www.construction.murrob.com SASOL MAFUTHA Limpopo, Lephalale PROJECT TYPE: OPENCAST MINING CLIENT: Sasol Mining Pty Ltd VALUE: R 134 Million CONSULTANTS: None PROJECT DURATION: 12 Months DATE OF PROJECT: 1 July 2009 PROJECT DESCRIPTION: Coal bulk sample in Lephalale, mined to a depth of 96m. Approximate volumes mined for the project :- Selective Mining of Bulk Coal sample. Total of 1, 500,000 m³ of topsoil and blasted over burden was moved, with a total of 996,000 tons of coal. Coal was crushed down to a <200mm.

Sasol mafutha

Embed Size (px)

DESCRIPTION

Opencast Contract Mining, drill Blast, Load, Haul, Crushing

Citation preview

Page 1: Sasol mafutha

www.construction.murrob.com

SASOL MAFUTHA Limpopo, Lephalale

PROJECT TYPE: OPENCAST MINING

CLIENT:

Sasol Mining Pty Ltd

VALUE:

R 134 Million

CONSULTANTS:

None

PROJECT DURATION:

12 Months

DATE OF PROJECT:

1 July 2009

PROJECT DESCRIPTION:

Coal bulk sample in Lephalale, mined to a depth

of 96m.

Approximate volumes mined for the project :-

Selective Mining of Bulk Coal sample. Total of 1,

500,000 m³ of topsoil and blasted over burden

was moved, with a total of 996,000 tons of coal.

Coal was crushed down to a <200mm.