56
Holcim Cement Pre-Engineered Office Building Presented by: Wes Villhard – Kozeny-Wagner VP Commercial Construction Tom Way – WGA Senior Engineering Manager

Office Building Constructed in Nine Weeks !

Embed Size (px)

DESCRIPTION

25,000SF Pre-Engineered Office Building Completed in 9 weeks for Holcim Cement & WGA

Citation preview

Page 1: Office Building Constructed in Nine Weeks !

Holcim Cement

Pre-Engineered Office Building

Presented by:

Wes Villhard – Kozeny-Wagner VP Commercial Construction

Tom Way – WGA Senior Engineering Manager

Page 2: Office Building Constructed in Nine Weeks !

Success Thru Best Practices

Front End Planning

Materials Management

Team Building

Partnering

Page 3: Office Building Constructed in Nine Weeks !

Front End Planning

Pre-Engineered Building

Architecture & Engineering

Mechanical / Electrical

Interior Finish

Project Team

Page 4: Office Building Constructed in Nine Weeks !

Pre-Engineered Building

Pre-Ordered American Metal Building

Released without Door & Window Trim

“In-Stock” Center Support Building

Early Delivery in order to Build Frames During Slab Pour

Page 5: Office Building Constructed in Nine Weeks !

Architecture & Engineering

Completed Foundation Design from Pre-Engineered

Building Loads

Ordered Rebar for Foundations before Slab Design was

Complete

Pre-Approved Concrete Mix Design

Allowed Two Weeks for Architectural Design

Page 6: Office Building Constructed in Nine Weeks !

Mechanical / Electrical

Ordered “In-Stock” Ground Mounted Split Systems

Saved Engineering Time for Roof Frames

Electrical Rough-in of Slab vs. Overhead

Saved Two Weeks on Schedule

Page 7: Office Building Constructed in Nine Weeks !

Mechanical / Electrical

HighBay Lighting for Open Office Areas

Reusable for Future Warehouse

Duct Socks Reduced Field Labor

Prefabed All Ductwork

Installed Ductwork Prior to Roofing

Page 8: Office Building Constructed in Nine Weeks !

Interior Finish

Panelized Office Walls During Floor Slab Pours

Install Studs Prior to Roofing

Ordered only “In-Stock” Material

Windows, Doors, Hardware, Toilet Partitions, Accessories, etc.

Allowed Sealed Concrete Floors Rather than VCT or Other Flooring

Coordinated all Interior Work with Roof Installation

One Side then the Other

Page 9: Office Building Constructed in Nine Weeks !

Project Team

Selected Only Subs with Available Manpower

Past Performance “Can-do” Attitude

Subcontractors- Foreman & Project Manager

Kozeny-Wagner - Foreman & Project Manager

Teamwork, Find Solutions

Overcome Obstacles

Go the Extra Mile

Page 10: Office Building Constructed in Nine Weeks !

Week 1 – Prefab Foundation Rebar

During Building Layout

Page 11: Office Building Constructed in Nine Weeks !

Week 1 – Bad Soils & Rock

Encountered

Page 12: Office Building Constructed in Nine Weeks !

Week 1 – Rock Encountered

Page 13: Office Building Constructed in Nine Weeks !

Week 1 – Foundations Started

Page 14: Office Building Constructed in Nine Weeks !

Week 1 – PreFabed Rebar in Perimeter

Foundations

Page 15: Office Building Constructed in Nine Weeks !

Week 2 – Foundation Complete and

Backfilled

Page 16: Office Building Constructed in Nine Weeks !

Week 2 – Slab Rough-in, Electrical &

Plumbing

Page 17: Office Building Constructed in Nine Weeks !

Week 2 – Rebar For Heavy Duty Slab,

Delivered & Installed

Page 18: Office Building Constructed in Nine Weeks !

Week 3 – Slab Pour, Steel Material Deck

Delivered in the Background

Page 19: Office Building Constructed in Nine Weeks !

Week 3 – Rain Pushed First Slab Pour

Late Into the Night

Page 20: Office Building Constructed in Nine Weeks !

Week 3 – Second Slab Pour

Page 21: Office Building Constructed in Nine Weeks !

Week 4 – Plumbing Rough-in Started

Immediately with Wall Layout

Page 22: Office Building Constructed in Nine Weeks !

Week 4 – Steel Erection in Progress

Using Pre-Assembled Frames

Page 23: Office Building Constructed in Nine Weeks !

Week 4 – Center Support vs Clear-Span

Steel Used for Early Delivery

Page 24: Office Building Constructed in Nine Weeks !

Week 4 – Building Frame Complete

Page 25: Office Building Constructed in Nine Weeks !

Week 5 – Roof Perlins Complete and

Duct Hangers In Progress

Page 26: Office Building Constructed in Nine Weeks !

Week 5 – Ductwork Delivered

Page 27: Office Building Constructed in Nine Weeks !

Week 5 – Plumbing Rough-In

In Progress

Page 28: Office Building Constructed in Nine Weeks !

Week 5 – Ductwork & West End & Side

Wall

Page 29: Office Building Constructed in Nine Weeks !

Week 5 – Exterior HVAC Units Set, Roof

Insulation & Roof Panels In Progress

Page 30: Office Building Constructed in Nine Weeks !

Week 5 – Roof Insulation, Roof Panels,

Widows & Exterior Framing In Progress

Page 31: Office Building Constructed in Nine Weeks !

Week 5 – Exterior View of Roof Insulation,

Window Framing & Ductwork / AC Units

Page 32: Office Building Constructed in Nine Weeks !

Week 6 – Close-up of Roof Panels

In Progress

Page 33: Office Building Constructed in Nine Weeks !

Week 6 – Ceiling Grid-Continuous,

Prior to Perimeter Offices

Page 34: Office Building Constructed in Nine Weeks !

Week 6 – First Panelized Office

Page 35: Office Building Constructed in Nine Weeks !

Week 6 – Exterior Office Framing,

Acoustical Grid, Prior to Roof Panels

Page 36: Office Building Constructed in Nine Weeks !

Week 6 – Roof Insulation & Roof Panels

Continue to the Far End of the Building

Page 37: Office Building Constructed in Nine Weeks !

Week 6 – One Side of Roof Complete,

Framing / MEP Rough-in In Progress

Page 38: Office Building Constructed in Nine Weeks !

Week 7 – High Bay Lights Above Open

Office Areas

Page 39: Office Building Constructed in Nine Weeks !

Week 7 – Roof Deck Delayed by High

Winds 1- 2 Weeks, Nearly Complete

Page 40: Office Building Constructed in Nine Weeks !

Week 7 – Exterior Panes / Windows

Nearly Complete

Page 41: Office Building Constructed in Nine Weeks !

Week 7 – Exterior Wall Panels Complete

Page 42: Office Building Constructed in Nine Weeks !

Week 7 – Exterior Duct Work Complete,

Power On! Test & Balanced Started.

Page 43: Office Building Constructed in Nine Weeks !

Week 7 – Duct Socks Installed to

Reduce Field Labor

Page 44: Office Building Constructed in Nine Weeks !

Week 7 – Sheetrock and Restrooms

In Progress

Page 45: Office Building Constructed in Nine Weeks !

Week 7 – Drywall / Doors / Hardware In

Progress, Preparing for Work Stations

Page 46: Office Building Constructed in Nine Weeks !

Week 8 – Work Stations In Progress, Flex

Duct / Diffusers Installed, Lights / HVAC On

Page 47: Office Building Constructed in Nine Weeks !

Week 8 – Painting Nearly Complete

Page 48: Office Building Constructed in Nine Weeks !

Week 9 – Project Complete

Page 49: Office Building Constructed in Nine Weeks !

COMPLETED IN

9 WEEKS!

Page 50: Office Building Constructed in Nine Weeks !

Project Summary

Design-Build Delivery

Half the Time of a Typical Schedule

32 Private Offices, 5 Conference Rooms and

90 Workstations

Critical Path – “Fast-Track” Mode

10-12 Hour Days

7 Days / Week

Page 51: Office Building Constructed in Nine Weeks !

Project Summary

$240,000 in Change Orders

$79 / Square Foot Total

45 Normal Working Days (9 Weeks M-F)

Less 16 Weather Days

Page 52: Office Building Constructed in Nine Weeks !

Safety Award

“On the Spot” WGA Safety

Award Given to Dan Fox of

Kozeny-Wagner.

MSHA Award – Recognized by

the South Central Region of the

Federal Mine Safety & Health

Administration for Outstanding

Safety Compliance &

Accomplishment.

Page 53: Office Building Constructed in Nine Weeks !

Success Thru Best Practices

Front End Planning

Materials Management

Team Building

Partnering

Page 54: Office Building Constructed in Nine Weeks !

Thank You Project Team!

Aschinger Electric

Bieg Plumbing Company

Fenix Construction Company

Frontenac Painting, Inc.

Grau Contracting, Inc.

Jarrell Contracting

Paul Abt Flooring

Rednour Steel Erectors, Inc.

Zumwalt Corporation

Wedemeyer/Cernik/Corrubia, Inc.

Zahner Surveying

A.F. Becker

CKC Woodworks, Inc.

H&G Sales

St. Louis Steel Buildings

Page 55: Office Building Constructed in Nine Weeks !

A Special Thanks to

Holcim Cement

&

WGA

Page 56: Office Building Constructed in Nine Weeks !

We Build A Better Quality of Life