27
0 to 60: A Milestone Update in the Development of a Holistic Corrosion Prevention & Control Program NICHOLAS D’ANGELO, E.I. ASSOCIATE CORROSION ENGINEER

0 to 60: A Milestone Update in the Development of a

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

0 to 60: A Milestone Update in the Development of a Holistic Corrosion Prevention & Control Program NICHOLAS D’ANGELO, E.I.

ASSOCIATE CORROSION ENGINEER

Introduction

• B.S. in Corrosion Engineering, 2018

• NACE Certified CP Level II (#71600)

• Corrosion Prevention & Control Program Engineer• Responsible for revamping CWD’s cathodic

protection approach

Overview

Program Updates

ECCR Project

Design Manual DevelopmentDocument OverviewDesign GuidelinesDecision Matrix

Continuing Work

Program Updates

• Program Management

• Specification Development

• Common Design Guidelines

• Standard Operating Procedures

• Water Main Design Review

• Failure Analysis (FA)

• Corrosion Education

• Utility Coordination

Corrosion Prevention & Control (CPC)

July 2018

2019

2020

2021

Baseline Assessments

Program Development

Program Implementation

Program Implementation Cont.

Inventory & Pre-Assessments 2018 ICCP BASELINE ASSESSMENT REPORT

Record Drawings Digitization Project GIS Integration, Equipment Procurement, Soil Sampling, ICCP Tank Rehabilitation NACE IMPACT Plus Assessment

Unmanned Aerial System (UAS) Facility InspectionsExternal Corrosion Control Design Manual Draft SOP Development & RefinementFailure Analysis

External Corrosion Control Design Manual Finalization ECCR Construction + RMU UpgradeContinued Equipment ProcurementExpanding CP Consultant Pool

Asset Overview Cleveland Water has an extensive network of impressed current cathodic protection assets, working to mitigate corrosion on nearly 24 miles of transmission mains and over 80 million gallons of potable water

Transmission Mains (5 ICCP Lines)CWD currently has approximately 24 miles of ICCP transmission mains.

Within the distribution network, five individual ICCP systems protect five separate mains:

• Brookpark 36” Main

• Lake Ave. 36” Main

• North Park 48” Main

• South Belvoir 48” Main

• Twin 60s 2-60” & 1-48” Mains

Tanks & Towers (24 Sites)CWD currently has 24 tanks with ICCP systems providing automatically controlled cathodic prevention. ICCP systems protect:

• 12 towers

• Three surge tanks

• Four wash tanks

• Five ground tanks

Rectifiers

Currently operate 50 rectifiers across five transmission mains:• Brookpark: 4• Lake Avenue: 7• North Park: 5 • South Belvoir: 7• Twin 60s: 25• Miscellaneous: 2

Currently operate 24 rectifiers on tanks and towers:• Towers: 12• Surge Tanks: 3• Ground Tanks: 5• Wash Tanks: 4

Tanks/TowerTransmission

LIVE POLL QUESTION #1

Does your organization currently utilize cathodic protection design guidelines in water main installation projects?

a) Yes, generally across all water main projectsb) Yes, however only on an ad-hoc basisc) No, cathodic protection design is often neglected

EXTERNAL CORROSION CONTROL REHABILITATION

Impressed Current Cathodic Protection (ICCP): Transmission Mains

• Advantages• Reliable performance in high soil resistivity

environments• Satisfies high current demands• Variable current controls

• Disadvantages• Stray current concerns• High operating & maintenance costs

ICCP Systems• Principles of Operation:

• Same as GACP• External power supply is used to drive current

demands

• System is monitored via a network of test stations, with direct electrical connections to the main

Junction Box

Protected Pipe (Cathode)

Rectifier

Deep Well Anode Bed

Test Station

Continuity Bond

ICCP Baseline Assessment

Conducted across August and September 2018, the purpose was to identify, quantify, and organize CWD’s cathodic protection assets to determine their operational effectiveness

Assessment Goals• Determine system performance

• Data collection

• Design verification

Outcomes• Identified operational issues

• CIP expenditure justification

• Upper-management engagement

ECCR ProjectThe goal of the External Corrosion Control Rehabilitation CIP is to modernize and replace inoperable transmission main external corrosion control systems

Project Overview

• Project Planning• Historical Review• Field Testing and Verification• Hydraulic and Advanced Planning Review

• Design Methodology: Redesign• Limited Historical Data• Field Testing and Verification• Qualified Cathodic Protection Firm• Technology Integration(s)

• Anticipated Challenges• Original Water Main Design • Electrical Continuity Issues• Test Station Integrity

ECCR Project Cont.

Project Design

• Deep Well Anode Beds Replacements

• Cathodic Protection Test Station Installation

• RMU Upgrades

Field Work

• Comprehensive Process• Soil Analysis• Stray Current Testing• Electrical Continuity Testing

• Test Stations Checks• Pipeline Current Mapping

This project encompassed updating and/or replacing 50 rectifier sites across distribution.

EXTERNAL CORROSION CONTROL DESIGN MANUAL (ECCDM)

Guidance

The development of the External Corrosion Control Design Manual incorporates guidance from numerous sources, including:

• Washington Suburban Sanitary Commission Water Main Design Guidelines

• M27 External Corrosion Control for Infrastructure Sustainability

• WRF Project #4618: Retrofit and Management of Metallic Pipe with Cathodic Protection

• External Corrosion and Corrosion Control of Buried Water Mains. Report. AWWARF #90987.

• Answers to Challenging Infrastructure Management Questions. Report. AWWARF #4367

• 2019 NACE IMPACT Plus Corrosion Management Assessment • 2018 Impressed Current Cathodic Protection Baseline

Assessment

Industry Standards

Internal Assessments

DOCUMENT OVERVIEW

The goal of this manual is to provide information for Cleveland Water (CWD) managers, operators, consultants, and contractors to select the best materials and practices for corrosion control.

• Corrosion Prevention Theory

• Corrosion Control Design Guidelines

• Asset Management Practices

• CP Specifications

• Standard Details

• Appendices• Submittal Overview• Design References

Document Breakdown

Design Guidelines Overview

Controlling External Corrosion

• Material Selection

• Corrosion Inhibitors

• Coatings and Linings

• Cathodic Protection

What are the options?

• Analyzing Conditions

• Optimizing Methods

• Determining Costs

Where do we begin?

Implementing quantitative measures to provide consistent design guidelines for cathodic protection implementation:

1. Likelihood of Corrosion (LoC)

2. Consequence of Failure (CoF)

Likelihood of Corrosion Factors (LoC)

• Point-rated scales for each parameter with total available points ranging 0-50

• Provides framework for uniform soil sampling and analysis

• ASTM Standardization is required for uniform analysis

• Stray Current Analysis complements this process• Severe • Moderate• No Exposure

Soil Corrosivity Rating

Required Field Data

• pH (ASTM G51)• Measurements shall be collected by jar sampling nearest the

proposed pipe depth

• Soil Resistivity (ASTM G57, ASTM G187)• Soil borings shall be collected nearest the proposed pipe depth

• Redox Potential (ASTM D1498)• Measurements shall be collected by jar sampling nearest the

proposed pipe depth

• Soil Type • Soil classification(s) and groundwater level shall be determined

nearest the proposed pipe depth and alignment

• Chloride Content (ASTM D512)• Water soluble chloride content shall be determined by chloride

ion extraction using acceptable industry methodology prior to testing.

Soil Condition Analysis

CONSEQUENCE OF FAILURE

Consequences of Failure (CoF) are critical factors relating to operational reliability, maintainability, and subsequent effects on the distribution system

Four Critical ParametersPoint-rated scales for each parameter with total available points ranging 4-50

I. Pipe Diameter

II. Storage and/or Redundancy

III. Reparability

IV. Consequence to Distribution

Defining Subjective Ranges

• The overarching goal of this effort is to create objective scoring criteria• Reparability Definitions• Consequence to Distribution

(CtD)

PARAMETER RANGE VALUE

36" to 60" 10

28" to 32" 6

16" to 24" 4

4" to 12" 2

No Redundancy 5

No Storage 3

Yes 0

Prohibitive 20Difficult 12

Moderate 5Routine 0

Severe 5

Moderate 3

Appreciable 0

Stor

age

and/

or

Redu

ndan

cy

Cons

eque

nce

to

Dist

ribut

iuon

Repa

riabi

lity

Pipe

Ser

vice

Corrosion Control Decision Matrix

• A risk scoring matrix adapted from The Design Decision Model [Corrpro & DIPRA]. (2018)

• This tool outlines the standard design guidelines unless more stringent requirements are necessitated based on a qualified corrosion professional’s analysis

1 2 3 4 5 6 7 8 9 # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #

Cons

eque

nce

of F

ailu

re (C

oF)

Likelihood of Corrosion501 10 20 30 40

50

10

1

20

30

40Design Guidelines

SAMPLE CALCULATION

Suburban Express Water Main Design

• 5500 LF of proposed express mains

• 16”, 12” and 8”

• Geotechnical Survey• Soil Borings• Soil Resistivity• Soil Sampling

Project Details

Likelihood of Corrosion (LoC)• Clay/Stone Soil Conditions

• Neutral pH, 0-100mV Redox

• >15% Moisture Content, 50-200ppm Chloride Content

• No Stray Current Exposure

Consequence of Failure (Cof)• Pipe Diameter: 4 Points

• Repairability: Prohibitive

• Consequence to Distribution: Moderate

• Storage/Redundancy: 10 Points

• Cathodic Protection Design• Cost Analysis

Sample Calculations

Likelihood of Corrosion (LoC) & Consequence of Failure (Cof) Analysis

• LoC: 26 Points

• CoF: 39 Points

1 2 3 4 5 6 7 8 9 # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #

Cons

eque

nce

of F

ailu

re (C

oF)

Likelihood of Corrosion501 10 20 30 40

50

10

1

20

30

40

Calibrating Expectations

• Establishing Proof-of-Concept

• Maximizing ROI

Design Submittal Process

Submittal I Submittal IIStray Current Submittal(1) All pipe sizes, submit the completed

Cathodic Protection Submittal I form along with:

i. Preliminary plans showing the pipeline alignment

ii. Proposed soil boring locations

(1) All pipe sizes, submit plans and specifications with corrosion control and stray current control measures.

(1) All pipe sizes, submit the completed Cathodic Protection Submittal II form including:

i. Soil Condition Analysis

ii. Stray Current Analysis

iii. Existing Pipe Analysis

iv. External Corrosion Control Requirements

LIVE POLL QUESTION #2

What challenge does your organization primarily experience in addressing corrosion control methods?

a) Identifying appropriate methods of corrosion controlb) Developing design guidelines for implementing corrosion

control methodsc) Identifying corrosion prone areas prior to failured) Securing stakeholder and upper management approval for

integration of corrosion control methodse) All of the above

CONTINUING WORK

CONTINUING WORKI. Capital ProjectsExternal Corrosion Control Rehabilitation

Bidding and Field ConstructionICCP Tank Upgrades

Inclusion of CP Design from Project Inception

II. Specification Development

III. Technology Improvements

External Corrosion Control Design ManualUnified Specifications and DetailsCorrosion Control Decision Framework

Continued Adoption of Industry Best Practices

Unmanned Aerial System (UAS) Facility InspectionsRemote Monitoring Unit (RMU) UpgradesCorrosion Field Testing

Questions

[email protected]

(216) 563-7855

THANK YOU!