Heather Davies – Project ManagerGraham Smith – Technical Lead

Oxfam FSCM 9.2

Upgrade Experiences

2/19

3/19

4/19

Who am I?

• Graham Smith

• PeopleSoft Technical Lead

• 18 years at Oxfam

• http://i-like-trains.blogspot.com

5/19

• PeopleSoft since 1999

• FSCM 9.2 (60+ countries 2,000+ users)

• HR 9.0 (1,200+ users)

• Microsoft Platform

• 10 functional/technical

PeopleSoft @ Oxfam

6/19

Agenda

•9.2 Upgrade Drivers

•The Plan

•Approach

•Recustomisation

•Lessons Learned

•Opportunities Created

7/19

9.2 Upgrade Drivers

• Application & Platform Support

• New 9.2 & 8.53 functionality

• Create platform for new opportunities

8/19

The Plan

Exposure to 9.2

Build Servers Test & Fix

Develop Training

Initial Pass Recustomise8.53 Beta

20142012 2013

MTP 1 - 6

Code

freeze

Go

Live

9/19

Approach

• Identify Key Business Contacts

– Get buy-in

– Make decisions

– Promote PeopleSoft

– Coordinate Testing

– Small group

• Demo new features

• Like for Like upgrade

10/19

What we learned

• Use PUM Images to learn 9.2 Apps

• PeopleSoft Release Notes & PeopleBooks

• PeopleTools 8.53

– PeopleSoft Selective Adoption

– Perform Initial Upgrade Pass

– WorkCentres

– Secure Enterprise Search

11/19

Technical Approach

• Learn – Exposure to Apps and Tools

• Initial Pass

• Analyse Customisations

• Re-apply all customisations and test

12/19

9.2 Recustomisation

and bug fixing

Development Process

Development

8.9

UAT

8.9

Development

9.2

Essential

8.9 development

Production

8.9

Demo

9.2

Upgrade

to 9.2

Initial Pass

MT

P

Freeze

development

Image

9.2.xPUM Updates

PUM Updates

Upgrade UAT

9.2

Test

13/19

Upgrade Weekend

• Shutdown 5pm Thursday & completed

transactions

• CA Upgrade Job (21 hours)

• Post Upgrade Database re-index & statistics

• Testing 10am – 5pm Saturday

14/19

Recustomisation

• Identify customised definitions

– Use data gathered from Performance Monitor

– Inspect meta data

– Review own documentation

15/19

Recustomisation

• Identify customised definitions

• Identify deprecated and new definitions

in 9.2

– Use the delivered Demo 8.9 to 9.2 compare

reports

– Tools only upgrade to copy of production

• Compare with latest Demo 9.2 Image

16/19

Recustomisation

• Identify customised definitions

• Identify deprecated definitions in 9.2

• Decide to

– Re-apply

– Drop

– Re-design/re-think

17/19

Recustomisation

• Identify customised definitions

• Identify deprecated definitions in 9.2

• Decide to

–Re-apply

–Drop

–Re-design/re-think

• Do customisations in defined order

– Means some testing can be done in parallel

18/19

Lessons Learned

• SES consumed more time than expected

– Performance issues

• PUM was hard work

• Froze on Image 005

– Should have kept a closer eye on new updates

• WorkCentre Issues

– Age = Maturity !

• Database upgrade

• Browser Issues

19/19

• SES Attachment Indexing (350,000 Files)

• SES Related Actions

• Emailing BACS remittances

• Requisition Workflow in PO

• Expanding use of WorkCentres

• Pivot grids for some Queries

• Activity Guides for some Project phases

Opportunities Created