Solar Power Production
Sourcing solar power generating equipment and producing a pollution free power at FIIB
Sangam Lalsivaraju# 138
Scope• The project facilitates power requirement only for the
FIIB campus• With the project facility daily 50KW energy to the
campus (on a sunny day)• The project will provide electricity for time of 25years
with regular maintenance• The project sources from solar energy only
Objectives• To enhancing the strategic agenda of the college
which is sustainability• To create renewable energy source to the organization
for day to day mechanical activities• To minimize the electricity and diesel expenses• To reduce the carbon foot print • To get a competitive advantage through this
sustainable business practice
MilestonesMilestones Deliverables Date
Approval from top management Project approval 09 Jan 2014
Finalizing on budgetOvercoming Financial
constraints 16 Jan 2014
Finding the supplier Found the supplier 23 Jan 2014
Negotiating and placing order Purchasing equipment 30 Jan 2014
Transportation Receiving equipment 07 Feb 2014
Installations Installations through skilled man power
21 Feb 2014
First phase of power production Power production 28 Feb 2014
Project WBS and activities
Major Activities:
1. Approval from the top management
2. Finalizing on the budget
3. Finding the supplier
4. Negotiating and placing the order
5. Transportation
6. Installation
7. Testing
Work break down structure
1. Approval from the top management
• Understanding the requirements
• Collecting the data
• Preparing and scheduling the presentation to top
management
• Waiting for the response
Contd..
2. Finalizing on the budget
• Negotiating on the budget
• Wait for the response
Contd…
3. Finding the supplier
• Searching for the suppliers on the Internet
• Finalizing the supplier from pool of suppliers
Contd…
4. Negotiating and placing the order
• Approaching the supplier
• Negotiating on the price, quality etc..
• Place the order
Contd…
5. Transportation
• Routing
• Communicating
• Receiving
Contd…6. Installation• Mounting• Welding• Cement work• Inverters installation• Electric work
Contd…7. Testing • Production testing
Effective time calculationActivities T
p(Days)T m T o T e( (T p+4*Tm +Te)/6
Approval from the top management
11 9 7 9
Finalizing on the budget
7 5 6 5.5
Finding the supplier 8 7 6 7
Negotiating and placing the order
10 7 6 7.3
Transportation 9 7 5 7
Installation 16 14 10 13.7
Testing 8 7 4 6.7
Critical Path
Data collection(5) Presentation(4) Negotiating on budget(5.5) Searching for supplier(5)
Finalizing the supplier(2)
Approaching the supplier(3) Negotiating(3) Place the order(1.3)
Order processing& Transportation(7)
Mounting(3) Welding(2) Cement work(4)
Testing(6.7)
Inverter installati
on(3)
CPM time=56.2 days
Off-Grid solution
Resource planningActivities Labo
urTechnicians
Materials
Approval from the top management 0 0 Stationery
Finalizing on the budget 0 0 Stationery
Finding the supplier 0 0 Internet, Telephone
Negotiating and placing the order 0 0 Internet, Telephone
Transportation 4 0 Truck, packaging material
Installation Mounting Inverter installation
Welding
Cement work
4
2
1
1
Iron rods, screws, solar panels
Cement etc
Testing 0 3 -
2 2 Inverters
2 1 Iron material etc
Budget• Transportation : 25k INR• Mono-crystalline PV solar panels(50KW) plus set : 50 lacs
INR• Labour: 14*4*450 = 25200• Technicians : 7*3*1000= 21000• Cement ,welding, wiring and stationery = 30000• Total estimated budget 51,01200 INR
Quality criterion• Reduces the diesel usage by 45% in 6months down
the line• Saves electricity expenses up to 50,000 P.A• Generates a power of 2 MW per 40Days
Project Risk• Electricity shortages during installations (S*O*D)=(8*5*6)=240• Budget Overrun• Quality issues• Delays