© Ameresco, Inc. 2012, All Rights Reserved

Oconto FallsSchool District

September 10, 2012

Energy Savings Performance

Contract Update

© Ameresco, Inc. 2012, All Rights Reserved

Ameresco Presentation Information

2

Project Status

Financing Timeline

Timeline̶� Abrams Bells/PA System̶� High School Old Gym

Next Step

© Ameresco, Inc. 2012, All Rights Reserved

3

Project Summary

Ameresco Project Size……..………….…………….. $ 2.7MUtility Rebates………..….................................. $ 43KGuaranteed Energy & Operational Savings… $ 137K Per Year

Funding Source 100% Self-Funded, no out of pocket costs Annual Savings Funds Project Financed by Low Bond Rate – Combine Project Finance w/District Refinance Combination will benefit existing Rate Payers w/Tax Reduction

Facility Improvements Lighting retrofits & controls Water retrofits Building Envelope Window Film (exterior low-e) Building Automation & Digital Control IT Solutions and Printing Savings OFHS - Domestic Water Heater

Replacement OFHS – Electrical Transformer Upgrade OFES - Partial Boiler Plant Upgrade &

Domestic Water Replacement

HS & WMS Kitchen Modifications High School Roofing – Old Gym WMS – Domestic Water Replacement /

Expansion Abrams & OFES, Bell / PA System

Replacement OFES – Window Replacement (Phase I) Abrams – Boiler Plant Upgrade District Wide – Exterior Wall

Restoration(Does not include HS)

© Ameresco, Inc. 2012, All Rights Reserved

4

Project Status

Milestones DATES

Board Approved Resolution for Financing Aug 20Published- Board Notice of Intent to Borrow Aug 29

Petition Period Expiration Sept 29

Board – Final Action for Bond Sale Oct 9Project Financing Closing Dec 3Construction Kickoff meeting Oct X

© Ameresco, Inc. 2012, All Rights Reserved

5

Timeline

Projected Activity Estimated Date

Contract Signature Complete

- FIM Abrams Bell/PA System Upgrade Sept 11th

- High School (Old Gym) Roofing Replacement Late October

Project Financing December 2012

Subcontractor Award/Contract November 2012

Construction Start December 2013

Project/Construction Management December 2012- July 2013

Project Completion July 2013

District Project Completion Acceptance July/August 2013

Utility Rebate Applications August 2013

Post Construction Savings Measurement and Verification

August – September 2013

© Ameresco, Inc. 2012, All Rights Reserved

Preliminary Timeline

6

Technical

OCONTO FALLS SCHOOLS – 2012/2013 ENERGY EFFICIENCY UPGRADES

PRELIMINARY PROJECT TIMELINE Project Action Item Project Timeline

Project kick-off meeting October, 2012

Roof replacement plan and specification preparation August 6 - 24, 2012

Bid Reviews, Qualifications & Contractor Selections of all other FIMs December 11 – December 24, 2012

Roof bids due & Issue all Sub-contracts September 11 - 18, 2012

Re-roof construction (materials & weather dependent) October 11 – October 26, 2012 (flashing to follow in Nov)

IT Improvements December 24, 2012 – February 25, 2013

Kitchen Modifications January 3, 2012 – January 31, 2013

Water Conservation January 3, 2012 – April 29, 2013

Lighting Improvements January 3, 2012 – May 26, 2013

BAS Improvements January 3, 2012 – May 31, 2013

OFES Alarm Bells September 10 – September 11, 2013

Building Envelope March 4 – April 26, 2013

HS Domestic Hot Water Replacement February 4 – March 22, 2013

HS Transformers February 4 – March 22, 2013

WMS Domestic Hot Water Replacement February 4 – March 22, 2013

WMS Urinal Replacements February 4 – March 22, 2013

Window Film April 15, 2013 – May 31, 2013

Wall Restoration April 15, 2013 – June 28, 2013

OFES Boiler Plant & Water Heater Replacements April 15, 2013 – June 28, 2013

OFES Window Replacements April 15, 2013 – June 28, 2013

ABES Boiler Plant Replacement April 15, 2013 – June 28, 2013

Punchlist/Substantial Completion June 28, 2013

Final Completion & Verification July 26, 2013

© Ameresco, Inc. 2012, All Rights Reserved

7

Project Adjustments

Superintendent Directed Adjustments1. Abrams Bell/PA system

2. New Path – Lighting Upgrade removala) $2,908 - project cost reductionb) District leased property – utilities included in lease

3. IT Scope Modifications

4. Other??? ….TBD

© Ameresco, Inc. 2012, All Rights Reserved

Next Steps

8

School Board resolution final project financing Ameresco to complete the Abrams Elementary School

Bell/PA system upgrade upon materials delivery(this week)

Ameresco Project Manager Introduction (October Board Meeting)

High School (Old Gym) Roofing Design work underway for (Possible October construction)

Project kickoff meeting once project financing has closed (October)

© Ameresco, Inc. 2012, All Rights Reserved

AMERESCO Information and Resources

9

Kent WolfBusiness Development Manager

952.942.5142 ext. 4690Cell: 612.804.6274

Ameresco-Midwest Region9855 West 78th Street, Suite 310

Eden Prairie, MN [email protected]

Thank You

Please visit our website: www.ameresco.com

Services Press Releases Case Studies

Please Google “Ameresco” Daily for more information