69
© Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by R.B. Clough – UNH M. E. Henrie - UAA

© Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Embed Size (px)

Citation preview

Page 1: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Chapter 16 – Project Management

Operations Managementby

R. Dan Reid & Nada R. Sanders3th Edition © Wiley 2010

PowerPoint Presentation by R.B. Clough – UNHM. E. Henrie - UAA

Page 2: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Project Management Applications What is a project?

Any unique endeavor with specific objectives With multiple activities With defined precedent relationships With a specific time period for completion It is one of the process selection choices in

Ch 3 Examples?

A major event like a wedding Any construction project Designing a political campaign

Page 3: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Underlying Process Relationship Between Volume and Standardization Continuum

Page 4: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Project Life Cycle

Conception: identify the need Feasibility analysis or study:

costs benefits, and risks Planning: who, how long, what to

do? Execution: doing the project Termination: ending the project

Page 5: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Network Planning Techniques

Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries of science &

engineering (tasks’ duration = probabilistic)

Critical Path Method (CPM): Developed to coordinate maintenance projects in

the chemical industry A complex undertaking, but individual tasks are

routine (tasks’ duration = deterministic)

Page 6: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Both PERT and CPM

Graphically display the precedence relationships & sequence of activities

Estimate the project’s duration Identify critical activities that cannot be

delayed without delaying the project Estimate the amount of slack associated

with non-critical activities

Page 7: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Network Diagrams Activity-on-Node (AON):

Uses nodes to represent the activity Uses arrows to represent precedence relationships

Page 8: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Step 1-Define the Project: Cables By Us is bringing a new product on line to be manufactured in their current facility in some existing space. The owners have identified 11 activities and their precedence relationships. Develop an AON for the project.

Activity DescriptionImmediate

PredecessorDuration (weeks)

A Develop product specifications None 4B Design manufacturing process A 6C Source & purchase materials A 3D Source & purchase tooling & equipment B 6E Receive & install tooling & equipment D 14F Receive materials C 5G Pilot production run E & F 2H Evaluate product design G 2I Evaluate process performance G 3J Write documentation report H & I 4K Transition to manufacturing J 2

Page 9: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Step 2- Diagram the Network for Cables By Us

Page 10: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Step 3 (a)- Add Deterministic Time Estimates and Connected Paths

Page 11: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Step 3 (a) (Continued): Calculate the Path Completion Times

The longest path (ABDEGIJK) limits the project’s duration (project cannot finish in less time than its longest path)

ABDEGIJK is the project’s critical path

Paths Path durationABDEGHJK 40ABDEGIJK 41ACFGHJK 22ACFGIJK 23

Page 12: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Revisiting Cables By Us Using Probabilistic Time Estimates

Activity DescriptionOptimistic

timeMost likely

timePessimistic

timeA Develop product specifications 2 4 6B Design manufacturing process 3 7 10C Source & purchase materials 2 3 5D Source & purchase tooling & equipment 4 7 9E Receive & install tooling & equipment 12 16 20F Receive materials 2 5 8G Pilot production run 2 2 2H Evaluate product design 2 3 4I Evaluate process performance 2 3 5J Write documentation report 2 4 6K Transition to manufacturing 2 2 2

Page 13: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Using Beta Probability Distribution to Calculate Expected Time Durations

A typical beta distribution is shown below, note that it has definite end points

The expected time for finishing each activity is a weighted average

6

cpessimistilikelymost 4optimistictime Exp.

Page 14: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Calculating Expected Task Times

ActivityOptimistic

timeMost likely

timePessimistic

timeExpected

timeA 2 4 6 4B 3 7 10 6.83C 2 3 5 3.17D 4 7 9 6.83E 12 16 20 16F 2 5 8 5G 2 2 2 2H 2 3 4 3I 2 3 5 3.17J 2 4 6 4K 2 2 2 2

6

4 cpessimistilikelymost optimistictime Expected

Page 15: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Network Diagram with Expected Activity Times

Page 16: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Estimated Path Durations through the Network

ABDEGIJK is the expected critical path & the project has an expected duration of 44.83 weeks

Activities on paths Expected durationABDEGHJK 44.66ABDEGIJK 44.83ACFGHJK 23.17ACFGIJK 23.34

Page 17: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Estimating the Probability of Completion Dates

Using probabilistic time estimates offers the advantage of predicting the probability of project completion dates

We have already calculated the expected time for each activity by making three time estimates

Now we need to calculate the variance for each activity The variance of the beta probability distribution is:

where p=pessimistic activity time estimate

o=optimistic activity time estimate

22

6

opσ

Page 18: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Project Activity VariancesActivity Optimistic Most

LikelyPessimisti

cVariance

A 2 4 6 0.44

B 3 7 10 1.36

C 2 3 5 0.25

D 4 7 9 0.69

E 12 16 20 1.78

F 2 5 8 1.00

G 2 2 2 0.00

H 2 3 4 0.11

I 2 3 5 0.25

J 2 4 6 0.44

K 2 2 2 0.00

Page 19: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Critical Activity VariancesActivity Optimistic Most

LikelyPessimisti

cVariance

A 2 4 6 0.44

B 3 7 10 1.36

C 2 3 5 0.25

D 4 7 9 0.69

E 12 16 20 1.78

F 2 5 8 1.00

G 2 2 2 0.00

H 2 3 4 0.11

I 2 3 5 0.25

J 2 4 6 0.44

K 2 2 2 0.00Critical activities highlighted Sum over critical =

4.96

Page 20: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Calculating the Probability of Completing the Project in Less Than a Specified Time

When you know: The expected completion time EFP

Its variance Path2

You can calculate the probability of completing the project in “DT” weeks with the following formula:

Where DT = the specified completion date EFPath = the expected completion time of the

path

2Pσ

EFD

time standard path

time expected pathtime specifiedz

PT

path of varianceσ 2Path

Page 21: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Apply z formula to critical path

1.424.96

weeks44.83 weeks48z

Use Standard Normal Table (Appendix B) to answer probabilistic questions, such as

Question 1: What is the probability of completing project (along critical path) within 48 weeks?

Page 22: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Probability of completion by DT

ZZ9292 = 1.42 = 1.42 zz00

Project not Project not finished finished

by the given by the given datedate

Tail Area Tail Area = .0778= .0778

Area = .4222Area = .4222

Area Area left of y-left of y-axis axis = .50= .50

Probability = .4222+ .5000 =.9222 or 92.22%

Page 23: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Apply z formula to critical path

Use Standard Normal Table (Appendix B) to answer probabilistic questions, such as

Question 2: By how many weeks are we 95% sure of completing project (along critical path)?

4.96

weeks44.83D1.65 T

Page 24: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Probability Question 2

ZZ9595 = 1.645 = 1.645 zz00

Tail Area = .05Tail Area = .05

Area = .45Area = .45

Area Area left of y-left of y-axis axis = .50= .50

DT = 48.5 weeks

Page 25: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Reducing Project Completion Time Project completion times may need

to be shortened because Different deadlines Penalty clauses Need to put resources on a new

project Promised completion dates

Reduced project completion time is “crashing”

Page 26: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Reducing Project Completion Time - continued

Crashing a project needs to balance Shorten a project duration Cost to shorten the project duration

Crashing a project requires you to know Crash time of each activity Crash cost of each activity

Page 27: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

The Critical Chain Approach

The Critical Chain Approach focuses on the project due date rather than on individual activities and the following realities:

Project time estimates are uncertain so we add safety time Multi-levels of organization may add additional time to be “safe” Individual activity buffers may be wasted on lower-priority activities A better approach is to place the project safety buffer at the end

Original critical pathActivity A Activity B Activity C Activity D Activity E

Critical path with project bufferActivity

AActivity

BActivity C Activity

DActivity

EProject Buffer

Page 28: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Adding Feeder Buffers to Critical Chains

The theory of constraints, the basis for critical chains, focuses on keeping bottlenecks busy.

Time buffers can be put between bottlenecks in the critical path

These feeder buffers protect the critical path from delays in non-critical paths

Page 29: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Approaches to Project Implementation

Pure Project Functional Project Matrix Project

Page 30: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Advantages

A PURE PROJECT is where a self-contained team works full-time on the project

The project manager has full authority over the project

Team members report to one boss Shortened communication lines Team pride, motivation, and

commitment are high

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 31: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Duplication of resources Organizational goals and

policies are ignored Lack of technology transfer Team members have no

functional area "home"

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Pure Project: Disadvantages

Page 32: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Functional Project

President

Research andDevelopment

Engineering Manufacturing

ProjectA

ProjectB

ProjectC

ProjectD

ProjectE

ProjectF

ProjectG

ProjectH

ProjectI

housed within a functional division

Example, Project “B” is in the functional area of Research and Development.

Example, Project “B” is in the functional area of Research and Development.

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 33: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Functional Project: Advantages

A team member can work on several projects

Technical expertise is maintained within the functional area

The functional area is a “home” after the project is completed

Critical mass of specialized knowledge

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 34: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Functional Project: Disadvantages

Aspects of the project that are not directly related to the functional area get short-changed

Motivation of team members is often weak

Needs of the client are secondary and are responded to slowly

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 35: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Matrix Project: combines features of pure and

functionalPresident

Research andDevelopment

Engineering Manufacturing Marketing

ManagerProject A

ManagerProject B

ManagerProject C

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 36: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Matrix Project: Advantages Enhanced communications between

functional areas

Pinpointed responsibility

Duplication of resources is minimized

Functional “home” for team members

Policies of the parent organization are followed

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 37: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

Matrix Project: Disadvantages

Too many bosses

Depends on project manager’s negotiating skills

Potential for sub-optimization

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 38: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Project Management OM Across the Organization Accounting uses project management

(PM) information to provide a time line for major expenditures

Marketing use PM information to monitor the progress to provide updates to the customer

Information systems develop and maintain software that supports projects

Operations use PM to information to monitor activity progress both on and off critical path to manage resource requirements

Page 39: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Chapter 16 Highlights A project is a unique, one time event of some

duration that consumes resources and is designed to achieve an objective in a given time period.

Each project goes through a five-phase life cycle: concept, feasibility study, planning, execution, and termination.

Two network planning techniques are PERT and CPM. Pert uses probabilistic time estimates. CPM uses deterministic time estimates.

Pert and CPM determine the critical path of the project and the estimated completion time. On large projects, software programs are available to identify the critical path.

Page 40: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Chapter 16 Highlights (continued)

Pert uses probabilistic time estimates to determine the probability that a project will be done by a specific time.

To reduce the length of the project (crashing), we need to know the critical path of the project and the cost of reducing individual activity times. Crashing activities that are not on the critical path typically does not reduce project completion time.

The critical chain approach removes excess safety time from individual activities and creates a project buffer at the end of the critical path.

Page 41: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Additional Example

Activity Imm Pred optimistic most likely pessimistic ET sigma0 0 0 0A 0 1 3 5B 0 1 2 3C A 1 2 3D A 2 3 4E B 3 4 11F C,D 3 4 5G D,E 1 4 6H F,G 2 4 5

Note: activity “0” is a formality.

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 42: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Additional Example

Activity Imm Pred optimistic most likely pessimistic ET sigma0 0 0 0 0 0A 0 1 3 5 3.00 0.44B 0 1 2 3 2.00 0.11C A 1 2 3 2.00 0.11D A 2 3 4 3.00 0.11E B 3 4 11 5.00 1.78F C,D 3 4 5 4.00 0.11G D,E 1 4 6 3.83 0.69H F,G 2 4 5 3.83 0.25

Note: activity “0” is a formality.

Source: Chase, Jacobs & Aquilano, Operations Management 11/e

Page 43: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Additional Example, continued

A

B

0

C

D

E

F

G

H

3

2

2

3

5

4

3.83

3.83paths

0ACFH

0ADFH

0ADGH

0BEGH

Page 44: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Additional Example, continued

A

B

0

C

D

E

F

G

H

3

2

2

3

5

4

3.83

3.83

Critical Path: 0-B-E-G-H

Length = 14.67

Page 45: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

A

B

0

C

D

E

F

G

H

.83

0

1.83

0

.83

0

0

.83

Add variances along path

to get path variance

0.11

1.78 0.69

0.25

total=2.83

Additional Example, continued.

Page 46: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Probabilistic Analysis

14.14.6767

16

Project completion times assumed normally distributed with mean 14.67 and variance 2.83

Z-score

79.

83.2

67.1416

z

From table look-up, P(DT16) = .7549

Find the probability of completing the project within 16 days.

Additional Example, continued.

Page 47: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Probabilistic Analysis

Project completion times assumed normally distributed with mean 14.67 and variance 2.83

Z95 = 1.645, thus

83.2

67.14645.1

X

Solving for X=17.44 days

Find the 95-th percentile of project completion.

14.14.6767

17.17.4444

Additional Example, continued.

Page 48: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16:

Activity Optimistic time Most likely time Pessimistic time Expected time VarianceA 8 10 12B 4 10 16C 4 5 6D 6 8 10E 4 7 12F 6 7 9G 4 8 12H 3 3 3

Page 49: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16:

Activity Optimistic time Most likely time Pessimistic time Expected time VarianceA 8 10 12 10.00 0.444B 4 10 16 10.00 4.000C 4 5 6 5.00 0.111D 6 8 10 8.00 0.444E 4 7 12 7.33 1.778F 6 7 9 7.17 0.250G 4 8 12 8.00 1.778H 3 3 3 3.00 0.000

Page 50: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16:

A(10)

B(10) D(8) F(7.17)

C(5) E(7.33)

G(8)

H(3)

Page 51: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16: PATH 1

A(10)

B(10) D(8) F(7.17)

H(3)

Length = 38.17

Page 52: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16: PATH 2

A(10)

C(5) E(7.33)

G(8)

H(3)

Length = 33.33

Page 53: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16: PATH 3

A(10)

B(10) D(8)

G(8)

H(3)

Length = 39

Page 54: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16: PATH 4

A(10)

F(7.17)

C(5) E(7.33)

H(3)

Length = 32.5

Page 55: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 2, #13-14 Ch 16: CRITICAL PATH

A(10)

B(10) D(8)

G(8)

H(3)

Length = 39

Path variance = 6.67

Page 56: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Apply z formula to critical path

-1.166.66

weeks93 weeks36z

Use Standard Normal Table (Appendix B) to answer probabilistic questions, such as

Question 1: What is the probability of completing project (along critical path) within 36 weeks?

Page 57: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Probability of completion by DT

Z = -1.16Z = -1.16 zz00

Project finished Project finished by the given by the given

datedateTail Area Tail Area = .1230= .1230

Area = .3770Area = .3770Area left Area left of y-axis = of y-axis = .50.50 Probability =

.5000 - 3770

=.1230 or 12.3%

Page 58: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Apply z formula to critical path

0.396.67

weeks93 weeks40z

Use Standard Normal Table (Appendix B) to answer probabilistic questions, such as

Question 2: What is the probability of completing project (along critical path) within 40 weeks?

Probability = .6517 = 65.17%

Question 3: By how many weeks are we 99% sure of completing project (along critical path)?

6.67

weeks93D2.33 T DT = 45.02 weeks

Page 59: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 3, #4-8 Ch 16:

Activity Optimistic time Most likely time Pessimistic time Expected time Variance

A 3 6 9 6.00 1.00

B 3 5 7 5.00 0.44

C 4 7 12 7.33 1.78

D 4 8 10 7.67 1.00

E 5 10 16 10.17 3.36

F 3 4 5 4.00 0.11

G 3 6 8 5.83 0.69

H 5 6 10 6.50 0.69

I 5 8 11 8.00 1.00

J 3 3 3 3.00 0.00

Page 60: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 3, #4-#8 Ch 16:

A(6)

B(5) D(7.67)

F(4)

C(7.33) E(10.17) G(5.83

)

H(6.5)

I(8)

J(3)

Page 61: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 3, #4-#8 Ch 16:

A(6)

B(5) D(7.67)

F(4)

C(7.33) E(10.17) G(5.83

)

H(6.5)

I(8)

J(3)

length =32.17

Page 62: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 3, #4-#8 Ch 16:

A(6)

B(5) D(7.67)

F(4)

C(7.33) E(10.17) G(5.83

)

H(6.5)

I(8)

J(3)

length = 35.50

Page 63: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 3, #4-#8 Ch 16:

A(6)

B(5) D(7.67)

F(4)

C(7.33) E(10.17) G(5.83

)

H(6.5)

I(8)

J(3)

length =37

Page 64: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 3, #4-#8 Ch 16:

A(6)

B(5) D(7.67)

F(4)

C(7.33) E(10.17) G(5.83

)

H(6.5)

I(8)

J(3)

length = 40.33 CRITICAL PATH

Page 65: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Example 3, #4-#8 Ch 16:

A(6)

B(5) D(7.67)

F(4)

C(7.33) E(10.17) G(5.83

)

H(6.5)

I(8)

J(3)

Path variance =1+1.78+3.36+0.69+1+0 = 7.83

Page 66: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Apply z formula to critical path

-0.837.83

weeks33.40 weeks38z

Use Standard Normal Table (Appendix B) to answer probabilistic questions, such as

Question 1: What is the probability of completing project (along critical path) within 38 weeks?

Page 67: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Probability of completion by DT=38

Z = -0.83Z = -0.83 zz00

Project finished Project finished by the given by the given

datedateTail Area Tail Area = .2033= .2033

Area = .2967Area = .2967Area left Area left of y-axis = of y-axis = .50.50 Probability =

.5000 - 2967

=.2033 or 20.33%

Page 68: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Apply z formula to critical path

0.5957.83

weeks33.40 weeks42z

Use Standard Normal Table (Appendix B) to answer probabilistic questions, such as

Question 2: What is the probability of completing project (along critical path) within 42 weeks?

Probability = .2257+.5000 = .7257 = 72.57%

Page 69: © Wiley 2010 Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 3 th Edition © Wiley 2010 PowerPoint Presentation by

© Wiley 2010

Apply z formula to critical path

Use Standard Normal Table (Appendix B) to answer probabilistic questions, such as

Question 3: By how many weeks are we 99% sure of completing project (along critical path)?

7.83

weeks33.40D2.33 T

DT = 46.85 weeks