46
Aaron Stevens Project Samples

Safety, Process, And Ergonomic Improvements

Embed Size (px)

DESCRIPTION

This is a small sample of My Shop Floor Improvements

Citation preview

Page 1: Safety, Process, And Ergonomic Improvements

Aaron Stevens

Project Samples

Page 2: Safety, Process, And Ergonomic Improvements

Lean Approaches and Goals

• Use just what you need when you need it.• 99.9% of the time, addressing ergonomic

and safety issues will reduce cycle time / tack time and increase Kaizan time (Improvement).

• Team member cross training and 5’s.• Simplifying, Standardizing, Sorting,

Sustaining, and Systematic Cleaning.

Page 3: Safety, Process, And Ergonomic Improvements

My Several hat’s

• Industrial Health and Safety Engineer• Project Manager• Safety Manager• Process Improvement Engineer• Associate Engineer Technician• Safety Specialist• Ergonomic Specialist• Welder Specialist• Fabrication Specialist• Production Specialist

Page 4: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 5: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 6: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 7: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 8: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 9: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 10: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 11: Safety, Process, And Ergonomic Improvements

From Solid Works to the Floor

Page 12: Safety, Process, And Ergonomic Improvements

Before and After

Working on the Floor

Working at the right height

Page 13: Safety, Process, And Ergonomic Improvements

Before

Make shift build Table to place bar after its been punched, then TM screws in the hardware from boxes as shown.

Fresh air stop punch

Page 14: Safety, Process, And Ergonomic Improvements

After

TM can now punch Stucco and regular frame bar, then slide over into new slot. Once bar is in slot, TM can screw in hardware easily. Punch has New shelf to hold three bins for screws and hardware, and holder for the air drill.

Page 15: Safety, Process, And Ergonomic Improvements

AfterFresh Air Stop Punch and Build Table

Page 16: Safety, Process, And Ergonomic Improvements

Before:Bins taking up space on shop floor

Page 17: Safety, Process, And Ergonomic Improvements

After:Space on shop floor has really opened up!

Page 18: Safety, Process, And Ergonomic Improvements

Before:Smoke Shack/Lunch Room

Page 19: Safety, Process, And Ergonomic Improvements

After:New Storage Area!

Page 20: Safety, Process, And Ergonomic Improvements

• Eliminating Trip Hazards

Before and After

Page 21: Safety, Process, And Ergonomic Improvements

• New Step Ladder to replace Wood Bench

Before and After

Page 22: Safety, Process, And Ergonomic Improvements

• New Guard Rail for electrical panel

Before and After

Page 23: Safety, Process, And Ergonomic Improvements

Designated Areas Marked

Page 24: Safety, Process, And Ergonomic Improvements

• No guarding/unsafe work conditions

• Pinch Points and rotating parts

Before

Page 25: Safety, Process, And Ergonomic Improvements

After

• New Machine Guarding

• Safe operation for Team Members

Page 26: Safety, Process, And Ergonomic Improvements

Storage Shed

OSHA compliant and organized!

Page 27: Safety, Process, And Ergonomic Improvements

Before

Bead Bundles stored outside on racks, which Team Members have to climb up to get Bead down.

Page 28: Safety, Process, And Ergonomic Improvements

Bead Bundles are now stored inside on a new cart, this gives Team Members easy access to bead when they need it.

After

Page 29: Safety, Process, And Ergonomic Improvements

Before

Team Members pulling and sliding heavy garbage bins across floor to dumpster.

Page 30: Safety, Process, And Ergonomic Improvements

After: New Bin Dollies

Page 31: Safety, Process, And Ergonomic Improvements

Before and After

• Balances on the floor

• Balances now on a new rack

Page 32: Safety, Process, And Ergonomic Improvements

Before

• Balances on the floor

Page 33: Safety, Process, And Ergonomic Improvements

After

• New Balance Rack

Page 34: Safety, Process, And Ergonomic Improvements

Before and After

• Wooden Step Stool • New ANSI approved Step Stool

Page 35: Safety, Process, And Ergonomic Improvements

New Battery Charging and Eye Wash Stations

Page 36: Safety, Process, And Ergonomic Improvements

New Machine Guarding

Page 37: Safety, Process, And Ergonomic Improvements

New Machine Guarding

Page 38: Safety, Process, And Ergonomic Improvements

New Machine Guarding

Page 39: Safety, Process, And Ergonomic Improvements

Before and After

Manually Lifting No More Lifting

Page 40: Safety, Process, And Ergonomic Improvements

Custom Tools

Page 41: Safety, Process, And Ergonomic Improvements

Modified Equipment

Page 42: Safety, Process, And Ergonomic Improvements

Carts

Page 43: Safety, Process, And Ergonomic Improvements

Carts

Page 44: Safety, Process, And Ergonomic Improvements

Solid Works

Page 45: Safety, Process, And Ergonomic Improvements

Solid Works

Page 46: Safety, Process, And Ergonomic Improvements

Thank You