Test Concepts and Practices From Concept to Deliverable Presented by T. James LeDoux, Test Management Consultant 1 n Executive-level overview of quality assurance and test management practices and considerations

Software test management overview for managers

Embed Size (px)

DESCRIPTION

Software test management presentation given to the senior management of several Fortune 100 companies to aid them in planning their software development management efforts.

Citation preview

Page 1: Software test management overview for managers

Test Concepts and Practices

From Concept to DeliverablePresented by

T. James LeDoux,

Test Management Consultant

1

An Executive-level overview of quality assurance and test management practices and considerations

Page 2: Software test management overview for managers

Topics

• Differences between QA and Test• Goals of Testing• Phases / Levels of Testing• Types of Testing• Basic Concepts of Test Planning and

Creation• Pass/Fail Criteria (Discussion)

• Traps and Pitfalls (Discussion)

• Successful Completion (Discussion)

2

Page 3: Software test management overview for managers

Differences Between QA and Test

• QA– Focused on managing

organization-wide process for acceptance of upgrade

– Targets affected system– Performs by developing

management processes– Involves Quality Manager,

Quality Director or QA Manager

• Test– Focused on validating

level of confidence in upgrade

– Targets a Release– Performs from planned

script– Involves Test Engineer

or Test Manager

3

Page 4: Software test management overview for managers

Goals of Testing

• Increase Quality of the Upgrade Quality = Confidence

• Reduce risks to the system or business• Stabilize the system• Meet the needs of the Users• Determine capability of the system• Define monitoring requirement in

production

4

Page 5: Software test management overview for managers

Phases / Levels of TestingRequirements

Unit Tests

Test Plan

Test Scenarios

Performance Tests

String Tests

System Tests

UAT Tests

Integration Tests

Staging Tests

5

Page 6: Software test management overview for managers

Types of Testing

• Functional

• Security

• User

• Exception

• Etc.

6

Page 7: Software test management overview for managers

System Tests

Unit Tests

String Tests

System Tests

Integration Tests

Functional Tests Security Tests Exception Tests

Developer System Testing

Test Group System Testing

7

Page 8: Software test management overview for managers

Performance Tests

Performance Tests

System Tests

UAT Tests

Staging Tests

Throughput Tests Stress TestsBenchmark Tests Load Tests

8

Page 9: Software test management overview for managers

User Tests

Performance Tests

System Tests

UAT Tests

Staging Tests

User Acceptance Tests Business Exception Tests

9

Page 10: Software test management overview for managers

Deployment Tests

Performance Tests

System Tests

UAT Tests

Staging Tests

Deployment TestsRelease Notes Test

10

Page 11: Software test management overview for managers

The Test Harness

• Acts as the initiator of the object’s task• Typically structured with three parts:

– Input data and form– Setup process– Output data handler

• Must also be capable of creating and determining exception responses

11

Page 12: Software test management overview for managers

Test Harness Example

Arithmetic AdderA + B = C

Method ARADD (A,B,C)

Input dataIteration A B

12345

Except 6Except 7

12457

21S

1378

12K8

Expected dataIteration C P/F

12345

Except 6Except 7

25

111319

ErrorError

PPPPPFF

12

Page 13: Software test management overview for managers

Test PlanPage 1

Describes purpose. Example: One of the primary goals of the Web To Compass project at Compassion International is to streamline the process of getting a web transaction from the web site (Compassion.com) to the Compass database. Currently, the web site and Compass are disconnected, and a series of manual and semi-automated processes are in place to facilitate this work.

1. Introduction1.1 Purpose

1.2 GoalsDescribes the goals of the testing.Example: This Test Plan for the Compassion W2C Release supports the following Goals:1. Defines the activities required to prepare for and conduct Unit, System, Load, and Performance Testing.2. Communicates to all responsible parties the testing strategy.

1.3 Test ScopeDescribes scope of testing. Example: Testing encompasses System, Load and Regression testing under a manual test process.

1.4 System OverviewDescribes the system layout along with a diagram

13

Page 14: Software test management overview for managers

Example of a System Overview Diagram

SQL 2000MSMQ Support

SQLServer

ExceptionWorkflow Database

App Server

BiztalkTracking

WorkflowExceptionHandler

Biztalk MessagingDatabase

Biztalk TrackingDatabase

NLB

IIS / ASP

Msg Broker

BiztalkMessaging

Inside Firewall

IIS / ASP

Test Controller(TC)

VirtualUser (VU)

Functional Test and Database Restore

Functional Test and Database Restore

Functional Test and Database Restore

Fun

ctio

nal T

est a

nd D

atab

ase

Res

tore

Fun

ctio

nal T

est

Sys

tem

and

Loa

d T

est

Sys

tem

and

Loa

d T

est

VU ControllerTest System

External to the PreProd System

14

Page 15: Software test management overview for managers

Test PlanPage 2

2.0 Test Strategy Overview (From Test Strategy document)

15

2.1 Purpose, 2.2 Approach2.3 Validation

Page 16: Software test management overview for managers

Test PlanPage 3

3.1 Unit/String Testing

• Unit/String Testing Environment• Test Data• Installation, Verification and Control• Unit/String Test to be Performed• Unit/String Test Logging and Reporting

3.1 Integration Testing• Integration Environment• Test Data• Installation, Verification and Control• Test Team Logistics• Logging and Reporting

3.0 Test Levels

Page 17: Software test management overview for managers

Test PlanPage 4

• System Test Environment• Test Data• Installation, Verification and Control• Test Team Logistics• System Test to be Performed• System Test Logging and Reporting• Defect Management• Quality Requirements and Metrics (see next slide)• Roles and Responsibilities

16

3.2 System Test

3.3 Performance Test

Page 18: Software test management overview for managers

Quality Requirements and Metrics Section

Entrance Criteria

• Test Plan completeo Test Cases completeo Test Procedures completeo Test Scenarios completeo Execution Schedule completeo Test data acquiredo User names, passwords and access rights issued

•Test environment ready

Exit Criteria

• Testing completed• Test results complete• Screen captures complete• Test logs up to date• Defects identified and reported or fixed

17

Page 19: Software test management overview for managers

Test PlanPage 5

4.0 Test Identification and Definition

18

• Requirements Testability Matrix• Functional Scenarios• Exception Scenarios• End-To-End

• Functional Test Cases• Test Cases not associated with a Use Case• Exception Tests• End-To-End

4.1 Test Scenarios

Page 20: Software test management overview for managers

Test PlanPage 6

4.2 Performance Test Scenarios

4.3 Regression Test Scenarios

4.4 Test Procedures

19

• Unit/String Test Schedule• Integration Test Schedule• System Test Schedule• Performance Test Schedule

• Manual Test Procedures• Automated Test Procedures

5.0 Test Schedule

Page 21: Software test management overview for managers

Test Case ExampleSection Description  

Procedure Name ABC1-TC100.0 Use Case 1 Happy Path

Procedure Overview This test covers the 2 steps of the UC1 happy path;1. Tester confirms no web comments2. Tester logs into system and navigates to the constituent screen and enters the constituent number

Procedure Dependencies 1.        Records have been properly created for the constituents being pulled up.

Functional Requirements 1.        No web comments are placed in the comments fields in the database2.        The IIS is properly set up.

Procedure Test Data Test Database Image Suite TDB100.0

Test Procedure

Conducted by __________________________________

Date Conducted ________________________

Build Label/Version  

Pre-Amble Instructions All databases need to be initialized to a known condition. This is typically done by copying the golden database images to their respective databases. Note that for Release 1, the databases will be small and the restoration of the databases will be more manual than is typical with a golden database environment.

Procedure Instructions  

Steps Passed/Fail Data Input Results Comments

Setup steps        

Step 1 – Tester confirms no web comments

     

Step 2 – Tester logs into the system

     

Post-Amble Instructions Do not restore the golden database to this environment after this test. Selected constituents in the database are set up for each test scenario to reduce the need to restore the database. 20

Page 22: Software test management overview for managers

Summary

• QA is organization-wide; Test is Project-wide

• QA requires that testing be performed at the development, validation and deployment phases

• The Test Strategy defines the validation approach (test, acceptance process) for the business need

• The Test Plan defines how testing is managed

• The Test Cases define how testing is executed

21