124
Discretio nary Dependenc y Cost of Quality (COQ) Summary Activity Baseline Activity Splitting Gantt Chart PMP EXAM FLASHCARDS By Jonathan Donado Over 500 dynamic Flashcards in PowerPoint PART 3 of 5

PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Embed Size (px)

Citation preview

Page 1: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

DiscretionaryDependency

Cost ofQuality (COQ)

Summary Activity

Baseline

ActivitySplitting

Gantt Chart

PMP EXAM FLASHCARDS

By Jonathan Donado

Over 500 dynamic Flashcards in PowerPoint

PART 3 of

5

Page 2: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

52

About me

Linkedin.com/in/jonathandonado

www.branded.me/jonathandonado

Twitter.com/donadosays

Bilingual senior general management executive with expertise in international

business and Mergers & Acquisitions (M&A)

If you like the Flashcards, please give a ”Like” in SlideShare. It’s much appreciated !

o Education: - Senior Executive Fellow – Harvard University- MBA – IESE

o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- Agile (ACP) – PMI Certified

Jonathan Donado

Page 3: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ManageCommunications

Process of making needed information available to project

stakeholders in a timely manner

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 4: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Mandatory Dependency

An activity that is dependent upon another activity. For example, a telephone pole must be put up before telephone

wire can be strung

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 5: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ManagementReserve

Time or money that management sets aside

in addition to the schedule or cost baseline

and releases for unforeseen work that is within the scope of the

project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 6: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

MasterSchedule

A summary level project schedule that identifies the major deliverables and work breakdown schedule components

and key schedule milestones

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 7: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

MatrixOrganization

An organizational structure in which the

project manager shares authority with the

functional manager temporarily to assign

work and apply resources

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 8: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

MaximumNumber of Segments

This value specifies the maximum number of

segments that an activity can be split into when

activity splitting is allowed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 9: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Methodology

Used to define the processes, policies, and

guidelines that are included as part of the framework for project

management

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 10: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Milestone

A significant point or event in a project,

program, or portfolio

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 11: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

MilestoneSchedule

A type of schedule that presents

milestones with planned dates

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 12: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Minimum Segment Duration

This value specifies the minimum duration

of a segment of an activity when activity

splitting is allowed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 13: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Mission Statement

A concise statement, usually one paragraph, summarizing what the

project is about and what it will accomplish

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 14: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Mitigation

Taking steps to lessen risk by lowering the probability of a risk

event's occurrence or reducing its effect

should it occur

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 15: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Monitor and Control Project

Risk

Tracking, reviewing, evaluating and directing the

progress to meet the performance objectives

defined in project documentation such as

Project Charter and/or in the SOW

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 16: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Monitor and Control Risk

Developing and implementing risk response

plans, tracking and evaluating identified risks, monitoring

residual risks, identifying new risks and opportunities, and

continual assessment of risks throughout the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 17: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Monitoring

The capture, analysis, and reporting of project performance, usually as

compared to plan

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 18: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Monte CarloAnalysis

A technique that uses computer software to simulate the outcome

of a project more accurately

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 19: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Most LikelyDuration

An estimate of the most probable activity

duration that takes into account all of the known

variables that could affect performance

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 20: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Near-CriticalActivity

An activity with a total float that is deemed to be low based on

expert judgment

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 21: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Near-CriticalPath

A sequence of activities with low float which, if exhausted, becomes a critical path sequence

for the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 22: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

NegativeVariance

The negative number that results from comparing planned

project results with actual project results. A negative

variance in the project schedule indicates the project is behind

schedule. A negative variance in the budget indicates the project

is over budget

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 23: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

NetworkAnalysis

The process of identifying early and late start and finish dates for

the uncompleted portions of project

activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 24: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

NetworkDiagram

A schematic display of the logical relationships

of project activities. Always drawnfrom left to

right to reflect project chronology. Often

incorrectly referred to as a"PERT chart"

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 25: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

NetworkPath

Any continuous series of connected activities that make up a project

network diagram

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 26: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Node

A point at which dependency lines

connect on a schedule network diagram

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 27: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Non-StandardLogical

Relationship

A dependency between two project activities that is not

the standard finish to startrelationship

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 28: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Nominal Group Technique

A technique that enhances brainstorming

with a voting process used to rank the most useful ideas for further

brainstorming

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 29: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OPM3

PMI’s organizational project management

maturity model (acronym)

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 30: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Operations and Maintenance

The turnover of a project to the

operational staff of an organization for ongoing

support and maintenance

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 31: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Operations vs. Project

Management

Operations is ongoing work to support the

business like manufacturing. Project work creates a unique product/service, it is temporary and ends when the project is

closed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 32: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Opportunity

A chance to increase project benefits. A risk

that would have a positive effect on one

or more project objectives

See also: issue, risk, and threat

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 33: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OpportunityCost

The opportunity given up by choosing to do

one project over another one

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 34: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OptimisticDuration

An estimate of the shortest activity

duration that takes into account all of the

known variables that could affect

performance

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 35: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Order of Magnitude Estimate

A high-level estimate usually made during the initiation phase that assigns a cost

estimate range to the project based on a completed similar

project. This estimate typically falls between - 25%

and +75% of the actual budget

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 36: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OrganizationalBreakdown

Structure (OBS)

A hierarchical representation of the project organization, which illustrates the

relationship between project activities and the organizational units that

will perform those activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 37: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OrganizationalEnabler

A structural, cultural, technological, or human‐resource practice that the performing organization

can use to achieve strategic

objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 38: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OrganizationalPlanning

Consists of defining team member responsibilities,

roles, and reporting structure, and preparing the staffing management

plan

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 39: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OrganizationalProcessAssets

Plans, processes, policies, procedures, and knowledge bases

specific to and used by the performing

organization

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 40: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OrganizationalProject

Management

A framework in which portfolio, program, and

project management are integrated with

organizational enablers in order to achieve strategic objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 41: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

OrganizationalProject

ManagementMaturity

The level of an organization’s ability to

deliver the desired strategic outcomes

in a predictable, controllable, and reliable manner

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 42: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Output

The outcome or end result of a process

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 43: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ParametricEstimating

An estimating technique in which an algorithm is used to calculate cost or duration based on

historical data and project parameters

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 44: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Pareto Chart

A graph that is used to rank the importance of

aproblem by the frequency with which it

occurs

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 45: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Path

A set of sequentially connected activities in

a project network diagram.

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 46: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PathConvergence

A relationship in which a schedule

activity has more than one predecessor.

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 47: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PathDivergence

A relationship in which a schedule

activity has more than one successor.

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 48: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PercentComplete

An estimate expressed as a percent of the amount

of work that has been completed on an activity

or a work breakdown structure component

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 49: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PerformanceMeasurement

Baseline

Integrated scope, schedule, and cost baselines used for

comparison to manage, measure, and control project

execution

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 50: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PerformanceQuality

Assurance

Process of auditing quality requirements and results of quality control measurements to ensure

quality standards/ operational definitions

are used

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 51: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PerformanceReporting

Collecting and disseminating

information about project performance to help

ensure project progress

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 52: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PerformingOrganization

An enterprise whose personnel are the most

directly involved in doing the work of the

project or program

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 53: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PessimisticDuration

An estimate of the longest activity duration that takes into account

all of the known variables that could affect performance

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 54: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PDM (AON)

A diagramming technique where

activities are represented by nodes,

and arrows represent the sequence

Explanation: Precedence diagramming method (PDM) is a network diagramming technique in which activities are represented by boxes (or nodes). Activities are linked together by precedence relationships to show the sequence in which the activities are to be performed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 55: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Performance Reporting

Reporting to the stakeholders to provide information about the

project’s status, progress, accomplishments and

future project performance predictions

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 56: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PERTChart

Technique that computes weighted

average of optimistic, pessimistic and most likely estimates for

activity duration/cost

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 57: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Phase

A distinct stage of the project or lifecycle. There

are btypically four phases in a project management lifecycle: Initiation and

scope definition; planning; execution, control and

coordination; and closure, acceptance an dsupport

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 58: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PhaseGate

A review at the end of a phase in which

a decision is made to continue to the next

phase, to continue with modification, or to end

a project or program

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 59: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PlannedValue (PV)

The authorized budget assigned to scheduled

work

Explanation: The sum of the approved cost estimates including any overhead allocation) for activities (or portions of activities) scheduled to be performed during a given period (usually project-to-date)

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 60: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Policy

A succinct statement that gives direction to state organizations to

support IT implementation. Policies are high-level, overall statements that do not dictate

specific procedural steps or processes. Directives issued by management for guidance and direction where uniformity of

action is essential.

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 61: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Portfolio

Projects, programs, subportfolios, and

operations managed as a group to achieve strategic objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 62: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PortfolioBalancing

The process of optimizing the mix of portfolio components to further the strategic

objectives of the organization

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 63: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PortfolioCharter

A document issued by a sponsor that

authorizes and specifies the portfolio structure

and links the portfolio to the organization’s

strategic objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 64: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PortfolioManagement

The centralized management of one or more portfolios to

achieve strategic objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 65: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PortfolioManagement

Plan

A document that specifies how a portfolio will be

organized, monitored, and controlled

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 66: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PortfolioManager

The person or group assigned by the

performing organization to establish, balance, monitor, and control

portfolio components in order to achieve strategic

business objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 67: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PositiveVariance

The positive number that results from comparing

planned project results with actual project results. A positive variance in the

project schedule indicates the project is ahead of schedule.

A positive variance in the budget schedule indicates the

project is under budget

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 68: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Post-Implementation

Evaluation Report

Documents the successes and failures of the project. It provides a

historical record of the planned and actual budget and schedule.

Other selected metrics on the project can also be collected based

upon state organization procedures. The report also

contains recommendations for other projects of similar size and

scope.

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 69: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PrecedenceDiagraming

Method (PDM)

A technique used for constructing a schedule

model in which activities are represented by nodes and

are graphically linked by one or more logical relationships

to show the sequence in which the activities are

to be performed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 70: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PrecedenceRelationship

The term used in the precedence diagramming

method (PDM) for a logical relationship. In current usage,

however, precedence relationship, logical relationship,

and dependency are widely used interchangeably regardless of the diagramming method in

use

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 71: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PredecessorActivity

An activity that logically comes before a dependent activity

in a schedule

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 72: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

PreventiveAction

An intentional activity that ensures the future

performance of the project work is aligned

with the project management plan

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 73: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Priority

The imposed sequences desired with

respect to the scheduling of activities

with inpreviously imposed constraints.

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 74: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Probability & Impact Matrix

A grid for mapping the probability of

occurrence of each risk and its impact

on project objectives if that risk occurs

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 75: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Procedure

Used to define a collection of steps that the

organization is responsible for implementing to ensure

that policies and process requirements are met. The agency may use guidelines

to develop these procedures

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 76: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Process

A set of interrelated actions and activities

performed to achieve a pre-specified set of products, results, or

services

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 77: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProcurementManagement

Plan

A component of the project or program

management plan that describes the process of how a team will acquire goods and services from

outside of the organization

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 78: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProcurementPlanning

The process of determining which goods and services should be purchased or

performed outside of the organization and outlines the details of what, how

and when the goods should be acquired

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 79: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProcurementSOW

Describes procurement in sufficient detail to allow

sellers to determine if they are capable of providing product, services or results

Note: SOW = Statement of Work

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 80: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Product General terms used to

define the end result of a project delivered to a

customer

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 81: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Product Description Statement

A non-formal, high level document that describes the characteristics of the

product/process to be created

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 82: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Product LifeCycle

The series of phases that represent the evolution

of a product, from concept through delivery, growth, maturity, and to

retirement

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 83: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Product Scope

The features and functions that

characterize a product, service or result

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 84: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Product Verification

Ensuring the stakeholders find the key deliverables to be

satisfactorily completed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 85: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Program

A group of related projects, subprograms, and program activities that are managed in a

coordinated way to obtain benefits not

available from managing them individually

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 86: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProgramCharter

A document issued by a sponsor that authorizes the program management team

to use organizational resources to execute the

program and links the program to the

organization’s strategic objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 87: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Program Evaluation and

Review Technique(PERT)

A technique used to estimate project duration through a

weighted average of optimistic, pessimistic, and most likely

activity durations when there is uncertainty with the individual

activity estimates

Explanation: A weighted average time estimate of project duration using optimistic (O), pessimistic (P) and most likely (ML) estimates of project duration. Also known as three point estimating. PERT = O + (4)ML + P

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 88: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProgramManagement

The application of knowledge, skills, tools, and

techniques to a program to meet the program

requirements and to obtain benefits and control not available by managing projects individually

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 89: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProgramManagement

Office

A management structure that standardizes the

program related ‐governance processes and facilitates the sharing of

resources, methodologies, tools, and techniques

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 90: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProgramManagement

Plan

A document that integrates the program’s subsidiary plans and establishes the management controls and overall plan for integrating

and managing the program’s individual

components

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 91: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProgramManager

The person authorized by the performing

organization to lead the team or teams

responsible for achieving program

objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 92: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProgressAnalysis

The evaluation of progress against the

approved schedule and the determination of its impact. For cost, this is

the development of performance indices

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 93: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProgressiveElaboration

The iterative process of increasing the level

of detail in a project management plan as greater amounts of

information and more accurate estimates become available

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 94: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Project

A temporary endeavor undertaken to create a

unique product, service, or result

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 95: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Project Administration

Entails making Project Plan modifications that may result from

such things as: new estimates of work still to be done, changes in scope/functionality of end

product(s),resource changes and unforeseen circumstances. It also involves monitoring the various

Execution Phase activities, monitoring risks, status reporting, and

reviewing/authorizing project changes as needed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 96: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectBudget

The sum of work package cost estimates,

contingency reserve, and management

reserve

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 97: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectCalendar

A calendar that identifies working days and shifts

that are available for scheduled activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 98: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectChampion

An individual, who believes in, understands and supports the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 99: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectCharter

A document issued by the project initiator or sponsor that formally authorizes the

existence of a project and provides the project

manager with the authority to apply organizational

resources to project activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 100: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectCommunications

Management

A subset of project management that includes the processes required to ensure proper

collection and dissemination of project information. It consists of communications planning,

information distribution, performance reporting, and

administrative closure

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 101: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectCoordinator

The person similar to the Project Expediter except

the Coordinator has some power to make decisions,

some authority and reports to a higher-level

manager

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 102: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectExpediter

The person who acts primarily as a staff

assistant and communications

coordinator. It has not power to make

decisions

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 103: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectInitiation

Document

It is the same as the Project Charter. It

authorizes the start of the project by the

Sponsor

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 104: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectizedOrganization

An organizational structure in which the

project manager has full authority to assign work

and apply resources

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 105: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectLife Cycle

The series of phases that a project passes

through from its initiation to its closure

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 106: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectManagement

The application of knowledge, skills, tools,

and techniques to project activities to

meet the project requirements

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 107: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectManagementInformation

Systems (PMIS)

The tools and techniques used to

gather, integrate and disseminate the

outputs of project management processes

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 108: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectManagementOffice (PMO)

A management structure that standardizes the

project related governance ‐processes and facilitates the sharing of resources,

methodologies, tools, and techniques

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 109: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectManagement

Plan

The document that describes how the

project will be executed, monitored and

controlled, and closed

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 110: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectManager

The person assigned by the performing

organization to lead the team that is responsible for

achieving the project objectives

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 111: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectPerformance

Indicators

Measures to determine whether the project is

on track

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 112: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectPhase

A collection of logically related project activities

that culminates in the completion of one or

more deliverables

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 113: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectSchedule

An output of a schedule model that presents linked activities with

planned dates, durations, milestones,

and resources

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 114: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

ProjectScheduleNetwork Diagram

A graphical representation of the logical relationships among the project schedule activities

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 115: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Project Scope

The work performed to deliver a product,

service, or result with the specified features

and functions

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 116: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Project ScopeStatement

The description of the project scope, major

deliverables, objectives, assumptions, and

constraints

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 117: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Project Selection

Determining which proposed projects

should move forward

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 118: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Project TimeManagement

Process required to accomplish timely completion of the

project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 119: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Proof ConceptA project that attempts

to prove whether an activity or an idea can

be accomplished

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 120: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Prototype

A technique of producing an example

of the finished product, service or

result to seek feedback from stakeholders

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 121: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Published Estimating Data

A database of known quantities or costs

relating to the completion of activities

in the project

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 122: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Pull Communication

A form of communication where

information is downloaded and

accessed by receivers when they want it

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 123: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

Push Communication

A form of communication where information is sent to

the receiver

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 124: PMP Exam Flashcards presentation 3 of 5 ( PMBOK - 5th Edition - PMI ) Download it in PowerPoint

52

Connect with me

Linkedin.com/in/jonathandonado

www.branded.me/jonathandonado

Twitter.com/donadosays

Bilingual senior general management executive with expertise in international

business and Mergers & Acquisitions (M&A)

If you like the Flashcards, please give a ”Like” in SlideShare. It’s much appreciated !

o Education: - Senior Executive Fellow – Harvard University- MBA – IESE

o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- Agile (ACP) – PMI Certified

Jonathan Donado

> Check my other Project Management presentations on SlideShare <

THANK YOU