11
TW@ESI 1 st November 2015 Hope that you and all your families had a good weekend .. Bye bye October and welcome November !! The following is an update of what was achieved during the past week and a forecast of the next week I ASK YOU ALL ONCE AGAIN .. I need your help and co operation to make this work!! We need a special push at MDH (John and Shawn I need your help here), Panel Build (with Julians help), Clinton from installation (Clifton please assist!!) and Manuel (who is new- Am sure that Graziella will assist on this )

TW@ESI Update 1st November 2015

Embed Size (px)

Citation preview

TW@ESI1st November 2015Hope that you and all your families had a good weekend .. Bye bye October and welcome November !! The following is an update of what was achieved during the past week and a forecast of the next week

I ASK YOU ALL ONCE AGAIN .. I need your help and co operation to make this work!! We need a special push at MDH (John and Shawn I need your help here), Panel Build (with Julians help), Clinton from installation (Clifton please assist!!) and Manuel (who is new- Am sure that Graziella will assist on this )

Projects and deadlines• We are presently executing a number of fast track projects and I would like to

summarise the major ones them as follows:– 14_081 - Siggiewi Primary School BMS- 3rd fix installation completed by 1st week of

November 2015. Commissioning completed by 8th December 2015- we also had a number of large variations approved on this project

– 13_076 - MDH Block D Ext MAU- Panel termination completed at the earliest possible date and IO testing has commenced now- we need to monitor what is happening and what still needs to be done – And give feasible targets here.

– 15_008 - Aurobindo PH02 BMS- The panel has been delivered and assembled on site with everyones good will and effort. We need to plan the programming and development of the system which is now extremely urgent. We have the first phase of handover which is to be done by 13th November 2015

– 14_089_MGA_DAC_PA_VA – needs to be completed by 15th November 2015 – including PA-VA

– 13_070 SCM Lagoona – needs to be completely commissioned by 15th December 2015

DesignLast Week• Westin 7AHUs – completed Panel Design (target completion

6/11/2015)• Siggiewi - Armoured Cables lengths check• Life Sciences - Received feedback on Plan Drawings from ClintonNext Week• Life Sciences - chase Clifton for P&IDs feedback (if any)• Westin 7AHUs – Gather Material Required, release for quotes,

orders - from MF, Tridium, Scan (UPS), and Rittal (check stock for Vent Fans, Side Panels)

• Siggiewi - Implement SAA Various feedback• Intercontinental - Start on Points list, then P&IDs

Installation

• Last week we were focused on– ESI Premises– Life Sciences Commissioning– Hilton AHU Project and installation of cold room sensors– MAU Panel terminations and IO testing

• Next week– MGA DAC installation and commissioning – Life Sciences Commissioning– MAU Panel terminations

Panel Build• Next to be done is Siggiewi DDCs• Also we have to finish off the FM Environmental

panels

Mater Dei

• The team at MDH is working full blast to assist the MAU installation and a lot of effort is being done in order for ESI to succeed

• The team at Mater Dei are working hard to fill in the missing people and hopefully, by the month of November 2015, we should settle on our new complement.

Development and Commissioning• We have done large important steps on finishing off the Parliament we need to get

the documentation out of the way too to avoid us going time and time again on site

• We finalised on the DAC for FTIAS – well done to LVA and JPO on this- this week there is a further meeting on site to decide what has to be done with the emergency doors

• We now need to start installation and commission the 14_089_MGA_PA_DAC• The last issues on the DAC for SCM PH2• SCM PH2 needs also some attention on the tagging purchase order for the BMS-

CVA is to work on this• CVA Is also now working on the Hilton Hotel Guest room AHU project • The Bosch HSDK interface is being done and we will now need to work on the

documentation• The PLC/SCADA team have been working to progress the MAU software

development

Development and Commissioning• OTM urgent jobs and snags were also done in the last weeks• Aurobindo is another important and, now, fast track project the first

pjase now needs to be completed by 13th November 2015- The idea is to have the panel by last week of October 2015 and terminate and test and commission right after

• Another project that needs attention is CCA Villa ... We need to see to snags and convince the client on the system we have installed

• The Siggiewi Primary school project is an extremely urgent project which needs to be completed from 3rd fix by First week of November 2015 and commissioned by end of November 2015

• There is a lot of commissioning work to be done and we need to work efficiently to make the commissioning time as short as possible

• CCI was on ProWatch training this week in Germany

Sales and Business Development

• We have been working on Home automation offerings and quotes for variations for existing projects and an offer a customer experience centre

• We are working on a PLC solution for a Sterling Plant in Perugia and we have made an ELV offer for offices in Mriehel

Team ESI• I urge you all to follow this blog and keep up to date with what is happening at

ESI • Have you seen the article of ESI as Siemens Partner on times of Malta? Have

you seen this weeks presentation on the office energy profile• I await all your feedback on all the ESI discussions – without this feedback – this

group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

• Send me pictures of all your work and what you are up to , so that I may create some videos on this blog- Julian, Claudio, Clifton, Silvio, and Clinton.... Well done!!

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• HAVE A GOOD WEEK