PRIMA RESIDENCES 243 QUEZON AVENUE, Q.C

August 23,2011

FIRST BALFOUR INC.

PRESENTATION OF SCAFFOLDING, PLATFORM & MASONRY WORKS

Page 2: PRESENTATION OF  SCAFFOLDING

CHB 1.2 METER HEIGHTCHB 1.2M

HEIGHT

SCAFFOLDINGW/ SAFETY CATCH FAN

Page 3: PRESENTATION OF  SCAFFOLDING

PRESENTATION OF SCAFFOLDING & PLATFORM

SCAFFOLDINGW/ SAFETY CATCH FAN

CHB 1.2 METER HEIGHT

SAFETY NET

Page 4: PRESENTATION OF  SCAFFOLDING

PRESENTATION OF SCAFFOLDING & PLATFORM

ANGLE BAR30X30X5mm. THK.

CATWALK

SAFETY NET

ANGLE BAR50X50X5mm. THK.

TOE BOARD

Page 5: PRESENTATION OF  SCAFFOLDING

PRESENTATION OF SCAFFOLDING & PLATFORM

ANGLE BAR30X30X5mm. THK.

TOE BOARD

ROUND BAR50 DIA. MM

Page 6: PRESENTATION OF  SCAFFOLDING

PRESENTATION OF SCAFFOLDING & PLATFORM

ROUND BAR50 DIA. MM

TOE BOARD

ANGLE BAR30X30X5mm. THK.

PREPARED BY: IRWIN O. GERMAN

Page 7: PRESENTATION OF  SCAFFOLDING

DETAILED OF SCAFFOLDING, PLATFORM & PERSPECTIVE

Page 8: PRESENTATION OF  SCAFFOLDING

DETAILED OF SCAFFOLDING, PLATFORM & PERSPECTIVE

Page 9: PRESENTATION OF  SCAFFOLDING

DETAILED OF SCAFFOLDING, PLATFORM & PERSPECTIVE

ROUND BAR50 DIA. MM

TOE BOARD

ANGLE BAR30X30X5mm. THK.

Page 10: PRESENTATION OF  SCAFFOLDING

3rd FLR.-4 th FLR- 3 STRONG FLOORS

NOV. - DEC.2011

Page 11: PRESENTATION OF  SCAFFOLDING

2th FLR- MEPF WORKS

NOV. - DEC.2011

Page 12: PRESENTATION OF  SCAFFOLDING

2nd FLR.-3 rd FLR- INTERIOR PARTITIONING

JAN. – FEB.2012

Page 13: PRESENTATION OF  SCAFFOLDING

5th FLR.-7 th FLR- 3 STRONG FLOORS

JAN. – FEB.2012

Page 14: PRESENTATION OF  SCAFFOLDING

5th FLR.-7 th FLR- 3 STRONG FLOORS, w/ SCAFFOLDING

JAN. – FEB.2012

Page 15: PRESENTATION OF  SCAFFOLDING

6th FLR.-8 th FLR- 3 STRONG FLOORS

JAN. – FEB.2012

Page 16: PRESENTATION OF  SCAFFOLDING

7th FLR.-9 th FLR- 3 STRONG FLOORS

JAN. – FEB.2012

Page 17: PRESENTATION OF  SCAFFOLDING

8th FLR.-10 th FLR- 3 STRONG FLOORS

FEB. – MAR.2012

Page 18: PRESENTATION OF  SCAFFOLDING

9th FLR.-11 th FLR- 3 STRONG FLOORS

MAR.2012

Page 19: PRESENTATION OF  SCAFFOLDING

10th FLR.-12 th FLR- 3 STRONG FLOORS

MAR.2012

Page 20: PRESENTATION OF  SCAFFOLDING

11th FLR.-12 th FLR- 2 STRONG FLOORS

MAR. – APR.2012

Page 21: PRESENTATION OF  SCAFFOLDING

ROOF DECKMEPF WORKS

APR.2012

PREPARED BY:IRWIN O. GERMAN

Page 22: PRESENTATION OF  SCAFFOLDING

LEVELExterior Walls

QUANTITY (SqM)

NO. OF MANPOWER

Start End

Roof Deck - Upper Roof Deck 2-Apr-12 17-Apr-12 224.79 36.00

12th Floor - Roof Deck 22-Mar-12 4-Apr-12 329.51 53.00

11th Floor - 12th Floor 12-Mar-12 24-Mar-12 329.51 53.00

10th Floor - 11th Floor 1-Mar-12 14-Mar-12 329.51 53.00

9th Floor - 10th Floor 20-Feb-12 3-Mar-12 329.51 53.00

8th Floor - 9th Floor 9-Feb-12 22-Feb-12 329.51 53.00

7th Floor - 8th Floor 1-Jan-12 11-Feb-12 329.51 53.00

6th Floor - 7th Floor 19-Jan-12 1-Feb-12 329.51 53.00

5th Floor - 6th Floor 9-Jan-12 21-Jan-12 329.51 53.00

4th Floor - 5th Floor 27-Dec-11 11-Jan-12 329.51 53.00

3rd Floor - 4th Floor 15-Dec-11 29-Dec-11 329.51 53.00

2nd Floor - 3rd Floor 5-Dec-11 17-Dec-11 389.57 62.00

Ground Floor - 2nd Floor 25-Nov-11 7-Dec-11 350.89 56.00

MASONRY WORKS – EXTERIOR WALLS