BVBA 03-23-05 December 2012 Project management : Set up reporting tool (MS Project & MS Excel) Presented by Jan Biets [email protected] +32(0)477 32 90 11 Mechelen - Belgium page 1 • reporting (graphical)

Set up pm reporting & tracking tool

Embed Size (px)

DESCRIPTION

how to start ? setting up tracking & reporting tool (MS Excel). All data are extracked from MS Project. aligned with Graphical project management reporting (earlier posted on Slideshare)

Citation preview

Page 1: Set up pm reporting & tracking tool

BV

BA

03-23-05December 2012

Project management : Set up reporting tool (MS Project & MS Excel)

Presented by Jan Biets

[email protected] +32(0)477 32 90 11 Mechelen - Belgium

page 1 • reporting (graphical)

Page 2: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

Reporting, analysing, steering [PDCA] : result driven pm

project progress : mandays

0

5

10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

reporting cycle

%

baseline (abs)

actual (abs)

project progress : budget [€] & mandays

0

50

100

150

200

250

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

reporting cycle

0

5

10

baseline [€]

actual [€]

baseline budget

baseline [md]

actuals [md]

reserved budget

project progress : mandays (cumulative)

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

reporting cycle

%

baseline

actual

Deliverables Chart

nov/10

jan/11

feb/11

apr/11

jun/11

jul/11

sep/11

baseline 28/02/2011 31/03/2011 30/04/2011 31/05/2011

reporting cycle

De

liv

era

ble

s d

ate

s

Business Requirements

Functional Design

Coding & Testing

Launch

Page 3: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

Project management : set up tracking & reporting tool (MS Excel)Once, the WBS is finalised (baseline), open ‘VIEW’ / ‘Tracking Gantt’ .

Page 4: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

Project management : set up tracking & reporting (MS Excel)Set view on ‘Resource usage’

Page 5: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

• Select timescale granularity (cursor on timescale/right mouse click / select Middle Tier ‘month’, and Bottom Tier ‘week’

• Select all dat and copy (use control-c)

Page 6: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

Open MS Excel (new file)Paste the copied selections (hours)Select all, and find&replace ‘h’ door ‘ ‘

Page 7: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

Cross check the sum of all cells, with ‘total work’ in MS Project fileadd tracking period (reporting period / frequency) on upper row (e.g.: wk 1 , wk 2, wk 3,…)Totalise planned hours per resource , or groupAdd the resource names (e.g. : name 1 , name 2 , name 3,…)You can now start to develop your own reporting & tracking tool

resource totaal wk 1 wk 2 wk 3 wk 4 wk 5 wk 6 wk 7 wk 8 wk 9 wk 10 wk 11 wk 12 wk 13 wk 14 wk 15 wk 16 wk 17 wk 18 wk 19 wk 20 wk 21 wk 22 wk 23 wk 24 wk 25 wk 26 wk 27 wk 28 wk 29 wk 30 wk 31 wk 32 wk 33 wk 34naam 1 978,2 26,7 44,5 26,7 44,5 25,6 32 32 41 36 32 32 19,2 32 32 32 32 32 32 32 32 32 32 32 32 32 32 32 32 34 40naam 2 1160 32 40 40 40 40 40 40 32 40 40 40 32 40 40 40 40 40 40 40 40 40 40 24 40 40 40 40 40 40 40naam 3 977 40 32 79 48 53 26 34,97 49,03 36 40 40 40 40 113 82,5 70,25 86,25 45 22naam 4 624 24 6 4,8 22,15 17,85 43 51,2 64 64 31 26 61 60 2 28 12 72,5 22,18 12,32naam 5 600 16 16 20 20 20 16 20 20 20 45,25 59,5 33,25 16 40 41 40 15 22 40 40 40naam 6 1120,21 40 27,2 32 46 122 62 0 40 26 17 40 40 40 45,22 66,12 62,67 1 39 86 40 48 40 80 80naam 7 991,15 54 0,93 0,45 0,37 0,45 0,45 2,88 28,5 34,5 61,5 79,4 0 80,4 52,5 38,9 10,5 10,5 50,5 50,5 90,5 47,72 0 115,5 74,2 50 32 24naam 8 719,2 0 0,2 16 63 32 44 17 35,1 12,9 44 21 2 39,02 109,73 137,38 28,87 50 59 8naam 9 485,2 0,2 24 40 64 54 40 3 24 40 40 26 72 50 8naam 10 851 65,5 16 41 28 10 40 40 40 40 30 24 174 144 5 53,5 52 40 8naam 11 40 0 8 32naam 12 621,02 24 40 32 8 7,75 10 10 39 53 68 38,23 22,72 48,13 75,47 23,7 22,4 16,47 17,67 23,68 16 24,8naam 13 107,99 12,48 20,8 16,63 20,8 20,8 16,48 0naam 14 444,5 1,3 1,67 1,67 1,67 1,33 1,67 1,67 1,67 1,67 21,07 25,67 35,67 45,67 25,67 25,67 25,67 15,4 25,67 25,67 25,67 31,67 25,67 49,67 25,67naam 15 33,34 8 0 0 0 0 0 0 0 0 0 5 0 0,97 1,67 1,67 1,67 1,67 1 1,67 1,67 1,67 1,67 1,67 1,67 1,67naam 16 699,72 7,82 7,82 6,25 7,82 7,82 7,82 6,25 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 31,82 52,68 57,82 63,82 73,32 71,82 47,82 56,82 121,82naam 17 446,11 7,82 7,82 6,25 7,82 7,82 7,82 6,25 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 27,13 66 40 40 40 40 40 31naam 18 355,12 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 24 26 40 40 40 60naam 19 235,12 24 30 6 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 7,82 18 30 2naam 20 270 50 20 20 20 20 20 20 20 40 40naam 21 0naam 22 800 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40naam 23 374 32 40 40 40 40 40 40 40 40 22naam 24 0naam 25 0naam 26 0naam 27 691,09 32 40 40 40 40 47,82 47,82 47,82 47,82 47,82 47,82 46,82 23,82 71,82 15,82 39,82 7,82 6,25naam 28 0naam 29 0 0naam 30 0naam 31 0 0naam 32 483 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 40 72 26 40 86 42 34 15naam 33 30 30naam 34 72 72 0 0 0 0 0 0naam 35 432 64 200 72 96naam 36 40 24 16naam 37 162 31 8 40 15 40 28

Page 8: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

Reporting, analysing, steering [PDCA] : result driven pm

project progress : mandays

0

5

10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

reporting cycle

%

baseline (abs)

actual (abs)

project progress : budget [€] & mandays

0

50

100

150

200

250

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

reporting cycle

0

5

10

baseline [€]

actual [€]

baseline budget

baseline [md]

actuals [md]

reserved budget

project progress : mandays (cumulative)

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

reporting cycle

%

baseline

actual

Deliverables Chart

nov/10

jan/11

feb/11

apr/11

jun/11

jul/11

sep/11

baseline 28/02/2011 31/03/2011 30/04/2011 31/05/2011

reporting cycle

De

liv

era

ble

s d

ate

s

Business Requirements

Functional Design

Coding & Testing

Launch

Page 9: Set up pm reporting & tracking tool

Project management Dynamics December 2012

BV

BA

Set up of reporting & progress tracking tool (MS Project – MS Excel)

• As of this point, you are able to develop further to a complete tracking and reporting tool, upon your own needs.

• More explanation about this tool, you will find at: www.slideshare/jan biets / graphical view on reporting