79
Technical Integrity of the Project Schedule MEETING NATIONAL NEEDS SCHEDULE TECHNICAL INTEGRITY THE KEY TO SUCCESSFUL PROJECT MANAGEMENT Shane Forth Msc, FAPM, FACostE Costain Natural Resources - PMO Director APM North West Event at University of Manchester - 16 TH March 2016

Schedule Integrity - The Key to Successful Project Management

Embed Size (px)

Citation preview

Page 1: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule

MEETING NATIONAL NEEDS

SCHEDULE TECHNICAL INTEGRITY

THE KEY TO SUCCESSFUL PROJECT MANAGEMENT

Shane Forth Msc, FAPM, FACostE

Costain Natural Resources - PMO Director

APM North West Event at University of Manchester - 16TH March 2016

Page 2: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 2

Introduction Alumni of Manchester University

www.costain.comContact Tel:

Mobile:

Email:

Follow us on:01642 664155 0161 910 3369

07812 961901

[email protected]

‘I received high quality support throughout from the Universities MACE School, course co-ordinators, programme team, academic staff, course administrators and especially, my dissertation supervisor Therese Lawlor-Wright, who provided excellent support and guidance.’

2

Page 3: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 3

Costain Group plc

Securing a future energy supply…

…maintaining a safe and reliable water supply

…upgrading the transport infrastructure

Infrastructure

Natural Resources

Page 4: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 4

Costain Group plc

Natural Resources

LISTED ON THE

LondonStock Exchange

SECURED BUSINESS UK EMPOLYEES

35382014

Female 681

Male 2857

Costain Group plcis one of the UK’s largest and most respected Engineering Solutions Providers

Infrastructure

Rail  Highways

Power Water

Nuclear

Oil & Gas

Page 5: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 5

Costain Natural Resources

Established over 60 years ago

UK & Internationally focused

Full project lifecycle delivery 

Driven by technology & innovation

Focus on advisory & design services

Improvement & development of customer facilities

Advisory & Concept Development

Specialist Design

Programme Management

Complex Project Delivery

Technology Integration

Asset Optimisation & Support

Our Natural Resources division supports the Oil & Gas, Power, Water and Carbon Management sectors.

Page 6: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 6

Costain Oil & GasProject Delivery Centres

Manchester Delivery Centre

870 people across processsectors

Immingham

CORE CAPABILITIES – FULL PROJECT LIFE CYCLE

Concept, feasibility and FEED

Detailed design, engineering, procurement and project management services

Construction Management

Asset management & industrial services

180

Head Office Maidenhead

450

Leeds170

Teesside30

Aberdeen130

Page 7: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 7

Project Management Office (PMO)

‘ To develop, implement and continuously improve our processes and tools for project controls and information management to help our project teams improve delivery outcomes on new projects to benefit both Costain and our customers

Our customers recognise the industry leading processes and tools we provide for project controls and information management that strongly support our project teams and ensure predictable project delivery in all our target markets

Page 8: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 8

Integrated Project Delivery Solution (IPDS)

http://costain.com/media/597674/ipds‐2pp.pdf

Page 9: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 9

IPDS System Offering

Page 10: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 10

IPDS System Offering

Page 11: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 11

Project Controls Technician Trailblazer Apprenticeship

Page 12: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 12

Agenda

1. Schedule Technical Integrity - What is it and How Big is the Problem ?

2. Common Problems in the Development of Project Schedules

3. A Review of Good Practice in Preparing the Project Network

4. Real World Case Studies

5. 5-Step Solution

6. Emerging Trends in Industry

7. Why is Planning & Scheduling Important?

Page 13: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 13

Technical relating to a particular subject, art, or craft, or its techniques

Integrity the condition of being unified or sound in construction

http://oxforddictionaries.com/

Schedule Technical IntegrityWhat is It?

Page 14: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 14

Technical Assurance The monitoring of the technical integrity of products.

Technical Pertaining to the application of specific principles and/or reasoning to the resolution of project management issues or problems.

Integrity In dealings between parties, firm adherence to a code of moral valuesincluding completeness, honesty, honor, forthrightness,straightforwardness and entirety.

Wideman Comparative Glossary of Project Management Terms v3.1 http://www.maxwideman.com/pmglossary/index.htm

Schedule Technical Integrity What is It?

Page 15: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 1515

After: Ernest & Young 2014 

Schedule Technical IntegrityHow Big is the Problem?

Page 16: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 16

Schedule Technical IntegrityHow Big is the Problem?

ENR, May 2003, reported on a meeting at which fourscheduling experts lamented the state of scheduling andwhat they saw as widespread abuse of powerful software toproduce badly flawed schedules, that look good but lackmathematical coherence or common sense. They describedthis as: The article included a quote from Russell J. Lewton,

construction manager for the Weitz Co LLC, Des Moines:

Korman et al (2003)

‘Among the young guys, computershave made it east to slap togethersomething that looks right, but thereis a thought process that must beinvolved, and it is hard to tell in manycontemporary schedules if thethinking has happened or not.’

Critics can't find the logic in many of today's CPM schedulesUsers want software with flexibility, but is it true CPM?

Page 17: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 17

Schedule Technical IntegrityHow Big is the Problem?

We might liken the current condition of schedule analyses to fruit we buy at the market.We have all had the experience of buying fruit that looks to be in excellent condition, onlyto get home and find it is rotten to the core. In the era of Enron we have seen this trendcarry over to accounting reports not worth the paper on which they are written.

Unfortunately the field of construction planning today presents a landscape that is litteredwith too many ‘rotten banana’ schedules. Whilst the majority of schedules in use todaypresent tools for planning and scheduling projects, too many of today’s schedules fall intothe ‘rotten bananas’ category.

Frequently these ‘rotten banana’ schedules appear to be in excellent condition from theoutside. However when we look at the actual content of these documents and files, wefind that the schedules are flawed, if not useless.

Wickwire et al, 2003

‘Rotten bananas in a Software Paradise

Page 18: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 18

Common Problems in the Development of Project Schedules

1. Open ended activities - no predecessor or no successor2. Use of constraint dates3. Negative Lags4. Incorrect software settings can affect calculations5. Excessive detail

These five problems lead to project networks with incorrect float calculations and invalid or absent critical path. Credibility is lacking, predictability and forecasts are poor and this not acceptable to customers

Page 19: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 19

Common Problems in the Development of Project Schedules

Open ended activities occur as a result of decisions (or errors) made by the project planner when creating the project schedule. To illustrate the impact of the problem, we can consider the impact on a very simple project network.

1. Open ended activities - no predecessor or no successor2. Use of constraint dates3. Negative Lags4. Incorrect software settings can affect calculations5. Excessive detail

Page 20: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 20

Common Problems in the Development of Project Schedules

A B F I J

C D E

G H

A B F I J

C D E

G H

Page 21: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 21

Common Problems in the Development of Project Schedules

Page 22: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 22

Common Problems in the Development of Project Schedules

The FS dependency between Activity C & D has been removed or missed by the planner below, what are the effects?

Page 23: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 23

Common Problems in the Development of Project Schedules

Page 24: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 24

Common Problems in the Development of Project Schedules

The FS dependency between Activity B & C has been removed or missed by the planner below, what are the effects?

Page 25: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 25

Common Problems in the Development of Project Schedules

Computerised project management systems have various constraint date types, which canbe assigned to activities as imposed dates – but beware, this will override the calculationand results of a natural forward and backward pass.

1. Open ended activities – no predecessor or no successor2. Use of constraint dates3. Negative Lags4. Incorrect software settings can affect calculations5. Excessive detail

Page 26: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 26

Common Problems in the Development of Project Schedules

Page 27: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 27

Common Problems in the Development of Project Schedules

Computerised project management systems offer various types of constraint dates which can be assigned to activities as imposed dates, overriding the calculation and results of a natural forward and backward pass

Page 28: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 28

Common Problems in the Development of Project Schedules

Computerised project management systems offer various types of constraint dates which can be assigned to activities as imposed dates, overriding the calculation and results of a natural forward and backward pass

Activity CStart On or After 28 Aug

Page 29: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 29

Common Problems in the Development of Project Schedules

Computerised project management systems offer various types of constraint dates which can be assigned to activities as imposed dates, overriding the calculation and results of a natural forward and backward pass

Look what’s happened

to the Project Finish date ?

Activity CStart On or After 28 Aug

Page 30: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 30

Common Problems in the Development of Project Schedules

Constraint Types (Primavera P6) Start On or After Finish On or After Start On or Before Finish On or Before Mandatory Start Mandatory Finish

Constraint Types (Microsoft Project) Start No Earlier Than Finish No Earlier Than Start No Later Than Finish No Later Than Must Start On Must Finish On

Page 31: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 31

Common Problems in the Development of Project Schedules

31

Extract from CPM Network without Imposed Restraints(Adapted from Ahujah, 1976: 54, Figure 3-8)

Figure ‐ Extract from CPM Network with Imposed Restraints(Adapted from Ahujah, 1976: 54, Figure 3‐9) 

Page 32: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 32

1. Open ended activities – no predecessor or no successor2. Use of constraint dates3. Negative Lags4. Incorrect software settings can affect calculations5. Excessive detail

Common Problems in the Development of Project Schedules

Page 33: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 33

Common Problems in the Development of Project Schedules

 

Activity B needs to Start 20 days before Activity A finishes

Dur = 50 days

Dur = 40 days

Page 34: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 34

Common Problems in the Development of Project Schedules

 

Activity B needs to Start 20 days before Activity A finishes

Dur = 50 days

Dur = 40 days

This suggests that the finish of a future activity will determine the start of an activity in the past which is neither logical nor possible

Better options are Use an SS relationship with a positive lag of 30 days from Activity A

to Activity B Use more detailed activities (with smaller durations) and an FS 0

relationship between them

Page 35: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 35

Common Problems in the Development of Project Schedules

1. Open ended activities – no predecessor or no successor2. Use of constraint dates3. Negative Lags4. Incorrect software settings can affect calculations5. Excessive detail

Page 36: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 36

Common Problems in the Development of Project Schedules

Some Examples of the complexity in software settings Include:

Activity Duration Types– Fixed Duration and Units– Fixed Duration and Units/Time– Fixed Units/Time– Fixed Units

Scheduling Options– Make open ended activities critical– When scheduling progressed activities use Retained Logic or Progress Override

or Actual dates – Calculate Start to Start Lag from Early Start or Actual Start– Use Expected Finish Dates– Ignore dependencies (relationships) to and from activities in other projects– Compute Total Float as Start Float, Finish Float or smallest of Start and Finish

Float – Calculate Float based on Finish Date of Each Project or Opened Projects

Page 37: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 37

Common Problems in the Development of Project Schedules

Some Examples of the complexity in software settings Include:

Activity Duration Types– Fixed Duration and Units– Fixed Duration and Units/Time– Fixed Units/Time– Fixed Units

Scheduling Options– Make open ended activities critical– When scheduling progressed activities use Retained Logic or Progress Override

or Actual dates – Calculate Start to Start Lag from Early Start or Actual Start– Use Expected Finish Dates– Ignore dependencies (relationships) to and from activities in other projects– Compute Total Float as Start Float, Finish Float or smallest of Start and Finish

Float – Calculate Float based on Finish Date of Each Project or Opened Projects

If the planner changes the activity duration manually, the software automatically changes the resources (manhours)

Page 38: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 38

Common Problems in the Development of Project Schedules

1. Open ended activities – no predecessor or no successor2. Use of constraint dates3. Negative Lags4. Incorrect software settings can affect calculations5. Excessive detail

Page 39: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 39

Common Problems in the Development of Project Schedules

Excessive activity detail in the project network has been a problem since the very first use of the critical path method. (CPM) 1957-58 - during testing in first use of CPM by Du Pont US on a new chemical

plant facility, a team of six engineers went into far more detail than expected(Kelley & Walker, 1959)

Early 1960s - the USAF Dyna Soar rocket missile program had a network of250,000 activities that had to be simplified for contractors (Battersby, 1964)

Early 1960s - Bristol Aircraft ran into difficulties with a 3000 activity network inConcorde, encountering incomplete logic, loops and incorrect event numbering(Battersby, 1964)

http://commons.wikimedia.org/wiki/Main_Page

Page 40: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 40

Common Problems in the Development of Project Schedules

Excessive network activity detail causes the following problems: Many stakeholders are overwhelmed and don’t understand the plan, or ignore it

Need for taller organisation with increased levels of management and slower decisions

Difficulties in keeping the project schedule current– Progress update is a high maintenance chore, the network quickly becomes out of date

– Difficulties adding authorised changes into the network, another high maintenance chore

– Progress status reports are late and inaccurate

Abortive and inefficient schedule development work– As the more distant planned work moves towards the upcoming time horizon, the schedule

activity detail that was planned too early, before the prerequisite level of scope definition and information was available, has to be reworked

Page 41: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 41

The convenience of PC, modern project management software and speed of data entry thatcan easily lead the planning engineer and project team into temptation to develop the projectnetwork in more detail than the availability of the prerequisite information supports

A long list of authoritative sources cite the problem of excessive activity as the single most problem in the development of robust and usable project networks(e.g. PMI, 2007, Andersen, 1996; Lockyer & Gordon, 1996; Drigani, 1989; Laufer & Tucker, 1988; Lockyer, 1984; Morton,

1983b; Lester, 1982 (citing NEDO, 1976); Woodgate, 1977; Ahuja, 1976

Common Problems in the Development of Project Schedules

Page 42: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 42

Common Problems in the Development of Project Schedules

In addition to the convenience of the PC, organisational and behavioural issues influence come into play: Whilst some project team members or stakeholders complain there is too

much detail in the project schedule

… it is often assumed that more thought must have been put into project schedule development and that more detail provides more certainty as to the outcome

… many find this a comfort, it give them a (false) sense of security

… I would suggest to you that this is a confusion in thinking that quantity is equal to quality.

Page 43: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 43

A Review of Good Practice in Preparing the Project Network

2015 - APM - Planning, Scheduling, Monitoring and Control: The Practical ProjectManagement of Time, Cost and Risk

2014 - CPM Scheduling for ConstructionBest Practice and Guidelines

2010 - American Association of Cost Engineers- Identifying the Critical Path- Schedule Level of Detail- Forensic Schedule Analysis

2007 - Project Management Institute (PMI)PMBOK

2002 - Society of Construction Law Delay and Disruption Protocol

Standards and Guidelines that contain statements of good practice concerning the project network include:

Page 44: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 44

A Review of Good Practice in Preparing the Project Network

2011 - Chartered Institute of Builders (CIOB) - Review for schedule integrity

2010 - Association for Project Management (APM)- The scheduling maturity model

2010 - Government Accountability Office (GAO) - 9 point schedule analysis

2009 - Defense Contract Management Agency (DCMS ) - 14 point schedule assessment

Standards and Guidelines - As awareness of problems have increased,government organisations and professional bodies have introduced specificstandards and guidelines for the checking of schedule integrity

Page 45: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 45

A Review of Good Practice in Preparing the Project Network

A B F I J

C D E

G H

A B F I J

C D E

G H

Open Ends

Page 46: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 46

A Review of Good Practice in Preparing the Project Network

Open Ends

Page 47: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 47

A Review of Good Practice in Preparing the Project Network

Use of Constraint Dates

Page 48: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 48

A Review of Good Practice in Preparing the Project Network

Use of Constraint Dates

Page 49: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 49

A Review of Good Practice in Preparing the Project Network

FS - 20 SS 30

FF 20

Negative Lags

Page 50: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 50

A Review of Good Practice in Preparing the Project Network

Negative Lags

Page 51: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 51

A Review of Good Practice in Preparing the Project Network

Most professional bodies recommend the ‘rolling wave method to address the issue of excessive detail (as do Costain procedures)

APM advocates the ‘rolling wave’ method PMI acknowledge that too much detail can mean a schedule which is difficult

to manage and suggest that the level should be sufficient for the assignedperson to carry out the task without requiring further sources of guidance

AACEI recommend Level 3 detail, which is not too high-level and not toodetailed and support the ‘rolling wave’ method whereby Level 3 may apply othe detailed engineering/design phase, but the later phases for procurementand construction phases might only be detailed to Level 1 or 2.

GAO Best Practice number 3 specifies the ‘rolling wave’ method Society of Construction Law guidance is that activities should not exceed

28 days duration Costain specify a maximum 3,000 activities for the project

network and recommend the ‘rolling wave’ method

Level of Detail

Page 52: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 52

A Review of Good Practice in Preparing the Project Network

CIOB (2011a :30). Graph of schedule density in relation to predictability

Level of Detail

Page 53: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 53

A Review of Good Practice in Preparing the Project Network

Level of Detail

CIOB (2011b :36). WBS levels and schedule density

Page 54: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 54

Real World Case Study 1

All eight networks would all fail the Defense Contract Management Agency (DCMA ) 14Point Schedule Assessment, which recommends a 5% limit for open ends, constraintsand negative lags

ProjectA

ProjectB

ProjectC

ProjectD

ProjectE

ProjectF

ProjectG

ProjectJ Max Avg

# Activities 4067 3597 3528 2792 1933 1526 923 522 2361

# Open Ends 5.3% 10.6% 9.2% 7.5% 4.4% 29.1% 33.3% 36.4% 36.4% 11.4%

# Constraints 1.1% 12.6% 11.3% 4.3% 6.5% 2.4% 1.1% 1.3% 12.6% 6.4%

# Negative Lags 0.1% 3.6% 1.8% 2.1% 1.0% 8.9% 1.6% 11.1% 11.1% 2.6%

ProjectA

ProjectB

ProjectC

ProjectD

ProjectE

ProjectF

ProjectG

ProjectJ Max Avg

# Activities 4067 3597 3528 2792 1933 1526 923 522 2361

# Open Ends 5.3% 10.6% 9.2% 7.5% 4.4% 29.1% 33.3% 36.4% 36.4% 11.4%

# Constraints 1.1% 12.6% 11.3% 4.3% 6.5% 2.4% 1.1% 1.3% 12.6% 6.4%

# Negative Lags 0.1% 3.6% 1.8% 2.1% 1.0% 8.9% 1.6% 11.1% 11.1% 2.6%

ProjectA

ProjectB

ProjectC

ProjectD

ProjectE

ProjectF

ProjectG

ProjectJ Max Avg

# Activities 4067 3597 3528 2792 1933 1526 923 522 2361

# Open Ends 214 380 325 209 86 444 307 190 444 269

# Constraints 46 454 399 121 126 36 10 7 454 150

# Negative Lags 6 130 64 58 20 136 15 58 136 61

ProjectA

ProjectB

ProjectC

ProjectD

ProjectE

ProjectF

ProjectG

ProjectJ Max Avg

# Activities 4067 3597 3528 2792 1933 1526 923 522 2361

# Open Ends 214 380 325 209 86 444 307 190 444 269

# Constraints 46 454 399 121 126 36 10 7 454 150

# Negative Lags 6 130 64 58 20 136 15 58 136 61

Page 55: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 55

Real World Case Study 1

Some Possible Causes– Lack of time to prepare plan (leads to

shortcuts)– Too much detail (high maintenance)– Lack of checking– Computer functionality– Bad habits– Laziness/easy way out– Unlearned what we did before– Lack of training and procedures– Lack of experience or capability– GiGO

Page 56: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 56

Real World Case Study 1

Some Possible Causes– Lack of time to prepare plan (leads to

shortcuts)– Too much detail (high maintenance)– Lack of checking– Computer functionality– Bad habits– Laziness/easy way out– Unlearned what we did before– Lack of training and procedures– Lack of experience or capability– GiGO

Some Definite Impacts– Float calculations wrong– Critical path invalid or absent– Plan lacks credibility– Plan not realistic– Plan not accepted by client– Poor predictability or forecasts– Poor reputation– Plan not recognised in

adjudication or arbitration– People may not realise there’s a

problem(ignorance is bliss)

– GIGO

Page 57: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 57

Real World Case Study 2The Good

Semi-Structured Interviews13 Project Controls and Planning Managers from 11 companies

with significant experience in energy industry

Page 58: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 58

Real World Case Study 2The Good

Page 59: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 59

Real World Case Study 2The Bad

Page 60: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 60

Real World Case Study 2… and the Ugly

Page 61: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 61

5 Step SolutionSteps 1 to 4

1 Rules

Procedures, practices & work instructions

- Procedures and practices prohibit or discourage actions which cause problems in project network development

- Detailed work instructions forPrimavera P6

2 Schedule integrity check

3Schedule Narrative

4 Risk analysis

Independent 99 point checklist

(before baseline issued)Eight topics covered including: - Network Logic & Constraints - Scheduling Method - Critical Path/ Float - Primavera P6 Practicecompliance

- etc.

Basis of Schedule- WBS & activity detail - Clarifications & assumptions- Schedule method statement- Use of constraints- Critical path,- Key issues- Calendars, and seasonal implications

- Resource availability - Resource levelling

Schedule optimisation- More realistic schedule, - 3 point estimate of completion date rather than deterministic schedule

- May be applied to separatestandalone schedules if program//project networkis too large.

Page 62: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 62

5 Step Solution Step 5

5Project team review the plan (content and constructability) before issue

Includes project management team and key stakeholders

Page 63: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 63

5 Step SolutionTechnical Integrity Audit of Project Network

Page 64: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 64

Independent 99 Point Checklist (before Baseline

issued)Items on Checklist include: Guidance Notes Findings Recommended ActionsEight Topics Covered:1.Project Setup2.Project Details3.Network Logic & Constraints4.Scheduling Method5.Critical Path/Float6.Resource Management7.Progress8.Primavera P6 Practice complianceSummary Report Produced for Senior Management

5 Step SolutionTechnical Integrity Audit of Project Network

Page 65: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 65

5 Step SolutionTypical Results (Project X)

Date / # Activities 17 Dec 2010 1340

Qty %

11 Jan 2011 1340

Qty %

10 Feb 2011 1358

Qty % Open Ends – No Predecessor or No Successor

204

15.2%

172

12.8%

24

1.8%

Constraints

246

18.4%

97

7.2%

83

6.1%

Negative Lags

35

2.6%

35

2.6%

31

2.3%

Date / # Activities 17 Dec 2010 1340

Qty %

11 Jan 2011 1340

Qty %

10 Feb 2011 1358

Qty % Open Ends – No Predecessor or No Successor

204

15.2%

172

12.8%

24

1.8%

Constraints

246

18.4%

97

7.2%

83

6.1%

Negative Lags

35

2.6%

35

2.6%

31

2.3%

Page 66: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 66

5 Step SolutionTypical Results (Project Y)

Date / # Activities 09 Nov2010 2965

Qty %

03 Dec2011 2394

Qty %

25 Jan 2011 2392

Qty % Open Ends – No Predecessor or No Successor

388 13.1% 113

4.7% 60 2.5%

Constraints

41 1.4% 26

1.1% 21 0.9%

Negative Lags

16 0.5% 24 1.0% 20 0.8%

Date / # Activities 09 Nov2010 2965

Qty %

03 Dec2011 2394

Qty %

25 Jan 2011 2392

Qty % Open Ends – No Predecessor or No Successor

388 13.1% 113

4.7% 60 2.5%

Constraints

41 1.4% 26

1.1% 21 0.9%

Negative Lags

16 0.5% 24 1.0% 20 0.8%

Page 67: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 67

5 Step SolutionFeedback

Project Director – Project X‘I welcome your input to ensure we have best practice on the project in line with governance’

Project Director – Project Y‘I really appreciate your time spent on auditing the schedule. Always good to have an outside view on the content. While the results are encouraging, I still believe we have a way to go on making this schedule robust. I am aware that this audit is usually undertaken on a 6 monthly cycle, but I would appreciate if you could take time out before the xmas holiday break to check the progress against the actions, and ensure they are closed out.’

Project Sponsor – Project Y‘Thanks team, great work’

Page 68: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 68

5 Step SolutionLooking Forward

Indications from feedback are that benefits are being realised

Schedule technical integrity 5-step solution has been incorporated into Costainproject management plans and procedures

Continued recruitment of new practitioners at all levels, and the development and training and retention of these and existing is happening

The level of checking required for technical integrity of project schedules can gradually be relaxed, as improved practice is embedded

The strong likelihood that customer requirements will include the need to the ensure schedule technical integrity will help implement the solution

Page 69: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 69

Emerging Trends in Industry

Further to the recent trend in issuing specific standards and guidelines, the number of software applications are coming onto the market for checking the schedule integrity of project networks is increasing

2007 Steelray

Project Analyzer

2010 Acumen

Fuse

2004Pertmaster

Risk 2003

Schedule Analyzer for

the Enterprise

2010 Primavera

P6 v 8

2010 Schedule Cracker

1999 Schedule Analyzer

Pro

Page 70: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 70

Why is Planning & Scheduling Important ?

A 2009 report by Independent Project Analysis (IPA) benchmarking organisation for the UK Government found that better scheduling and cost estimating methods lead to better engineering and construction labour productivity and cost performance

Page 71: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 71

Why is Planning & Scheduling Important ?

The same report found that in the UK, less than 20% of projects have resource loaded schedule at project sanction, compared to over 40% in US Gulf Coast, but use of critical path techniques is 40% in UK compared to just over 30% in US Gulf Coast. The paradox is that UK projects tend to be cost rather than schedule driven

Page 72: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 72

Why is Planning & Scheduling Important ?

Projects not using network analysis techniques had an average 26%schedule overrun this includes projects using project management software but with over-constrained project networks

Almost 50% of projects use network analysis techniques with an average 14% schedule overrun

Page 73: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 73

References

Association for Project Management (2010: 17-18). The Scheduling Maturity Model. High Wycombe, UK: APM PublishingAssociation for Project Management (2008: 15). Introduction to Project Planning. High Wycombe, UK: APM PublishingAACE International (2010a: 76). Recommended Practice No. 29R-03 Forensic Schedule analysis. AACE International: Morgantown, WV. AACE International (2010b: 4-6). Recommended Practice No. 49R-06 Identifying the Critical Path. AACE International: Morgantown, WVAACE International (2010c: 2 & 4). Recommended Practice No. 37R-06 Schedule Level of Detail – As Applied in Engineering, Procurement and Construction. AACE International: Morgantown, WVBendix Corporation (1955 :1). The Bendix G-15 CPM/PERT Program http://www.computerhistory.org/collections/accession/102646275[Accessed 31 January 2010]CIOB (2011a :30). Guide to Good Practice in the Management of Time in Complex Projects. Chichester: Wiley-BlackwellCIOB (2011b :36). Guide to Good Practice in the Management of Time in Complex Projects. Chichester: Wiley-BlackwellDrigani, F. (1989 :149). Computerized Project Control. New York. Marcel Dekker IncFoxley, E. (2005), Computers 1960 to 1965.http://www.cs.nott.ac.uk/~ef/ComputerXHistory/FirstComputers-2/1963-ICT1500-GeneralView.htm [Accessed 31 January 2010}Moder, J. et al (1983 :64). Project Management with CPM, PERT and Precedence Diagramming.3rd Edn.Wisconsin, USA. Blitz Publishing Company (Reprinted 1995)Moder, J. et al (1983 :356). Project Management with CPM, PERT and Precedence Diagramming.3rd Edn.Wisconsin, USA. Blitz PublisghingCompany (Reprinted 1995)Mosaic Project Service Pty Ltd. (2009b :21). Seeing the Road Aheadhttp://www.mosaicprojects.com.au/PDF_Papers/P106_Seeing_The_Road_Ahead_PMOZ.pdf [Accessed 2nd February 2011]Project Management Institute.(2007) 18). The Practice Standard for Scheduling. Newtown Square, PA: Project Management InstituteProject Management Institute.(2007) 19). The Practice Standard for Scheduling. Newtown Square, PA: Project Management InstituteSociety of Construction Law (2002: 40). Delay and Disruption Protocol. Wantage. Society of Construction Law (Reprinted October 2004)Society of Construction Law (2002: 68). Delay and Disruption Protocol. Wantage. Society of Construction Law (Reprinted October 2004)

Page 74: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 74

Bibliography

AACE International (2010a). Recommended Practice No. 29R-03 Forensic Schedule analysis. AACE International: Morgantown, WV. AACE International (2010b). Recommended Practice No. 49R-06 Identifying the Critical Path. AACE International: Morgantown, WVAACE International (2010c). Recommended Practice No. 37R-06 Schedule Level of Detail - As Applied in Engineering, Procurement and Construction. AACE International: Morgantown, WVAcumen Fuse. http://www.projectacumen.com/fuse/industry-standards/dcma-14-point-assessment/ [Accessed 7th December 2010]APM PMC SIG (2015). Planning, Scheduling, Monitoring and Control: The Practical Project Management of Time, Cost and Risk. High Wycombe, UK: APM Publishing Association for Project Management (2010). The Scheduling Maturity Model. High Wycombe, UK: APM PublishingAssociation for Project Management (2008: 15). Introduction to Project Planning. High Wycombe, UK: APM PublishingAssociation of Cost Engineers, Book Review, Project Control Professional, Vol 49 No 1, 26Bendix Corporation (1955). The Bendix G-15 CPM /PERT Program http://www.computerhistory.org/collections/accession/102646275[Accessed 31 January 2010]Binafore, B. (2007 :69). Microsoft Project 20007: The Missing Manual. USA. O’Reilly Media, Inc. Buttrick, R. (1997). The Project Workout. London. Pitman PublishingCarson, C, Oakander, P., Relyea, C. (2014). CPM Scheduling for Construction Best Practice and Guidelines. Newtown Square, PA: Project Mangement InstituteCIOB (2011). Guide to Good Practice in the Management of Time in Complex Projects. Chichester: Wiley-BlackwellCIOB (2008). Managing the Risk of Delayed Completion in the 21st Century. Ascot: CIOBCornish. J. (2008). A Brief History of Project Scheduling. http://www.microplanning.co.uk/downloads.htm#Papers [Accessed 28th January 2011] Douglas III, E.E., Calvey, T.T., McDonald Jr, D. F., & Winter, R. M. The Great Negative Lag Debate. http://www.calveyconsulting.com/files/PS02_Great_Negative_Lag_Debate.pdf [Accessed 7th December 2010]Drigani, F. (1989). Computerized Project Control. New York. Marcel Dekker IncGray, C.F. and Larson, E.W. (2011). Project Management: The Managerial Process. 5th Ed. Boston, MA: McGraw-HillKerzner, H. (1992). Project Management A Systems Approach to Planning, Scheduling and Controlling. 4th Edn. London, Chapman and Hall

Page 75: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 75

Korman, Richard & Daniels, Stephen H. (2003). “Critics Can’t Find the Logic in Many of Today’s CPM Schedules,” http://enr.construction.com/features/bizLabor/archives/030526.asp [Accessed 1st December 2010] . PlPLester, A. (2005). Project Planning and Control. 4th Edn. Bodmin, MPG Books Ltd.Minor Richards Associates (2001). An evaluation of the projected future evolution of the workforce and key skills needs within the engineering contractors sector of the Oil Gas and Chemical Industry URN/01/1066. June 2001.Moder, J. et al (1983). Project Management with CPM, PERT and Precedence Diagramming.3rd Edn.Wisconsin, USA. Blitz Publishing Company (Reprinted 1995)Mosaic Project Service Pty Ltd. (2009a).Improving Schedule Management http://www.mosaicprojects.com.au/Resources_Papers_081.html[Accessed 2nd February 2011]Mosaic Project Service Pty Ltd. (2009b). Seeing the Road Aheadhttp://www.mosaicprojects.com.au/PDF_Papers/P106_Seeing_The_Road_Ahead_PMOZ.pdf [Accessed 2nd February 2011]O’Brien, J. & Plotnick, F.L. (2010). CPM in Construction Manaagement. 7th Ed. USA, McGraw-Hill ProfessionalPacelli, L. (2004). The Project Management Advisor: 18 Major Project Screw-ups, and How to Cut Them off at the Pass. New Jersey. Prentice HallPC User NSTL Lab Report (1992). NSTSL Lab Report. PC User. 179, March. p134-140Pinto, J. K. (2010). Project Management Achieving Competitive Advantage. 2nd Edn. New Jersey, USA. Prentice HallPrimavera P6 Professional Project Management. http://www.oracle.com/us/products/applications/042374.htm [Accessed 7th December 2010]Primavera Risk Analysis. .http://www.oracle.com/us/products/applications/042371.htm [Accessed 7th December 2010]Project Management Institute.(2007). The Practice Standard for Scheduling. Newtown Square, PA: Project Management InstituteReiss, G. (1998). “Project Management Demystified. 2nd Edn. London, E & FN SponSchedule Analyzer Professional for the Enterprise. http://scheduleanalyzer.com/ [Accessed 7th December 2010]Schedule Analyzer Professional. http://scheduleanalyzer.com/ [Accessed 7th December 2010]Society of Construction Law (2002). Delay and Disruption Protocol. Wantage. Society of Construction Law (Reprinted October 2004)Steelray Project Analyzer. http://www.steelray.com/spafeatures.html [Accessed 7th December 2010]

Bibl iography

Page 76: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 76

Stretton, A. (2007). A Short History of Modern Project Management. http://www.pmforum.org/library/second-edition/2007/PDFs/Stretton-10-07.pdf [Accessed 27th January 2010]Wikipedia (2011). Critical Path Method http://en.wikipedia.org/wiki/Critical_path_method#History [Accessed 27th January 2010]Wickwire, J. (2004). An Interview with Jim O’Brien – December 1, 2004. http://www.pmicos.org/jointerview.asp

Bibliography

Page 77: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule

IMPROVING  PROJECT  SCHEDULE  OUTCOMES  HOW  EFFECTIVE  ARE  YOUR  PROJECT  SCHEDULES  

AND  CRITICAL  PATH  ANALYSIS  METHODS   IN  MANGING  TIME  

Shane Forth - PMO Director

Page 78: Schedule Integrity - The Key to Successful Project Management

Technical Integrity of the Project Schedule 78

Two Hour WorkshopTo Help You Improve Your Project Planning

Page 79: Schedule Integrity - The Key to Successful Project Management

This presentation was delivered

at an APM event

To find out more about

upcoming events please visit our

website www.apm.org.uk/events