    GSM - e-cell: Radio Cabinet Installation andCommissioning

    Document number: 22-9773Issue number: 3.02Date: September 16, 2005

    Kiosk Reference: PE/ICM/APP/296Kiosk issue: 02.04/EN

    Pkgid: 0000003

    Copyright!2005 Nortel Networks, All Rights Reserved

    Printed in France

    NORTEL NETWORKS CONFIDENTIAL:

    The information contained in this document is the property of Nortel Networks. Except as specifically authorizedin writing by Nortel Networks, the holder of this document shall keep the information contained herein

    confidential and shall protect same in whole or in part from disclosure and dissemination to third parties and usesame for evaluation, operation and maintenance purposes only.

    The content of this document is provided for information purposes only and is subject to modification. It doesnot constitute any representation or warranty from Nortel Networks as to the content or accuracy of theinformation contained herein, including but not limited to the suitability and performances of the product or itsintended application.

    The following are trademarks of Nortel Networks: * NORTEL NETWORKS, the NORTEL NETWORKScorporate logo, the NORTEL Globemark, UNIFIED NETWORKS. The information in this document is subject tochange without notice. Nortel Networks assumes no responsibility for errors that might appear in this document.

    All other brand and product names are trademarks or registered trademarks of their respective holders.

  • 8/11/2019 0000003-22-9773

    2/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 2

    CONTENTS

    1 INTRODUCTION.............................................................................................................5

    1.1 OBJECT..................................................................................................................................5

    1.2 SCOPE ...................................................................................................................................52 RELATED DOCUMENTS...............................................................................................5

    2.1 REFERENCE DOCUMENTS..................................................................................................5

    2.2 APPLICABLE DOCUMENTS..................................................................................................5

    3 ABBREVIATIONS AND TERMS....................................................................................5

    3.1 ABBREVIATIONS...................................................................................................................5

    3.2 TERMS ...................................................................................................................................7

    4 PREREQUISITES...........................................................................................................7

    5 RESOURCES .................................................................................................................8

    5.1 HUMAN RESOURCES...........................................................................................................8

    5.2 HARDWARE TOOLS..............................................................................................................8

    5.3 TOOLS AT THE OMC-R.........................................................................................................9

    6 SAFETY..........................................................................................................................9

    6.1 STAFF SAFETY .....................................................................................................................9

    6.2 EQUIPMENT SAFETY..........................................................................................................10

    7 IMPACTS ON THE NETWORK....................................................................................10

    8 QUALITY CONTROL....................................................................................................10

    9 PRELIMINARY OPERATION AT THE OMC-R SITE ..................................................11

    10 TRANSMISSION PARAMETERS.............................................................................12

    11 SEQUENCE OF OPERATIONS ...............................................................................12

    END OF DOCUMENT ................................................................................................41

  • 8/11/2019 0000003-22-9773

    3/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 3

    SHEETS

    SHEET S1 Preliminary check......................................................................................................... 13SHEET S2 Integrated antenna connection......................................................................................15

    SHEET S3 Cabinet securing...........................................................................................................17

    SHEET S4 Cabinet connection.......................................................................................................20

    SHEET S5 Securing and connection of the extension cabinet ....................................................... 21

    SHEET S6 External antenna connection ........................................................................................ 22

    SHEET S7 Cabinet start up with a PC............................................................................................ 24

    SHEET S8 Cabinet start up with a smart card................................................................................29

    SHEET S9 Extension cabinet start up ............................................................................................ 33SHEET S10 Communication test......................................................................................................35

    SHEET S11 Battery test .................................................................................................................37

    SHEET S12 Final checks ................................................................................................................. 38

  • 8/11/2019 0000003-22-9773

    4/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 4

    APPENDICES

    Appendix 1 Report sheet....................................................................................................................39

    LIST OF FIGURES

    Figure 1: DC cable connector .......................................................................................................... 13

    Figure 2: Presentation of the radio cabinet and the integrated antenna ........................................... 15

    Figure 3: Securing and connecting the internal antenna.................................................................. 16

    Figure 4: Ground connection ...........................................................................................................18

    Figure 5: Location of the securing screw......................................................................................... 18

    Figure 6: Connection at the bottom of the radio cabinet..................................................................20Figure 7: Connection of the antenna jumper....................................................................................22

    Figure 8: RF quarter-wave protection .............................................................................................. 23

    Figure 9: Location of the smart card reader and the Ethernet connector ......................................... 24

    Figure 10: Choose mode screen....................................................................................................... 25

    Figure 11: BTS connection ..............................................................................................................25

    Figure 12: Peer to peer connection .................................................................................................. 26

    Figure 13: CPM windows ................................................................................................................26

    Figure 14: Sequence of starting of the e-cell with parameter of PC................................................ 27

    Figure 15: Insertion of the smart card.............................................................................................. 30

    Figure 16: Location of the auto-test LED........................................................................................ 30

    Figure 17: Sequence of starting of the e-cell ...................................................................................31

    Figure 18: Sequence of starting the extension cabinet.....................................................................34

  • 8/11/2019 0000003-22-9773

    5/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 5

    1 INTRODUCTION

    1.1 OBJECT

    This procedure describes the operations to secure, connect and insert the e-cell radio

    cabinet in a network.

    1.2 SCOPE

    This document applies to the roll-out of the e-cell, with the following characteristics:

    GSM 900, GSM 1800 and GSM 1900.

    With or without Power Supply Unit.

    With or without lightning protection.

    With or without battery back-up assy.

    With or without integrated antenna.

    T1 PCM 100 ,E1 PCM 120 / 75 .

    The configurations are 1O2, 2O4 and 2O2_2.

    2 RELATED DOCUMENTS

    2.1 REFERENCE DOCUMENTS

    None.

    2.2 APPLICABLE DOCUMENTSAll applicable documents are referenced in the report sheet.

    [A1] External release definition : Project document

    [A2] Packing list : Project document

    [A3] Site preparation and installation document : Project document

    [A4] GSM V13/V14/V15 OMC-R operations called by

    BSS I&C procedures

    : 30-9615

    [A5] Test tools quick user guide : 90-9863

    3 ABBREVIATIONS AND TERMS

    3.1 ABBREVIATIONS

    A : Ampere

    AC : Alternative Current

    BSC : Base station controller

  • 8/11/2019 0000003-22-9773

    6/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 6

    BTS : Base Transceiver Station

    CPM : Commissioning Parameter Modification

    DC : Direct CurrentDDF : Dedicated Distribution Frame

    E1 PCM : Pulse Coded Modulation at 2.048 MHz

    GND : GrouND

    GSM : Global System for Mobile communications

    LBO : Line Build Out

    LP : Lightning Protection

    OMC-R : Operations and Maintenance Center for Radio

    subsystem

    PALPRO : Pico Alarm Lightning Protection

    PCM : Pulse Code Modulation

    PPLPRO : Pico PCM Lightning Protection

    PSU : Power Supply Unit

    T1 PCM : Pulse Coded Modulation at 1.544 MHz

    TML : Local Maintenance Terminal

    V : Volt

  • 8/11/2019 0000003-22-9773

    7/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 7

    3.2 TERMS

    Commissioner Person in charge of equipment commissioning

    Coordinator Person in charge of coordinating the project installationSupervisor Person in charge to supervising a site installation

    4 PREREQUISITES

    The required prerequisite operations are:

    The installation kit is secured and wired.

    If necessary, the external antenna is installed and wired.

    Audit of the BSC: on-line BSC site observation.

    The PCM links have been qualified.

    OMC-R data have been created: see preliminary operation at the OMC-R site.

    If necessary, at the DDF, the connection between the PCM cable of the BTS and

    the PCM cable of the transmission equipment has been performed by

    suppression of the loop on the terminal block.

    The unused PCM is check to be looped at the DDF or in the interconnection box.

    In case of parameter modification:

    # By smart card, the smart card with the correct parameters is available with

    the commissioner.

    # By setting directly the parameters on the e-cell, the CPM tool is correctly

    installed on the PC. For CPM installation refer to document 90-9662GSM e-cell CPM User Manual.

    The use of this procedure requires the availability on site of:

    In case of configuration with battery back-up assy, an other battery back-up assy.

    The filled-out report sheet(See Appendixat the end of this document) which

    gives all input data required to apply the procedure.

    All the applicable documents listed in paragraph 2.2.

  • 8/11/2019 0000003-22-9773

    8/41

  • 8/11/2019 0000003-22-9773

    9/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 9

    5.3 TOOLS AT THE OMC-R

    The command files dedicated to the site creation must be available at the OMC-

    R before the beginning of creation operations.

    The EFT files required for the operation are available.

    Two gigatapes for BDE archiving.

    A floppy disk for log files archiving.

    Note: EFT and delivery references, depending on BTS configuration, are found in [A1]

    External release definition.

    6 SAFETY

    6.1 STAFF SAFETY

    Commissioners should respect the safety rules specific to the work site:

    Operators rules

    Site regulations (see signs in the building)

    Product-related rules

    Statutory regulations in the country

    Caution: Extreme caution should always be exercised while working with powered

    equipment in order to avoid injury.

    Warning: The BTS equipment generates, uses, and radiates radio frequency (RF)

    energy. If not installed and operated in accordance with the installation

    methods, personal injury may occur.

    Any outdoor operation is forbidden in case of stormy weather.

    The equipment should not be carried up manually. A mechanical (pulley, cradle...) or

    electrical device should be used to lift them up to the site.

  • 8/11/2019 0000003-22-9773

    10/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 10

    6.2 EQUIPMENT SAFETY

    The cabinet physical installation (and particularly its hoisting in a high site) must be

    postponed in case of windy weather without using a shelter.

    Never remove any internal module or cable

    7 IMPACTS ON THE NETWORK

    In preliminary operations, the OMC-R database is updated to include the data of the

    new BTS.

    During software downloading, some alarms may appear at the OMC-R, which are

    parts of the operation. Just follow the instructions contained in this document,

    waiting the necessary time.

    For information, the downloading times are 5 to 15 minutes.

    During the communication tests, special care should be taken not to disturbcommercial service. Preferably, use a mobile able to communicate on barred cells, so

    that nobody else can connect on this BTS.

    8 QUALITY CONTROL

    All cases of non-compliance should be recorded as they occur and summarized

    clearly on the report sheet.

    For corrective actions, refer to the coordinator.

  • 8/11/2019 0000003-22-9773

    11/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 11

    9 PRELIMINARY OPERATION AT THE OMC-R SITE

    The sequence of OMC-R preliminary operations (using catalog [A4]) is the

    following:Action Condition Sheet OMC

    Creation of OMC-R user CM1

    Installation of CT1000 command files CM6

    BDA audit, archive BDE on a first

    gigatape

    ADM1 /

    ADM2

    Creation command files execution CM3

    Deletion command files execution if CM3 failed CM5

    Software preparation SM17

    BDA audit, archive BDE on a second

    gigatape

    ADM1/

    ADM2

  • 8/11/2019 0000003-22-9773

    12/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 12

    10 TRANSMISSION PARAMETERS

    The default transmission parameters of the radio cabinet loaded by the factory are:

    E1 PCM T1 PCM

    Impedance 120

    TEI number 0 0

    CRC Not used Used

    Frame type ESF

    Codage type B8ZS

    LBO 0 to 40 m

    Management of the parameters

    Default parameters must be changedDefault parameters can be used

    With a smart card With a laptop PC

    Refer to sheet S7 Refer to sheet S6

    11 SEQUENCE OF OPERATIONS

    The sequence of operations is given in the report sheet.

    The operations to be performed by the OMC-R technician are described in [A4] V11-

    V12 OMC-R operations called by BSS I&C procedures, available at the OMC-R site.

    The present document calls OMC-R operations as indicated by the following

    example:

    'Sheet UN2': In that case you should refer to [A4] V11-V12 OMC-R operations

    called by BSS I&C proceduresand make the OMC-R technician perform the UN2

    sheet.

  • 8/11/2019 0000003-22-9773

    13/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 13

    SHEET S1 Preliminary check

    INITIAL STATUS:

    The installation kit(s) is (are) secured.

    The external cables are connected between the installation kit and the customer interface.

    ACTIONS:

    1. Check that the radio cabinets are delivered in their initial packing.

    2. Check that the packages do not show any visible sign of faulty storing or handling

    (wooden packages rotten, saturated with water, cracked, distorted...).

    3. Check that the sites number (or the sites name) and the package number are marked on

    each package and that the number of packages complies with the one given in [A2]:

    packing list.

    4. Check that the shock indicator (the specific label stuck on the external packing of the radio

    cabinets) did not turn red and therefore remains transparent. Should this indicator be

    missing or red, the equipment has to be replaced for it has been subjected to a faulty

    handling during transportation.

    5. Open the packages.

    6. If a battery back-up is used, check that it is disconnected.

    7. At the customer distribution box, put the circuit breaker in ON position.

    8. At the end DC cable in the installation kit, measure the voltage between the points A and B

    using a multi-meter.

    - 48V

    0V

    Figure 1: DC cable connector

  • 8/11/2019 0000003-22-9773

    14/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 14

    9. Check that the measure is within the tolerance range and report it in the Report Sheet, see

    Appendix 1.

    10.At the customer distribution box, put the circuit breaker in OFF position.

    FINAL STATUS:

    The conditions listed above are met, allowing equipment handling.

  • 8/11/2019 0000003-22-9773

    15/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 15

    SHEET S2 Integrated antenna connection

    INITIAL STATUS:

    The radio cabinet(s) is (are) unpacked.

    ACTIONS:

    1. Unfasten the two securing screws from the cosmetic panel.

    2. Slide the cosmetic panel from the radio cabinet.

    3. Slide the integrated antenna on the radio cabinet.

    4. Secure the integrated antenna on the top of the radio cabinet.

    5. Connect the integrated antenna to the top of the radio cabinet.

    6. Check the connection tightening; use a torque driver.

    Securing screws

    Securing screws

    Cosmetic panel Antenna connector

    Antenna connector

    Figure 2: Presentation of the radio cabinet and the integrated antenna

  • 8/11/2019 0000003-22-9773

    16/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 16

    Removal of the cosmetic panel Installation of the integrated antenna

    Securing and wiring the integrated antenna

    Securing screws

    Antenna connector

    Figure 3: Securing and connecting the internal antenna

    7. For a 204 or 202-2 configuration, perform the same operation for the extension cabinet.

    FINAL STATUS:

    The internal antenna(s) is (are) secured and connected to the radio cabinet(s).

  • 8/11/2019 0000003-22-9773

    17/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 17

    SHEET S3 Cabinet securing

    INITIAL STATUS:

    The circuit breaker is off in the customer power distribution.

    ACTIONS:

    1. Set up a phone link with the OMC-R technician and check that the preliminary OMC-R

    operations are over.

    2. If the battery back-up assy is present, check that the date Prochaine Charge WW/YY

    found on the label has not expired. If it has expired the batteries should be returned to the

    warehouse for complete recharging and a new battery back-up assy has to be installed.

    3. In case of installation in an elevated site, the radio cabinet must be lifted with a specific

    tool.

    4. Unfasten the securing screws from the standard cosmetic or the battery back-up assy.

    5. Remove the standard cosmetic or the battery back-up assy from the installation kit and let

    it to hang.

    6. Check that the battery back-up assy is not connected to the PSU.

    7. If an RF lightning protection is used, connect the ground cable on the ground bar of the

    installation kit.

    8. Check the connection tightening on the ground bus bar; use a torque driver (1Nm).

    9. Let the RF lightning protection hang.

    10. Install the radio cabinet on the installation kit.

    11. Secure the radio cabinet with two screws.

  • 8/11/2019 0000003-22-9773

    18/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 18

    PSU

    Reserved forthe intercabinetground cable

    Ground cable ofthe RF lightning protection

    RF lightningprotection

    Figure 4: Ground connection

    Radio Cabinet s ecuring s crews

    Battery back-

    up s ecuring

    screws

    Radio cabinet

    Figure 5: Location of the securing screw

  • 8/11/2019 0000003-22-9773

    19/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 19

    FINAL STATUS:

    The radio cabinet is secured on its installation kit.

  • 8/11/2019 0000003-22-9773

    20/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 20

    SHEET S4 Cabinet connection

    INITIAL STATUS:

    The radio cabinet is secured on its installation kit.

    ACTIONS:

    On the bottom of the radio cabinet, connect:

    1. The ground cable .

    2. The PCM/data cable .

    3. The DC cable .

    DC cable

    Data & PCMcable

    Ground cable

    NETWORK&

    SITE LINK

    POWER IN-48VDC

    TEST & CONFIGURATION

    GNDBottom of the radio cabinet

    DC connectorData & PCMconnector

    Groundconnection

    1

    2

    3

    12

    3

    Figure 6: Connection at the bottom of the radio cabinet.

    FINAL STATUS:

    The radio cabinet is connected to its installation kit.

  • 8/11/2019 0000003-22-9773

    21/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 21

    SHEET S5 Securing and connection of the extension cabinet

    INITIAL STATUS:

    In case an extension cabinet is used in the configuration.

    ACTIONS:

    1. Secure the extension cabinet according to the procedure described in Sheet S3.

    2. Connect the extension cabinet according to the procedure described in Sheet S4.

    3. Check that the end labeled main is connected to the base cabinet and the end labeled

    extension to the extension cabinet.

    FINAL STATUS:

    The extension cabinet is secured and connected.

  • 8/11/2019 0000003-22-9773

    22/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 22

    SHEET S6 External antenna connection

    INITIAL STATUS:

    In case the configuration uses an external antenna.

    The following operation should be performed on each cabinet.

    The radio cabinet(s) is (are) secured.

    ACTIONS:

    1. If an RF lightning protection is used, secure it on the top of the radio cabinet.

    2. Connect the antenna jumper to the top of the radio cabinet or to the RF lightningprotection.

    3. Check the connection tightening; use a torque wrench.

    4. Attach the antenna jumper with cable ties.

    RF antenna jumper

    RF lightning protection

    Ground cable of

    the RF lighning protection

    Figure 7: Connection of the antenna jumper

    5. In case of an e-cell 1900, secure the RF quarter-wave stub protection on the top of the

    radio cabinet with the 3 screws.

  • 8/11/2019 0000003-22-9773

    23/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 23

    RF Quarter Wave Protection

    Figure 8: RF quarter-wave protection

    FINAL STATUS:

    The external antenna(s) is (are) connected.

  • 8/11/2019 0000003-22-9773

    24/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 24

    SHEET S7 Cabinet start up with a PC

    INITIAL STATUS:

    In case the transmission parameters need to be changed with a PC.

    The radio cabinet is secured and connected.

    ACTIONS:

    1. Open the hatch at the bottom of the radio base cabinet.

    2. Ask the OMC-R to unlockthe PCMobject(s) associated with the BTS (sheet INT1).

    3. Switch on the circuit breaker to the radio cabinet in the customer distribution box.

    4. Wait for the auto-test LED to become blinking orange.

    5. Connect the PC to the radio cabinet through the Ethernet connector; see Figure 9.

    NETWORK&

    SITE LINK

    POWER IN48 VDC

    GNDTEST&

    CONFIGURATION

    Smart cardreader

    48 VDCLED

    Autotest LEDstatus

    Hatch

    Ethernetconnector

    Figure 9: Location of the smart card reader and the Ethernet connector

    6. Choose menu Start (Dmarrer)/Programs (Programmes)/Tml/BTS Tools/CPM

    Vxxx/CPM.

    The following window appears (see Figure 9).

  • 8/11/2019 0000003-22-9773

    25/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 25

    Figure 10: Choose mode screen

    7. Check the Read/write radio cabinet configurationbox and click OK.

    The following window appears (see Figure 11).

    Figure 11: BTS connection

    8. Select Peer to Peerconnection type. Click on Connect. The following windows appear

    one after the other (see Figure 12).

  • 8/11/2019 0000003-22-9773

    26/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 26

    Figure 12: Peer to peer connection

    9. Click on Yes, the CPMwindows appears (see Figure 13).

    Figure 13: CPM windows

    10. Select the parameters (TEI, CRC4 and E1 impedance) according to the data given in the

    Appendix 1 Report Sheet.

    11. Click on Writeand accept to reset the BTS.

    12. Ask the OMC-R technician to:

    Unlockthe btssitemanager(Sheet UN1).

    Bar the cells and to prohibit incoming handovers (SheetUN4).

    13. Check the sequence of the auto-test LED.

  • 8/11/2019 0000003-22-9773

    27/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 27

    LED is blinking red

    Status of the

    test LED

    Internal problem :

    - check the customer ACdistribution

    - check the CRC parameter

    LED is blinking orange

    LED is blinking green

    LED is green

    LED is red

    LED is orange

    PCM scanning

    Sofware downloading

    by the BSC

    replace the radio cabinet

    External problem :

    Status of the

    test LED

    LED is orange

    External problem :

    - check the PCM link

    The BTS is

    downloaded

    Power on the e-cell

    at the power supplycustomer box.

    Start of

    BIST autotest

    LED is red

    LED is off

    Figure 14: Sequence of starting of the e-cell with parameter of PC

    14. Disconnect the PC.

  • 8/11/2019 0000003-22-9773

    28/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 28

    15. Close the hatch of the radio cabinet.

    FINAL STATUS:

    The BTS is in service.

    The e-cell is barred, and the incoming handovers are prohibited.

  • 8/11/2019 0000003-22-9773

    29/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 29

    SHEET S8 Cabinet start up with a smart card

    INITIAL STATUS:

    In case the transmission parameters can be updated with a smart card.

    The radio cabinet(s) is (are) secured and connected.

    ACTIONS:

    1. If necessary, open the hatch at the bottom of the radio cabinet.

    2. Ask the OMC-R technician to:

    Unlockthe PCMobject(s) associated with the BTS (sheet INT1).

    Unlockthe btssitemanage(Sheet UN1).

    Barthe cellsand to prohibitincoming handovers(SheetUN4).

    3. Refer to Appendix 1 to knowif the parameters should be changed.

    4. Insert the smart card inside the reader of the radio cabinet according to Figure 15.

  • 8/11/2019 0000003-22-9773

    30/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 30

    Front of the radio cabinet

    Orientation of

    the smard card

    Figure 15: Insertion of the smart card

    5. Switch on the circuit breaker of the radio cabinet in the customer distribution box.

    6. Check the sequence of the auto-test LED.

    NETWORK&

    SITE LINK

    POWER IN48 VDC

    GNDTEST&

    CONFIGURATION

    Smart cardreader

    48 VDCLED

    Autotest LEDstatus

    Hatch

    Figure 16: Location of the auto-test LED

  • 8/11/2019 0000003-22-9773

    31/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 31

    LED is blinking red

    LED is blinking orange

    LED is blinking green

    LED is green

    LED is red

    PCM scanning

    Sofware downloading

    by the BSC

    - change the smart card

    - check the customer

    AC distribution

    - check the CRC parameter

    LED is orange

    External problem :

    Status of the

    test LED

    LED is orange

    External problem :

    - check the PCM links

    The BTS is

    downloaded

    Power on the e-cell

    at the power supply

    customer box.

    Start of

    BIST autotest

    Internal problem :

    replace the radio cabinet

    LED is red

    LED is off

    Smart card

    present ?

    Yes

    No

    Copy parameter

    from smart card

    to radio cabinet flash

    LED blinking red-orange-green

    Status of the

    test LED

    Copy is

    correct ?

    Yes

    No

    External problem :

    Replace the smart card

    LED is orange

    - check the PCM link

    to the extension cabinet

    Figure 17: Sequence of starting of the e-cell

  • 8/11/2019 0000003-22-9773

    32/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 32

    7. Close the hatch of the radio cabinet.

    FINAL STATUS:

    The cell is barred, and the incoming handovers are prohibited.

  • 8/11/2019 0000003-22-9773

    33/41

  • 8/11/2019 0000003-22-9773

    34/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 34

    LED is blinking red

    Status of the

    test LED

    Internal problem :

    - check the customer AC

    distribution

    - check the inter-cabinet

    cable

    LED is blinking orange

    LED is green

    LED is red

    LED is orange

    PCM scanning

    The cabinet is recognized as extension

    PCM scanning is interrupted

    Sofware downloadingby the BSC

    replace the radio cabinet

    External problem :

    The BTS is

    downloaded

    Power on the e-cell

    at the power supply

    customer box.

    Start of

    BIST autotest

    LED is red

    LED is off

    LED is green

    Figure 18: Sequence of starting the extension cabinet

    Note: If the software is downloaded, it lasts about 10 to 15 minutes.

    4. If necessary, close the hatch.

    FINAL STATUS:

    The BTS is in service.

    The cell is barred and the incoming handovers are prohibited.

  • 8/11/2019 0000003-22-9773

    35/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 35

    SHEET S10 Communication test

    INITIAL STATUS:

    The site is enabled.

    The cell is barred and incoming handovers are prohibited.

    ACTIONS:

    There are 2 ways of performing a communication test.

    The following tests should be performed by the commissioner and checked by the OMC-R for

    each TRX:

    At least 1 call on an even TS for each TRX on the main path.

    At least 1 call - mobile originated - to the OMC-R via PSTN for each cell (voice

    quality check) for main.

    At least 1 call - mobile terminated - from the OMC-R via PSTN for each cell (voice

    quality check) for main.

    A. Use of a mobile able to communicate on barred cells

    1. Go away from the BTS site (100 meters if possible), within the area covered by the sector

    to test.

    2. On the mobile, set the following parameters: Cell barred, forced BCCH, inhibit

    handovers, and activate the debug mode.

    3. Check with OMC-R that the BCCH frequency corresponds to the right BCC (BSIC=

    NCC + BCC is displayed on the mobile) (Sheet CT1).

    4. Place the following calls (one call to another mobile located on the BTS site validates 2

    time slots):

    If no Frequency Hopping, one call on an odd time slot, on each frequency of the

    cell. The help of the OMC-R is not required.

    If Frequency Hopping, one call on an odd time slot, on each TRX of the cell,

    checking with OMC-R technician (Sheet CT1) on which TRX is the call.

    At least 2 calls per cell with the OMC-R, one being originated by the OMC-R, and

    check the voice quality.

    5. Report the results in the Report Sheet.

    6. Perform the same tests as above (steps 2 to 8) on the even time slots.

  • 8/11/2019 0000003-22-9773

    36/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 36

    7. If required by the project, place calls on emergency numbers and report the result in the

    Report Sheet.

    B. Use of a standard debug mobile1. Ask the OMC-R technician to unbar only the cell to test (Sheet CT5).

    2. Go away from the BTS site (100 meters at least), within the area covered by the sector to

    test.

    3. If a debug mobile is used, activate the debug mode.

    4. Check with OMC-R the information displayed on the mobile screen: the BCCH

    frequency should correspond to the right BCC (BSIC is displayed on the mobile = NCC +

    BCC).

    5. Once this is checked, place some calls (one call to another mobile located on BTS site

    validates 2 time slots):

    If no Frequency Hopping, place one call on an odd time slot, on each frequency of

    the cell. Ask the OMC-R to confirm (Sheet CT5).

    If Frequency Hopping, place calls on each TRX, checking with OMC-R the TRX

    position of the call.

    Place at least 2 calls with the OMC-R, one being originated by the OMC-R, and

    check the voice quality.

    Note: If it is a Network extension, ask OMC-R technician to visualize in the same

    time, the traffic activity on the cell, with Performance Monitor tool (Sheet

    CT5).

    1. Report the results in the Report Sheet.

    2. If required by the project, perform calls on emergency numbers on a cell and report the

    result in the Report Sheet.

    FINAL STATUS:

    The communication tests are completed for the e-cell.

  • 8/11/2019 0000003-22-9773

    37/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 37

    SHEET S11 Battery test

    INITIAL STATUS:

    In case the configuration uses a battery back-up assy.

    The BTS is on line.

    ACTIONS:

    For each radio cabinet:

    1. Check that the hatch is closed.

    2. Fasten the battery back-up on the chain.

    3. Connect the battery back-up assy at the bottom of the PSU.

    4. Install the battery back-up on the installation kit.

    5. Place a call to check that the BTS capabilities are saved.

    6. Ask the OMC-R technician to check that there is no alarms related to power distribution.

    7. Switch off the e-cell breaker in the customer distribution box.

    8. Ask the OMC-R to check that the following hardware alarms (1067) appear on BTS

    object with the following labeled: AC FAULT.

    9. Make sure the call is not lost.

    10. Switch on the e-cell breaker in the customer distribution box.

    11. Release the call.

    12. Secure the battery back up with its securing screws on the installation kit.

    FINAL STATUS:

    The battery of the e-cell is able to backup the BTS.

  • 8/11/2019 0000003-22-9773

    38/41

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 38

    SHEET S12 Final checks

    INITIAL STATUS:

    The BTS is on line.

    ACTIONS:

    1. Ask the OMC-R technician to unbar the cell and enable the incoming handovers (Sheet

    UN7).

    2. Check with the OMC-R technician that no alarms are remaining.

    3. Ask the OMC-R technician to:

    Manage the remaining alarms (Sheet FO4).

    Display the hardware status of the BTS (Sheet FO5).

    Perform a BDE archiving (Sheet ADM2).

    4. If the OMC-R user profile created for the on-line tests is not required anymore, the OMC-

    R technician may delete it (Sheet FO3).

    5. Check the hatch is closed.

    6. Check the radio cabinet and the battery back up (or the standard cosmetic) are secured on

    the installation kit.

    7. Finish filling out the Report Sheet.

    8. Any non-compliance has to be physically spotted on site and summarized on the Report

    Sheet.

    9. Send one copy of the Report Sheet to the customer representative and another to the

    coordinator.

    10. For corrective actions, refer to the coordinator.

    11. Release the phone link with the OMC-R site.

    12. Leave the premises clean and tidy.

    FINAL STATUS:

    Cell is unlocked, unbarred and incoming handovers are enabled.

  • 8/11/2019 0000003-22-9773

    39/41

    PROJECT:............................

    SITE NAME:.......................

    FOLIO /.....

    RECORD:...................

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 39

    Appendix 1 Report sheet

    The following parts MUST be filled by the coordinator before the site operation.

    Applicable documents:(new documents may be added) Reference Ver. / Ed.

    Project documentation plan ..............................

    [A1] External release definition ..............................

    [A2] Packing list ..............................

    [A3] Site preparation and installation document ..............................

    [A4] V_ OMC operations called by I&C procedures ..............................

    [A5] Test tools quick user guide ..............................

    ....................................................... ..............................

    Note: Default Core methods reference are given in Applicable Documents paragraph.

    Input parameters:(new parameters may be added)

    Network type: GSM 900% GSM 1800% System release: ..........................

    BTS configuration: . SIM card access class: ..........................

    Software versions: . Hardware Reference ..........................

    Parameters need to change : Yes% No% Parameter change with : smart card%

    Laptop PC%

    Drop-insert: Yes% No% TEI number: .

    Parameter E1 Parameter T1

    CRC4 : Yes% No%

    PCM type : 120 Ohms % 75 !Ohms%

    LBO : 0 - 40 % 40 - 81% 81 - 121%

    121 - 162% 162 - 199%

    CRC6 : Yes% No%

    AMI% B8ZS%

    Integrated antenna : Yes% No% RF lightning protection : Yes% No%

    External alarm used : Yes% No% Number of external alarm: .

    Ref of Debug Mobile to use: .......... Mobile for barred cells? : No% Yes%

    Dual band Mobile : No% Yes%

    Emergency numbers to call : No%Yes% Battery backup : No% Yes%

  • 8/11/2019 0000003-22-9773

    40/41

    PROJECT:............................

    SITE NAME:.......................

    FOLIO /.....

    RECORD:...................

    This confidential document is the property of NORTEL NETWORKS and should not be copied or circulated without permission.

    GSM - e-cell: Radio Cabinet Installation and Commissioning

    Method 22-9773 of 09/16/05 Page 40

    In the Action following chart, To Use? column MUST be filled by the coordinator before the siteoperation.

    Action Condition To USE? Sheet SITE Sheet OMC OK NOK

    Preliminary check &. S1

    Integrated antenna

    connection

    In case of

    internal

    antenna

    '. S2

    Cabinet securing &. S3

    Cabinet connection &. S4

    Securing and connectionof the extension cabinet

    For 204 or 202-2

    configurations

    '. S5

    External antenna

    connection

    In case of

    external

    antenna

    '. S6

    Cabinet start up with a PC In case of

    parametermodification

    with a PC

    '. S7 INT1, UN1,

    UN4

    Cabinet start up with a

    smart card

    In case of start

    up with or

    without smart

    card.

    '. S8 INT1, UN1,

    UN4

    Extension cabinet start up For a 204 or

    202-2configuration

    '. S9 INT1, UN1,

    UN4

    Communication test &. S10 CT1, CT4, CT5

    Battery test If battery back-

    up

    '. S11

    Final checks &. S12 UN7, FO4,

    FO5, ADM2,

    FO3

  • 8/11/2019 0000003-22-9773

    41/41

    PROJECT:............................

    SITE NAME:.......................

    FOLIO /.....

    RECORD:...................

    This folio MUST be filled by the commissioner during the site operation.

    Additional results:

    -48V DC measur ements:

    First installation kit Second installation kitV V

    Tolerances: - 57 V < V< - 40.5 V

    Communication Tests

    Channel

    (frequency)

    TRX n 0 1 2 3

    Main(OK/NOK)

    Emergency Calls

    Cell n 0 1 2 Comment

    Emergency ... (OK/NOK)

    Numbers ... (OK/NOK)

    ... (OK/NOK)

    Comments:

    Sign off:

    Coordinator Commissioner Customer representative

    Company name

    Functions

    Name

    Signature

    Date

    END OF DOCUMENT