Upload
sankalp-chandel
View
2.561
Download
0
Embed Size (px)
Citation preview
1.1 INITIALLY THE SITE IS CLEARED
1.3AFTER THAT ANY PERMANENT OBJECT WITHIN THE SITE
IS CONSIDERED AS THE REFERENCE POINT.
1.3THEN FROM THIS REFFERENCE POINT BASE LINE IS MADE.
1.4 FINALLY FROM THE BASE LINE REST ALL THE REQUIRED
LINES ARE MEASURED & CREATED BY SEEING AT THE
DRAWINGS.
1.5 THE MARKING IS DONE BY THIN THREAD.
1.6 THE SETTING OUT IS ALSO DONE USING THEODOLITE
FOR
BETTER ACCURACY. But setting out still continuous when the columns are to be casted just after the P.C.C. layers.Here marking of the columns are made.In case of right angel to be marked 3,4,5 method can be used.
SETTING OUT
2.1 INITIALLY THE ALL THE EXCAVATION PITS ARE BEING
MARKED AS PER THE DRAWINGS.
2.2 ROCKS BELOW THE PITS ARE CRACKED BY
CONTROLLED EXPLOSION USING MACHINE.
2.3 THEN THE WORKERS USING CHISEL & HAMMER
BREAKS THE ROCKS INTO SMALL SIZE SO THAT IT
COULD BE EASILY TRANSPORTED OUT.
2.4 IF THERE IS SOIL IN THE SITE THEN EXCAVATED IS
DONE USING SPADE, PICK ,AXE OR JCB .
EXCAVATION
3.1 FIRSTLY, ON THE EXCAVATED AREA SAND FILLING
OF ABOUT 6 INCHES THICK IS PROVIDED.
3.2 AFTER THAT A LAYER OF FLAT BRICK OR METAL
SOLING IS PROVIDED, NOW THE BASE IS READY.
3.3 ONCE THE BASE IS READY NOW P.C.C LAYER
IS MADE.
3.4NOW ABOVE THE P.C.C LAYER THE
REINFORCEMENT
FOR THE FOUNDATION ARE PLACED
3.5 FINALLY CONCRETE IS PLACED ABOVE THIS
REINFORCEMENT UPTO COLUMN SHOES.
COLUMN SHOES
CONCRETE BLOCK
After the p.c.c. the column position is marked accurately by using the rope & the plumb bob.
FOUNDATION
4.1 INITIALLY, A TEMPORARY SETUP IS
MADE WITHIN THE SITE WHERE THE
REINFORCEMENT STEEL IS
BROUGHT TO PROPER SHAPE BEFOE
BRINGING IT FOR INSTALLATION.
4.2 NOW ON THE SETUP BARS ARE
BROUGHT, MEASURED & VARIOUS
POINTS ARE MARKED.
4.3 THEN ACCORDING TO THE
STRUCTURAL DRAWING BARS ARE
BEND BY FIXING THE BAR IN THE
SETUP & TWISTING THE BAR BY
HOOK.
4.4 VARIOUS ANGELS ARE THUS
PRODUCED IN THE BAR .
NOTE :
THE STEEL BARS USED FOR REINFORCEMENT MUST BE FREE FROM UNWANTED BENTS AND CURVES.
BAR BENDING
5.1 INITIALLY, THE FORMWORKS ARE
MADE .
5.2 FIRSTLY, OIL IS APPLIED ON THE
SURFACE OF THE FORM BOARDS.
5.4 THEN SMALL BLOCKS OF WIDTH
EQUAL TO CLEAR COVER ARE TIED TO
THE REINFORCEMENT BARS.
THESE BLOCKS ENSURES THE CLEAR
COVER WIDTH.
5.3 AFTER THAT FORM BOARD ARE SET AS
REQUIRED FOR THE CASTING .
5.5 FINALLY, THESE FORMS ARE TIES TO
ADJACENT SIDES BY NUT & BOLT.
5.6 ALSO IT IS ANCHORED TO THE
GROUND
USING STEEL OR WOODEN STRUTS.
FORM WORK
6.1 ONCE THE FORMWORK IS READY, THE INTERIOR
DIMENSIONS OF THE FORMWORK SHOULD MATCHES THE
DIMENSION OF THE COLUMN PROVIDED IN THE DRAWING.
6.2AFTER THAT CONCRETE IS POURED, COMPACTION IS
DONE USING VIBRATORS OR MS BAR (MANUALLY). CARE
SHOULD BE TAKEN TO AVOID SEGREGATION AND
BLEEDING.
6.3 THEN THE FORMWORKS ARE REMOVED WITHIN 2 -3
DAYS & CURING IS DONE.
6.4 FOR CURING GUNNY BAGS ARE USED WHICH ARE
WRAPPED AROUND THE COLUMN. THESE GUNNY BAGS
ARE KEPT WET BY SPRINKLING WATER AT REGULAR
INTERVALS TO PROVIDE THE MOISTURE REQUIRED
DURING THE
CURING OF CONCRETE.
6.5 CURING SHOULD CARRY FOR 3 - 4 WEEKS.
Stripping of form ( in site ) 1 day ( recommended) 2-3 daysCuring of column (in site) 20 days (recommended) 21 days.
COLUMN CASTING
7.1 STEPS INVOLVED IN BRICK WORKS
7.1.1 INITIALLY MARKING IS DONE USING STRING WHICH GENERALLY
DEFINES OUTER TOP EDGE OF THE BRICK LAYER TO BE
CONSTRUCTED.
7.1.2 AFTER THAT BRICKS ARE SOAKED IN WATER.
7.1.3 THEN A LAYER OF MORTAR IS LAID & ABOVE THAT BRICKS
ARE LAID & IS SLIGHTLY PRESSED TO ENSURE ADHESION.
7.1.4 AT SOME EQUAL VERTICALLY INTERVALS (GENERALLY IN EVERY
4 COURSE) A THIN IRON SHEET OF WIDTH OF 1 CMS ARE ALSO
INSTALLED TO PROVIDE REINFORCEMENTS.
7.1.5 VERTICAL ALIGNMENT OF WALLS IS CHECKED IN EVERY 5-6
COURSES OF BRICK BY PLUMBING BOB.
7.2 STEPS INVOLVED IN PLASTERING OF WALLS
7.2.1 INITIALLY THE WALLS ARE WATERED & MADE READY FOR
PLASTERING.
7.2.2 AFTER THAT A THIN PASTE OF WATER CEMENT IS APPLIED OVER
THE BRICK WORKS TO ENHANCE GRIP BETWEEN BRICK WORK
& PLASTERS.
7.2.3 THEN PLASTER OF ABOUT 0.5 INCH THICK IS APPLIED OVER
WALLS.
7.2.4 FINALLY THE WALLS ARE READY FOR THE COLOUR & OTHER
FINISHING WORKS.
Plastering of ceiling is done in the similar way but the plaster used are of higher grade . in the roof slabs chipping is done to enhance griping of plaster with the slab.
NOTE :
•Plastering grades 1: 6 or 1:5 for interior walls.•Pastering grade for exterior walls 1: 4•Plastering grade for ceiling 1: 3
PLASTERING
FLOORING CAN BE DIVIDED INTO TWO DIFFERENT TYPES8.1 FLOORING AT GROUND LEVEL8.2 FLOORING ON R.C.C. SLAB.
8.1 STEPS INVOLVED IN FINISH FLOORING AT GROUND LEVEL 8.1.1 THE ACTUAL GROUND LEVEL IS HAMMERED & IS MADE HARD WHICH IS THEN TREATED WITH PESTICIDE IF REQUIRED IN THE SITE. 8.1.2 AFTER THAT A LAYER OF SAND OR STONE POWDER IS APPLIED WHICH IS GENERALLY 6 INCHES THICK. 8.1.3 NOW THIS LAYER IS HARDENED & IS LEVELED BY WATERING & HAMMERING. 8.1.4 FINALLY THE R.C.C SLAB IS CASTED IF THE SITE HAS HIGH WATER TABLE OR ELSE BRICK / METAL SOLING IS DONE WITH MORTAR LAYER ABOVE IT. 8.1.5 THEN LEVELS OF FINISHED FLOORS ARE BEING MARKED WHICH ACTS AS CHECK POINTS AT VARIOUS POINTS INSIDE THE BUILDING. 8.1.6 FINALLY A LAYER OF MIXTURE OF CEMENT & SAND (RATIO OF 1: 6) IS CONSTRUCTED. 8.1.7 ONCE THE ABOVE LAYER IS MADE & THE REQUIRED LEVELING IS ACHIEVED CEMENT-WATER PASTE IS APPLIED. 8.1.8 FINALLY THE TILES ARE CUT TO REQUIRED DIMENSION & ARE FITTED OVER THE CEMENT LAYER (WHERE CEMENT WATER PASTE ACTS AS ADHESION PASTE . 8.1.9 ATLAS THE TILES ARE HAMMERED IN ORDER TO ENHANCE ADHESION & TO BRING TILES IN ACCURATE POSITION.8.2 FLOORING ON R.C.C. SLAB. THE PROCEDURE ARE SIMILAR FROM POINT 8.1.5
The mix of plaster (masala) used for the plastering is 1: 8)
FLOORING
9.1 INITIALLY THE FORMWORKS ARE ARRANGED
WHICH ARE RECTANGULAR G.I. SHEETS WITH AT
SECTION AT THE ENDS. THIS IS SUPPORTED BY
TELESCOPIC PROPS .
9.2 BUT FORMWORK FOR THE BEAM ALSO HAS
VERTICAL BOARDS.
9.3 AFTER THAT THE REINFORCEMENTS ARE
ARRANGED AS SPECIFIED IN THE DRAWINGS
9.4 THE REINFORCEMENTS ARE RAISED TO CERTAIN
HEIGHT AS SPECIFIED IN THE DRAWINGS WHICH
IS
CLEAR COVER & RAISING IS DONE BY
PLACING CONCRETE BLOCK IN BETWEEN
REINFORCEMENT &FORMWORKS.
9.5 FOR SLABS THE ELECTRICAL P.V.C. PIPES ARE
LAID
& FINALLY CONCRETE IS POURED.
AFTER 3 DAYS SLAB SOFFIT IS TAKEN OFF WHERE AS
PROPS ARE TAKEN OFF AFTER 7 DAYS.
FINALLY CURING IS DONE BY PONDING.
SLAB CASTING
10.1 THE ELECTRICAL MARKING IS DONE BASED ON THE ELECTRICAL
MARKING DRAWING ISSUED BY THE ARCHITECT.
10.2 ONCE THE MARKING IS DONE GROVES ARE CREATED IN WALLS BY
CHIPPING WALLS. THE GROVES ARE ABOUT ¾INCH DEEP WHICH
ACCOMMODATES P.V.C PIPES FOR REQUIRED FOR WIRING.
10.3 WHERE AS IN R.C.C. ROOFS WHILE CASTING ;ELECTRICAL CONDUITS
ARE PLACED.
10.4 THE PIPES ARE ANCHORED IN THE WALL BY STEEL HOOKS & THE
PLASTERING IS DONE ABOVE THESE PIPE ABOVE CHICKEN MESH WHICH
ENSURES BETTER GRIP FOR PLASTERING.
10.5 FINALLY ONCE PAINTING ARE DONE THEN SWITCH BOARD ARE FIXED.
ELECRTIFICATION
11.1 INITIALLY ALL THE IMPORTANT PLUMBING POINTS ARE MARKED AS
PER THE DRAWING ISSUED BY THE ARCHITECT.
11.2 AFTER THAT WALLS ARE CHIPPED TO CREATE A GROVE SO THAT P.V.C
PIPES OF GIVEN THICKNESS COULD BE ACCOMMODATED INSIDE THE
GROVE MADE.
11.3THEN PIPES ARE LAID & IS ANCHORED BY THICK STEEL U SHAPE
HOOKS.
11.4IN TOILETS SPECIALLY FOR WATER CLOSET THE SLAB ARE SUNKEN. THIS
IS THE PLACE WHERE THE TRAPS ARE INSTALLED.
11.5AT LAST THE SUNKEN SLAB IS THEN FILLED WITH COARSE AGGREGATE
AND SOIL AND RAMMED PROPERLY, TO FORM THE BASE FOR THE
FLOORING.
11.6FINALLY, ALL GROVES ARE SEALED BY PLASTERS ONLY CERTAIN PARTS ARE
LEFT OUT WHERE FURTHER PIPE FITTINGS LIKE SHOWER, TAP ETC ARE
FIXED.
11.7EXPOSE PIPE FITTINGS ARE FITTED TO WALL BY “U” SHAPED HOOKS
WHICH ARE FIXED TO WALLS USING NAILS.
PLUMBING
12.2 THEN VARIOUS POINTS ARE MARKED ON THE WALLS & DRILLING IS
DONE. SOMETIMES FRAME IS FIXED TO WALL BY ANGEL PLATE IN THE
EMPTY AREA LEFT FOR THE OPENING
12.3THEN ALUMINIUM WINDOW FRAMES ARE SCREWED INTO THESE HOLES.
12.4AFTER THAT WINDOW PANELS ARE CONSTRUCTED BY CONNECTING
DIFFERENT ALUMINUM SECTION BY SCREWS.
12.5AT LAST GLASS ARE FIXED TO THE PANELS; P.V.C. PUTTY ARE USED TO
KEEP GLASS HOLD TIGHT TO THE WINDOW PANELS.
12.6WHEN THE WINDOW PANELS ARE CREATED VARIOUS HOLES , GROVES
ARE CREATED WHICH HELPS IN FIXING OF ALUMINUM CHANNELS TO
OTHER CHANNELS & RAILS.
12.7FINALLY THE WINDOW PANELS ARE FIXED INTO THE FRAMES.
WINDOW FIXING
13.1 AFTER PLASTERING OF WALL INTERIOR FINISH IS DONE: HERE IT IS DONE
BY P.O.P
13.2 THE PLASTERED WALLS IS IDEAL FOR P.O.P AS IT IS ROUGH.
13.3INITIALLY MIXTURE OF P.O.P IS MADE WITH WATER & SPECIAL CARE IS
TAKEN AS P.O.P TENDS TO LOSE WATER QUICKLY & HARDENS QUICKLY.
13.4THEN BY USE OF TWO THIN RECTANGULAR G.I. SHEET P.O.P. IS APPLIED
( GENERALLY CALLED BLADES).
13.5NOW THE WALL IS READY FOR PAINTING BUT BEFORE THAT COAT OF
PRIMER & WEATHER COAT (PUTTY )IS APPLIED.
INTERIOR FINISH
14.1 INITIALLY ANGEL CLAMPS ARE FIXED TO THE EXTERIOR WALL WHICH IS
DONE BY DRILLING HOLES IN WALLS & THEN SCREWING.
14.2 AFTER THAT CLAMPS ARE SCREWED TO THE VERTICAL METAL SECTION &
THEN HORIZONTAL METAL CHANNELS ARE SCREWED TO VERTICAL
CHANNELS BY DRILLING HOLES IN METAL CHANNELS & THEN SCREWING IT.
14.3 NOW THE ALUMINIUM PANELS ARE SCREWED TO THESE HORIZONTAL &
VERTICAL METAL CHANNELS BY DRILLING HOLES IN METAL CHANNELS &
THEN SCREWING IT.
14.4FINALLY THE PLASTIC COVER ON THE ALUMINIUM PANELS ARE TAKEN
OFF.
EXTERIOR FINISH
I. INITIALLY THE METAL CHANNELS ARE FIXED ON TO THE CEILING BY MEANS OF
SCREW; THESE SUSPENDERS SUPPORT THE WHOLE SKELETON OF THE FALSE
CEILING.
II. NOW HORIZONTAL MEMBERS OF THE METAL CHANNELS ARE ATTACHED TO THE
VERTICAL BY SCREWS.
III. ONCE THE SKELETON IS READY THEN GYPSUM BOARDS OR ACOUSTICS PANELS ARE
ATTACHED TO THE SKELETON WITH THE HELP OF SCREWS .
IV. FINALLY THE SPACE BETWEEN THE TWO GYPSUM BOARD IS SEALED BY PLASTER OF
PARIS.
V. THE SPACE FOR ELECTRICAL FITTINGS ARE LEFT VACANT SO THAT ELECTRICAL
FITTINGS LIKE LIGHTS COULD BE FIXED.
VI. THE SPACE BETWEEN THE ROOF SLAB & FALSE CEILING CARRIES ALL AIR
CONDITIONING DUCTS & ELECTRICAL WIRINGS.
FALSE ROOF
INNOVATIVE DETAILS
I. THE COLOUM IS PRESENT IN THE ENTRANCE OF STAPATI, CALICUT
II. IT IS APPROX 300 CMS TALL.III. THE STEEL COLUMN IS PUT INSIDE THE
BRANCH OF A COCONUT TREE.IV. THIS IS DONE BY MAKING HOLE IN THE
COCONUT BRANCH MANUALLY BY THE CARPENTERS OF STAPATI.
V. FINALLY THE COCONUT BRANCH IS BOLTED TO THE STEEL COLUMN IN BOTH THE END .
VI. EACH END HAS TWO BOLTS.
M.S ROD (as column)
COCONUT TREE BRANCH
Cross section of the column
L.S. of the colomnbolt
nut
Fixing details
SELF
I. The self is for the Fred Stuart showroom in Chennai.
II. This is designed by contour dakshin , Calicut.
III. The client wanted the interior to have very informal & innovative look for his showroom.
IV. Here the top & bottom wooden board are fixed to wall & floor respectively.
V. the middle boards are held in position by the knots tied rope passing through the boards.
VI. These knots makes the wooden board free to move in certain direction.
VII. These movement are created when the consumer tries to take clothes kept at the selfs. Hence making it a different feeling for the consumers.
Opaque coloured sheet
8 mm glass
L.E.D strip
L.E.D spot light
Metal case
Wooden beading (3cm x 2 cm)
I. THE LIGHTING ELEMENT IS FOR THE BAR TABLE OF ANANTA APARTMENTS IN MUMBAI BY CONTOUR DAKSHIN.
II. THE SIZE OF THE ELEMENT IS 150 X 90 CMS 2.
III. THERE ARE TWO SET OF LIGHTS LED SPOT LIGHT & LED STRIP.
IV. THE SPOT LIGHT IS USED WHILE MAKING THE DRINK & THE LED STRIPS COMES TO USE WHILE DRINKING TO GIVE A GOOD ENVIRONMENT.
LIGHTING ELEMENT
MECHANISM
I. THE LIGHTING ELEMENT IS PRESENT IN HOTEL ASMAN TOWER, CALICUT
II. THIS ELEMENT IS PLACED AT THE ENTRY WITH THE HOTEL NAME BOARD
III. THE LIGHTING IS DONE BY L.E.D STRIPS.
IV. THE LIGHT AFTER PASSING THROUGH TRANSPERENT GLASS FALLS TO THE STONE HENCE CREATING A GOOD LIGHTING EFFECT.
FRONT ELEVATION
IVORY P.V.C. BOARD
TRANSPERANT GLASS
SQUARE IRON BAR
PLYWOOD BOX
STONE ABOVE GLASS
L.E.D STRIP
IVORY P.V.C. BOARD
PLAN @ A-A’
SQUARE IRON BAR
PLYWOOD BOX
STONE ABOVE GLASS
L.E.D STRIP
IVORY P.V.C. BOARD TRANSPERANT GLASS
SECTION A-A’ METAL GLASS HOLDER
TRANSPARENT GLASS
PLYWOOD BOX
PLAN @ B-B’
LIGHTING FIXTURE AT ASMA TOWER
TRUSS ROOF
I. THE ROOF TRUSS IS DESIGNED BY CONTOUR DAKSHIN , CALICUT
II. THE ROOF WAS DESIGNED TO CAPTURE MAXIMUM VIEW OF THE MOUNTAINS OF OONTY.
III. ALSO THE ROOF BEING TIMBER GIVES AN TRADITION LOOK.ALSO THE TRUSS ACT AS DESIGN ELEMENT DURING NIGHT WHEN THE LIGHTS ARE ON.
CONCEPT BEHIND THE ROOF
CONCRETE BLOCKS
I. THE CONCRETE BLOCKS ARE USED IN THE HOTEL BURJ-AL – ARAB.
II. THIS IS USED BY THE ARCHITECT TONY WRIGHT TO MAKE THE BUILDING SAFE FROM THE TIDAL FORCE.
III. THE BLOCKS ARE VERY WELL TESTED IN THE LAB FOR AROUND 1 WEEK USING SIMILAR SCALE MODEL & PRODUCING
IV.A TIDAL WAVE WHICH IS HAS STRENGTH EQUAL TO HIGHEST TIDAL WAVE OCCURRED IN 100 YEARS.
VI.THE BLOCKS ARE DESIGNED IN SUCH A WAY THAT THE BLOCKS ACTS LIKE A SPONGE & ABSORBS ALL THE TIDAL FORCES.
VII.THE WATER TRIES TO REVOLVE INSIDE THE BLOCK WHICH DECREASES MOST OF ITS STRENGTH. HENCE MAKING THE BASE SAFE FOR THE HOTEL.