30
District of Columbia Public Schools | 1200 First Street, NE | Washington, DC 20002 | T 202.442.4800 | F 202.442.5517 | www .k12.dc.us Murch Community Meeting December 17, 2015

| dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

District of Columbia Public Schools | 1200 First Street, NE | Washington, DC 20002 | T 202.442.4800 | F 202.442.5517 | www.k12.dc.us

MurchCommunity Meeting

December 17, 2015

Page 2: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Agenda

DCPS | OCOO

2

o Introductions / “Rules of the Road”

o Welcome from Principal Cebrzynski

o Project Overview & Builder Announcement

o Murch Swing Space Discussion (Q&A after eachscenario)

o Next Steps

o Q&A

Page 3: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Rules of the Road

DCPS | OCOO

3

o CELLPHONES OFF OR ON VIBRATE

o RESTROOMS

o RESPECT OPINIONS OF OTHERS

o THE MEETING WILL RUN FROM 6PM TO 8PM

o Q&A WILL BE TAKEN AT THE END OF SWING SCENARIO

o Each speaker will be given 30 seconds

o Comments / Questions will be documented

Page 4: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Opening Remarks from Principal C

DCPS | OCOO

4

Page 5: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Project Overview

DCPS | OCOO

5

Project: Murch ES

Start Date: June 2016

Students Occupy Building: August 2018

Budget: FY16: $30.4 million | FY17: $32.756 million | Total: $68,295,000 (incudes previous balance)

Architects: R. McGhee and Associates / Hord Coplan Macht

Design Builder: MCN Build

- Rose Reno Modernization

- Powell ES Modernization

- Hyde-Addison ES Modernization

- Langdon ES Phase I Modernization

- Several others…

Page 6: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Swing Space Program Criteria

DCPS | OCOO

6

o 35 Classrooms

o Administrative space/ Welcome Center

o Gym/Cafeteria space

o Kitchen space

o Nurse space

o Outdoor play space

o Pick-up/Drop-off

o Safe location (i.e. able to utilize DCPS security protocols)

o Delivery access

o ADA considerations

o DCPS IT Infrastructure

o Able to accommodate the above for 2 years

o Close to Murch ES

o Access to parking

Page 7: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Overarching Considerations

DCPS | OCOO

7

o Transportation Logistics

o Parking Availability

o Play Space Availability

o Financial Cost

o Safety

o Impact on Instruction

o Proximity to Murch

o Community Impact

Page 8: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Swing Space Sites Analyzed by RFS

DCPS | OCOO

8

Intelstat Building – only response to RFS received; lease and tenant improvements; cost prohibitive

Fannie Mae – tenants will not vacate until 2017

American University – building and land owner would not grant lease

Howard University Law School – building in extremely poor condition; only 25,000 sf; lack of play space

Fillmore School – building and land owner would not grant lease

Wesley Theological Seminary – building and land owner would not grant lease

• Christ Church of Washington – building and land owner would not grant lease

• Jackson School Art Center – building and land owner would not grant lease

• 4001 Brandywine St NW (Partially empty office building) – building and land owner would not grant lease

• 5252 Wisconsin Ave NW (Partially empty office building) – 37,000 sf of retail space, mostly below grade; no natural light

DGS has be evaluating multiple swing space options for Murch. The DGS Portfolio team issued a Request for Space (RFS) for private buildings to express interest in leasing property to DCPS.

4 scenarios remain under consideration: On Site at Murch, Split Between Murch/Capital Memorial Church, Lafayette, and UDC.

Page 9: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 1: On Site at Murch

DCPS | OCOO

9

Insert On Site Images

Page 10: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 1: On Site at Murch

DCPS | OCOO

10

Page 11: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 1: On Site at Murch

DCPS | OCOO

11

Page 12: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 1: On Site at Murch

DCPS | OCOO

12

Page 13: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 1: On Site at Murch

DCPS | OCOO

13

Page 14: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 1: On Site at Murch

Estimated Cost: $2.5M

DCPS | OCOO

14

Pros

Students remain in MurchCommunity

Student population remains together

Estimated to be the cheapest Option

Cons

Students next to active construction site (noise, dust, etc)

Multiple moves at different phases of construction.

Additional construction traffic will make pick-up and drop off difficult.

Reduced play space

Adds restrictions to the builder (location, timing)

Next Steps – Scenario 1

Evaluate laydown areas, trailer placement, and phasing with builder.

Evaluate traffic impact

Evaluate feedback from Murch community

If selected, work with the school and the SIT on program layout.

Page 15: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 2: Split Option

DCPS | OCOO

15

BRANDYWINE ST NW

Forest Hills Playground

Capital Memorial Church

Page 16: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 2: Split Option

DCPS | OCOO

16

Page 17: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 2: Split Option

DCPS | OCOO

17

Page 18: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 2: Split Option

DCPS | OCOO

18

Page 19: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 2: Split Option

DCPS | OCOO

19

Page 20: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 2: Split Option

DCPS | OCOO

20

Page 21: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 2: Split Option

Estimated Cost: $3.5M

DCPS | OCOO

21

Pros

Moves trailers further away from construction zone.

Reduced programmatic movement.

Reduces the number of students at pick-up and drop-off

Capital Memorial Church is 0.4 mi away

Cons

Creates logistical challenge for staff and families.

Challenging for “Specials” teachers.

School community disconnected.

Many students still near construction zone.

Potential limitations in the church. Restrictions on room set-up.

Relies on street parking for staff at Church

Next Steps – Scenario 2 Evaluate programmatic and play space

impacts (recess)

Continue dialog with Capital Memorial Church and DPR

Evaluate feedback from Murch community

Page 22: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 3: Lafayette

DCPS | OCOO

22

Students would utilize the trailers at Lafayette ES for School Years 16-17 & 17-18.

Page 23: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 3: Lafayette Trailers

Estimated Cost: $4.5M

DCPS | OCOO

23

Pros

Large enough to fit entire Murchstudent body.

Complex already constructed.

In close proximity to Murch.

Cons

Increased traffic, especially during drop off and pick up. Safety concern.

Limited play space

Field would be off line for 2+ years.

Lafayette 5-12 year old playground would not be finished for 2+ years.

DPR equipment would have to be used by both schools. Tough to coordinate recess.

Concerns with overuse of DPR equipment.

Emergency evacuation procedures for 2 schools would have to be evaluated.

Staff parking limited to the street.

Utility capacity needs to be evaluated.

Impact on Lafayette community.

Next Steps Evaluate traffic impact (drop off/pick up)

Evaluate programmatic and play space impacts (recess)

Evaluate feedback from Murch & Lafayette communities

Page 24: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 4: UDC

DCPS | OCOO

24

Trailers would be constructed on the UDC field and used for School Year 16-17 & 17-18.

Page 25: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 4: UDC

DCPS | OCOO

25Note: SAMPLE “TEST FIT”. SUBJECT TO CHANGE

Trailers would be constructed on the UDC field and used for School Year 16-17 & 17-18.

Page 26: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Scenario 4: UDC

Estimated Cost: $6M

DCPS | OCOO

26

Pros

Large enough to fit the entire Murch student body – no mid-year moves required.

Away from active construction.

Access to play equipment and field.

In close proximity to Murch.

Cons

Elementary students on a College campus.

Limited pick up and drop off. Needs further evaluation.

Estimated to be the most expensive option.

Teacher and Visitor parking needs further evaluation.

Next Steps

Continue conversations with UDC & State Department

Evaluate traffic impact and traffic management requirements

Evaluate feedback from Murch community

If selected, work with the school and the SIT on program layout.

Page 27: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Next Steps

DCPS | OCOO

27

o DCPS/DGS will post summary of meeting notes by 12/23/15

o Community can submit questions / comments until 12/31/15

o DCPS/DGS will issue a summary of responses by 1/6/15

o DCPS will evaluate each option taking into consideration communityfeedback

o DCPS Senior Leadership will make a decision by 1/12/16

Page 28: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

How to Submit Comments

DCPS | OCOO

28

o Questions / Comments are being documented tonight.

o Comments can be submitted by 12/31/15 to:

o Email: [email protected]

o Murch Swing Space Survey: http://goo.gl/forms/UgPiIrMte8

o r/YQYBVMB

o Comment Cards (Collected at the end of the meeting)

Page 29: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Questions & Answers

DCPS | OCOO

29

Page 30: | dcps - Murch Community Meeting December 17, 2015 · 2015. 12. 21. · o DCPS/DGS will post summary of meeting notes by 12/23/15 o Community can submit questions / comments until

Contact Information

DCPS | OCOO

30

Kenneth Diggs, DGS Director of Communications

[email protected]

202-580-9361