractorLOC470
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
5/13
Doc. Title : Method statement for Installation of Earthing System onRCC structure
Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR
T BLE OF CONTENTS
1. PURPOSE _____________________________________________________________________5
2. SCOPE ________________________________________________________________________5
3. HSE __________________________________________________________________________5
4. REFERENCES _________________________________________________________________5
5. DEFINITIONS _________________________________________________________________6
6. RESPONSIBILITY ______________________________________________________________6
6.1. SITE MANAGER _________________________________________________________________6
6.2. CONSTRUCTION MANAGER______________________________________________________6
6.3. EQUIPMENT MANAGER__________________________________________________________6
6.4. SITE ENGINEER _________________________________________________________________6
6.5. SUPERVISOR ____________________________________________________________________7
6.6. QA/QC INSPECTOR ______________________________________________________________77. EQUIPMENT & MANPOWER ____________________________________________________7
7.1. EQUIPMENT_____________________________________________________________________7
7.2. MANPOWER_____________________________________________________________________8
7.3. MATERIALS_____________________________________________________________________8
8. METHOD OF EXECUTION ______________________________________________________8
8.1. PRIOR TO INSTALLATION _______________________________________________________8
8.2. INSTALLATION__________________________________________________________________8
8.3. INSPECTIONS ___________________________________________________________________8
9. QUALITY ASSURANCE _________________________________________________________9
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
6/13
Doc. Title : Method statement for Installation of Earthing System onRCC structure
Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR
1. PURPOSE
This document describes the methods proposed to be used for the installation of earthingsystem for the inside RCC structure at the Ras Laffan Industrial City in Qatar for the C2 ASUPEARL GTL Project by GAMA-QATAR.
2. SCOPEThe scope of this method statement is to define the procedure that will be followed at site forthe installation of earthing systems.
3. HSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan
Industrial City and International standards, codes, LINDE/SHELL (OR) PMC requirements andinstructions.
In addition all employees and GAMA employees on site will have through LINDE/SHELL (OR)PMC Site Safety Induction and GAMA Qatar Safety induction for site safety, health,environmental and security prior to work activities. Other training courses will be attended asrequired by LINDE/SHELL (OR) PMC as required.
The job safety analysis combined with risk assessment, shall be prepared and attached to thisdocument.Each work scope or task will have a completed and approved Job Safety Analysis (JSA)identifying the potential hazards and control measures that will be implemented to protectpeople and environment.
The JSA will be used by Supervisor as the basis of conducting his daily Pre-Task meeting and
his weekly Tool Box Talk (TBT).
For additional safety requirements for a particular or specific task please refer to the JSAprepared for that task.
In the event of a release, fire or explosion, employees will secure their area and evacuate to
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
7/13
Doc. Title : Method statement for Installation of Earthing System onRCC structure
Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR
5. DEFINITIONS
Company : QSGTL or its PMC
Contractor : LINDE ENGINEERING AG
Sub Contractor : GAMA QATAR
Contract : QSGTL Pearl Plant - C2 ASU Project
ITP : Inspection and Test Plan
QCP : Quality Control Procedure
QCR : Quality Control Record
6. RESPONSIBILITY
6.1. SITEMANAGER
The site manager will provide inputs to the project execution plan to ensure that strategies &philosophy are properly addressed.
6.2. CONSTRUCTIONMANAGER
The construction manager is responsible for the overall management of the projectconstruction team to ensure that safe and effective operations are conducted and properlydocumented.
6.3. EQUIPMENTMANAGER
The equipment manager will be responsible for the transporting equipments availability andgood order.
6.4. SITEENGINEER
He shall be overall responsible for safe execution of the whole job including:
Confirming the installation location from schedule of approved construction drawings
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
8/13
Doc. Title : Method statement for Installation of Earthing System onRCC structure
Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR
6.5. SUPERVISOR
He shall be responsible for safe execution of the following activities:
Conduct START talk with the concerned work force prior to start the work which ismandatory requirement of LINDE/SHELL (OR) PMC.
Ensure that relevant work permits for the job are obtained prior to start the work.
Conduct daily toolbox talks for the entire work force prior to start day work.
Assigning a competent work crew for specific activities, details of activities and taskinformation shall be given to the work crew.
Organizing tools and equipment needed to the work site.
Inspection and supervision of work.
Ensure all LINDE/SHELL (OR) PMC safety regulations are followed as applicable.
Coordination of the work together with the Site Engineer
6.6. QA/QCINSPECTOR
He shall be responsible for:
Assurance of approved methods and materials are being used and conformance ofthe specifications.
Stage inspections and surveillance in accordance with ITP and assurance of qualityof work as per specification and erection procedures.
Incoming material inspection and review of test certificates.
7. EQUIPMENT & MANPOWER
When materials and equipments are delivered on site, it shall be checked againstmanufacturers drawing and packing list which provided by vendor. Ensure that allitems are received in good condition with respect to packing list with test certificates.
Materials/equipments shall be stored at inside the storage area with plastic/nylon cover
on top.Materials/equipments that shall be used for the purpose are as follows:
7.1. EQUIPMENT
Cable cutter
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
9/13
Doc. Title : Method statement for Installation of Earthing System onRCC structure
Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR
7.2. MANPOWER
Supervisor
Foreman
Electricians
Helpers
7.3. MATERIALS
Earthing Bus-bars
Earthing cables
Earthing rods
8. METHOD OF EXECUTION
8.1. PRIORTOINSTALLATION Check the availability of latest revision of drawings.
Surveying and marking location of earthing location
Check visual for any damage
8.2. INSTALLATION
Installation of the earthing conductors shall be properly identified at the side ofmain earth busbar, as per installation drawing.Install fixed earthing terminal to the reinforcement bar by bolting with clampAll earth connections shall be protected against corrosionProtect the fixed earth conductor threaded portion during concrete.
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
10/13
Doc. Title : Method statement for Installation of Earthing System onRCC structure
Doc No : GAM-MTS-ELE-GTL-001 Rev. C DATE: 23.12.07QQQ AAA TTT AAA RRR
9. QUALITY ASSURANCE
A Quality Assurance System shall be operated conforming to related standards. Controls andchecks shall be established and documented.
10. ATTACHMENTS
JSA
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
11/13
JOB SAFETY ANALYSIS FORM
JSA Number: T.4.251.042 Page No: 1 of 2
Job being analysed: Installation of Junct ion Boxes
Department/Section doing JSA:HSE & Construct ion JSA Members:
Job Performers:
Normal Approvals: Name Signature Date General job requirements / Common
Personnal Protective Equipment.JSA by:
Job Supervisor: 1. The following Personal Protective
Equipment shall be worn while installing
junction boxes: Approved coveralls, safety
glasses, safety helmet, safety shoes and
gloves.
Additional Approvals (Determined by Job Supervisor in correlation withLINDE/SHELL (or) PMC SHES Manager).
Name Signature Date
Discipline Superindent(LINDE/SHELL (or)
SHES Representative(LINDE/SHELL (or) PMC)
OTHERS(List Below): 2.Permit To Work.
Approval required for hazardous work detailed in the LINDE/SHELL (or) PMC work permi t procedure.
Changing conditions and emergency procedures
Stop work. Switch of equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees. Missing
employees are reported to LINDE/SHELL (or) PMC HSSE Dept. When all clear is given check with LINDE/SHELL (or) PMC HSSE before returning to work.
LINDE/SHELL (or) PMC EMERGENCY RLIC: 474 88 88LINDE HSSE MANAGER: 583 40 72
Note: 1) If any of the tasks involves biological, physical or chemical hazards, then The LINDE/SHELL (or) PMC Industrial Hygienist must also approve the work.
2)Use additional sheets as necessary.
3)Details on safety (PPE,Hazard etc) and environmental requirements can be found in LINDE/SHELL (or) PMC Safety and Environment Procedures.
NEW REVISED
QQQ AAA TTT AAA RRR
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
12/13
HAZARD / POTENTIAL RISK CURRENT ADDITIONALCONSEQUENCES RANK CONTROLS CONTROLS
1 1.1.1 Ensure employee wear approved hand
gloves.
1.1.1.1
1.1.2 Keep away hand and fingers to any
pinch point hazard during frominstallation of junction boxes.
1.2.1 Ensure all tools shall be inspected and
color coded.
1.2.1.1
1.2.2 Do not use wrenches if the jaws are
sprung when tightening bolts.
1.2.3 Do not use tools with loose, cracked,
splintered.
1.2.4 Use the right tool for the job during
tightening of bolts.1.3.1 Ensure all electrical power tools have
a 3 wire cord plugged into a grounded
receptacles & must be double
insulated.1.3.2 Insulate yourself from work and
ground.
1.3.3 Dont allow any live electrical parts to
touch the ground.
1.3.4 Ensure all cables must be kept clear ofany standing water.
1.3.5 Ensure good electrical connection.
1.4 Eye injury.B 2 MED
1.4.1 Ensure employee wear a approved
eye protection.
1.5.1 Ensure employee are trained and
competent to carry out task.
1.5.2 Wear approved working gloves.
1.5.3 Removed all sharp edges on the steel
junction box using roughed pile.
1.5.1.1
MED3
Cut injury due to
presence of sharp edges
in the steel boxes.B LOW3A
Supervisor/foreman shall ensure
that the TSTI is properly executed
at the work front and hazards
discussed.
1.5
LOW4AMED
Ensure all auxiliary power
receptacles shall be protected by
an ELCB set to trip at 30mA.
Dont touch electrically live parts
with skin or wet clothing.
1.3.1.1
1.3.1.2
1.3
4
Electric shock.
Improper use of hand &
power tools.
Hand & Finger Injury.
MED
Operate according to
manufacturers instructions.
3B
1.2
1.1
RP C
Ensure Supervisor to supervised all
works at all times as per Work
Method Statement. LOW3A
JOB SAFETY ANALYSIS / RISK ASSESSMENT
T.4.251.042SCOPE: Installation earth Systems
Residual RiskInitial Risk
ITEM ACTIVITY CP
Installation of Earth
Systems.
B
MED3B
QQQ AAA TTT AAA RRR
7/21/2019 001-MS for Installation Earthing System on RCC Structure.pdf
13/13
HAZARD / POTENTIAL RISK CURRENT ADDITIONALCONSEQUENCES RANK CONTROLS CONTROLS
RP C
JOB SAFETY ANALYSIS / RISK ASSESSMENT
T.4.251.042SCOPE: Installation earth Systems
Residual RiskInitial Risk
ITEM ACTIVITY CP
QQQ AAA TTT AAA RRR
1.6.1 Employees shall wear clear lens safety
glasses.
1.6.2 All access should be cleared of all
materials.
1.6.3 Lighting shall be set up to prevent
shadows.
1.6.4 Lighting shall be set up in such a way
that it does not blind employees.
1.6.5 Provide adequate lighting ( Light
Towers or Flood Lights) around the
work fronts, access roads and welfare
facilities.
MED3
1.6
LOW3A
Refer to Lighting Plan.
Obtained Extended Work
Hours/Night Work Request with
LINDE approval prior to night work.
1.6.1.1
1.6.1.2
B
Poor illumination.