Optimizing wind farm construction logistics

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 1 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Optimizing Wind Farm Construction Logistics

Page 2: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 2 / 64

The Company (Ballast Nedam)

• Amsterdamsche Ballast Maatschappij: 1877

• Nederlandse Aannemings Maatschappij: 1899

• Merged into Ballast Nedam: 1969

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 3: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 3 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

The Company (Ballast Nedam)

Page 4: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 4 / 64

Offshore Windfarm Lely - Engineering, supply and installation of 4 foundations

Offshore Windfarm Dronten / Irene Vorrink - Engineering, supply and installation of 28 foundations

Offshore Wind – The Early Years

32 foundations

1994 / 1996

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 5: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 5 / 64

Offshore Wind Farm Egmond aan Zee

69 foundations

2006

Turn-key delivery of an Offshore Wind Farm in joint venture with Vestas. - Engineer, supply and installation of 37 foundations (1

xMeteo Mast, 36 turbine foundations. - All offshore installations (foundations, turbines and

cables) - 50% Electrical Scope

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 6: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 6 / 64

Rhyl Flats Offshore Wind Farm

94 foundations

2008

Installation of 25 foundations at the Rhyl Flats Offshore Wind Farm in the Irish Sea. Monopiles transported floating, transition piece transported vertical on barges.

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 7: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 7 / 64

Gunfleet Sands Offshore Wind Farm

126 foundations

2009

Installation of 32 foundations at the Gunfleet Sands Offshore Wind Farm. Installation started during the 2nd half of 2008 and was finalised during the first months of 2009. Both monopiles and transition pieces were transported on barges towards the HLV Svanen

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 8: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 8 / 64

Belwind, Sheringham Shoal and Baltic I

228 foundations

2010

Installation of 56 monopiles at the Belwind Offshore Wind Farm. Started in 2009, finalised in Q1/2010 Installation of 24 foundations at the Sheringham Shoal Offshore Wind Farm. Design and installation of 22 foundations at the Baltic I Offshore Wind Farm in Germany. Installation with jack-up vessel

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 9: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 9 / 64

Walney 2 and London Array Offshore Wind Farms

Logistics and installation of 51 monopiles at the Walney 2 Offshore Wind Farm. Floating transport of heaviest monopiles so far in offshore wind. Maximum weight up to 805 tons. Installation of 11 foundations at London Array ,monopile and transition piece, at shallow locations beyond the limitation of the projects existing installation vessels, Seaworker and Adventure

290 found.

2011

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 10: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 10 / 64

Future Projects (2012/2013)

Installation of 111 monopiles at the Anholt Offshore Wind

Farm in Denmark during 2013

Engineering, supply and installation of 80 foundations at

the Butendiek Offshore Wind Farm in Germany during 2013.

481 found.

2013

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 11: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 11 / 64

Overview designed and installed foundations - 2011

Number of foundations 290 Designed by Ballast Nedam 91 Installed by Ballast Nedam 290 Installed by HLV Svanen 235 Number of monopiles 290 Number of transition pieces 148

Type of contracts Installation contracts Engineering and installation contracts Full EPC foundation contracts Turn-key offshore wind farm project

Track record - On time - 100% availabilty - Reliable cycle times

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 12: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 12 / 64

Project Example: Walney 2 Offshore Wind Farm (Summer 2011)

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 13: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 13 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Walney 2 Offshore Wind Farm (Logistics summary)

Page 14: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 14 / 64

Onshore Operations (Site Barrow-in-Furness UK)

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 15: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 15 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Onshore Operations (Site Barrow-in-Furness / UK)

Page 16: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 16 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Onshore Operations (Logistical flow)

Page 17: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 17 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Onshore Operations (Launching Monopiles)

Page 18: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 18 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Onshore Operations (Launching Monopiles)

Page 20: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 20 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Transport to Site (Floating Monopiles)

Page 21: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 21 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Transport to Site (Transition Pieces on barges)

Page 22: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 22 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Docking Monopile)

Page 23: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 23 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Upending Monopile)

Page 24: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 24 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Upending Monopile)

Page 25: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 25 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Releasing Plugs & Pile Contingency Floatation Units)

Page 26: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 26 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Releasing plugs & Pile Contingency Floatation Units)

Page 27: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 27 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Hammering Monopile)

Page 28: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 28 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Hammering Monopile)

Page 29: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 29 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Offshore Operations (Transition Piece Installation)

Page 30: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 30 / 64

Weather Conditions / Working Windows

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Page 31: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 31 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Weather Conditions / Working Windows

Page 32: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 32 / 64

Gross cycle time :

- net cycle time

- unworkable weather

- (logistic) delays

Focus

3 weeks of delay during the project can easily results in 8

weeks delay at the end which is 1/3 of the onshore and

offshore running cost

1

24 w eeks

October November

2

3

8

April May June July August September

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Weather Conditions / Working Windows

Page 33: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 33 / 64

3

2

1

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Project Engineering Solutions (Feeding concepts)

Page 34: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 34 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Project Engineering Solutions (Rigging & Temporary Works)

Page 35: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 35 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Human Resources (mixing experience & ambitions)

Page 36: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 36 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Human Resources (1-BN concept / in-house specialities)

Page 37: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 37 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Planning & Logistics (Traditional Planning)

Page 38: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 38 / 64

,0

1,0

2,0

3,0

4,0

5,0

6,0

7,0

8,0

9,0

10,0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

du

rati

on

(d

ays)

foundation (1 to 56)

Progress HLV Svanen + floating piles(Bligh Bank Offshore Wind Farm from 01 Sep 2009 to 05 Feb 2010)

nett duration (20% / average 12,5hrs) logistical delay (13%) repairs (1%) unworkable weather (66%)

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Planning & Logistics (Relevant Factors: nett. duration / logistical delays / repairs / weather)

Page 39: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 39 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling

Page 40: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 40 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data)

Page 41: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 41 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data)

Page 42: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 42 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: substructure components)

Page 43: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 43 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: substructure components)

Page 44: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 44 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: substructure components)

Page 45: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 45 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: marine spread)

Page 46: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 46 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: marine spread)

Page 47: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 47 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: sub-cycle times / durations)

Page 48: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 48 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: sub-cycle times / durations)

Page 49: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 49 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: local conditions)

Page 50: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 50 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: local conditions)

Page 51: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 51 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: local conditions)

Page 52: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 52 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Input data: weather)

Page 53: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 53 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Output)

Page 54: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 54 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Output: utilization rates)

Page 55: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 55 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Output: cycle time charts)

Page 56: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 56 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Output: waiting times)

Page 57: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 57 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Output: resource tracking)

Page 58: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 58 / 64

Base case Weather 2005 lock gates < 2.5h 6m MP´s only 6.5m MP´s first no buffer nett cycle 12.5hr cycle 12,5 + >

speed TT

cycle 12,5 + > speed TT + extra

6.5m plug

belwind variance on Svanen nett

cycle

1 project duration (day) 34 66 38 33 52 41 33 28 27 39

2 nett cycletime (hrs) 16 40 18 15 22 20 15 13 13 18

3 occupancy SVANEN (%) 82% 73% 73% 85% 60% 67% 68% 79% 82% 55%

4 occupancy AHT’s (%) 29% 11% 20% 32% 14% 13% 24% 36% 38% 6%

5 occupancy Transportation Tug (%) 93% 60% 95% 94% 86% 97% 95% 93% 93% 97%

6 occupancy Harbor Tug (%) 31% 10% 43% 18% 54% 80% 68% 56% 18% 11%

7a occupancies 6.0m plugs (%) 49% 43% 45% 9% 47% 47% 39% 44% 61% 47%

7b occupancies 6.3m plugs (%) 42% 19% 46% 0% 44% 49% 35% 36% 70% 47%

7c occupancies 6.5m plugs (%) 98% 98% 100% 0% 45% 99% 99% 97% 53% 100%

8 occupancy towage beams (%) 62% 80% 63% 93% 5% 69% 72% 67% 17% 68%

10 occupancy onshore equipment (60t crane) (%) 23% 12% 20% 24% 17% 19% 23% 27% 28% 19%

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling (Sensitivity analysis)

Page 59: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 59 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Modelling

Page 60: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 60 / 64

Walney 2

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

24 hour time lapse movie available at:

www.youtube.com/watch?v=YIAovkexkYo

Page 61: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 61 / 64

A total of 1,247 offshore turbines are now installed and grid connected in European waters, bringing total installed capacity to 3,294MW, spread across 49 wind farms in nine European countries.

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Developments Offshore Wind

Page 62: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 62 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Future Locations

Page 63: Optimizing wind farm construction logistics

Hosted by:

01 November 2011, 63 / 64

who we are what we did how we do it critical factors mastering logistics all comes together future challenges

Logistical Challenges

Page 64: Optimizing wind farm construction logistics