Upload
symposium
View
201
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Murray Zircon - Investor presentation delivered at the 4th annual Resources Investment Symposium held in Broken Hill NSW Australia, 26-28 May 2014.
Citation preview
Mindarie Mineral Sands Project: A New Beginning
4th Annual Resources Investment Symposium
26-28 May 2014 Broken Hill, NSW
Patrick Mutz
CEO Murray Zircon Pty Ltd
Murray Zircon Pty Ltd
Copyright Murray Zircon 2
Australia’s newest mineral sands miner.
Copyright Murray Zircon 3
5/30/2014
Murray Zircon in Australia
South
Australia
Murray Zircon was established in June 2011 as a joint venture to
redevelop the Mindarie Mineral Sands Project in South Australia
Copyright Murray Zircon 4
5/30/2014
Mindarie Mineral Sands Project
Adelaide
Mindarie
Mindarie Project area
is located 150km east
of Adelaide.
Murray Zircon Pty Ltd
Copyright Murray Zircon 5
Murray Zircon joint venture majority shareholder:
Guangdong Orient Zirconic Industry Science and Technology Co., Ltd. (Orient Zirconic), a listed company in China (SHE: 002167).
Joint venture minority shareholder: Initially, Australian Zircon NL, the former owner/operator of the Mindarie Project.
Australian Zircon’s shareholding now owned by private investors.
Murray Zircon Pty Ltd
Copyright Murray Zircon 6
Objective: Rehabilitate and redevelop the Mindarie Project.
All project and company assets as well as certain liabilities were transferred to the Joint venture and into Murray Zircon.
Mindarie Project land, wet and dry processing plants and all associated equipment and infrastructure;
Mineral Leases and associated reserves and resources;
Exploration portfolio covering more than 11,000 km² within the Murray Basin; and
Liability for rehabilitation of previously mined land.
Reserves & Resources
Copyright Murray Zircon 7
JORC Reserves of 58.1 million tonnes at 4.3% THM.
Up to 15 year mine-life
JORC Resources of 171 million tonnes at 3.2% THM.
Exploration potential
Copyright Murray Zircon 8
5/30/2014
Primary Concentration Plant (PCP)
Copyright Murray Zircon 9
5/30/2014
Mineral Separation Plant
Location of Murray Zircon Exploration Tenements
Copyright Murray Zircon 10
Rehabilitation Liability Areas
Aerial Photo: March 2011
Area 1 Area 2
Area 3
Area 6 Area 4 Area 5
Mindarie Project – History
The Mindarie Project was originally developed by Australian Zircon Limited (ASX:AZC) in 2006.
The mine commenced operations in October 2007 following the construction of a Primary Concentrator Plant (PCP) and Mineral Separation Plant (MSP).
From the outset the project was plagued with numerous challenges;
Technical; community; regulatory; financial including a falling commodities market.
In October 2009 the project was placed on care & maintenance.
Copyright Murray Zircon 12
Mindarie Project – Redevelopment
As part of its strategy to redevelop Mindarie, Murray Zircon assumed responsibility for all remaining rehabilitation liability over previously mined areas.
Rehabilitation works commenced in August 2011.
At the same time, the Company initiated refurbishment of the PCP and associated wet plant facilities in October 2011.
The Company also submitted a Program for Environmental Protection and Rehabilitation (PEPR) to the South Australian Department of Manufacturing, Innovation, Trade, Resources and Energy (DMITRE), for approval to resume mining.
Copyright Murray Zircon 13
Rehabilitation Success
Phased Rehabilitation Milestones
Overburden Completed December 2011
Sub-soil replacement Completed February 2012
Top-soil replacement Completed March 2012
Cropping Completed April/May 2012
Copyright Murray Zircon 15
5/30/2014
Rehabilitated Land
Mindarie Project – Redevelopment
Through its successful rehabilitation efforts, positive relationships were built with the local community, affected landowners as well as the government through DMITRE.
NET RESULT?
DMITRE approved Murray Zircon’s PEPR application in April 2012 and issues a licence to resume mining;
less than 1 year from the formation of the company.
Copyright Murray Zircon 16
Mindarie Redevelopment & Commissioning
Primary Concentrate Plant refurbishment/upgrade activities completed in August 2012.
Mining contract and product logistics contract finalised in September 2012.
A newly purchased Mining Slurry Unit was installed and a new slurry pumping system was completed in November 2012.
Resumption of mining commenced in October 2012 and wet commissioning of the Slurry Unit and PCP began in December.
First HMC product was exported before the end of December.
Copyright Murray Zircon 17
Highlights of Operations
Mining at Mindarie is via dry, open-cut method using scrapers to remove overburden and dozers to mine the ore.
Typical mineral strands in the area are 150-200m wide, 10-20m deep and up to 13km long.
Mining/processing design capacity is 500 dry tonnes per hour ore feed to produce 10-12K tonnes of HMC per month.
Ore is slurried with water at the in-pit Slurry Unit and the slurry is pumped 3-8km to the Primary Concentration Plant (PCP).
At the PCP, the heavy minerals are removed with spiral classifiers to produce a Heavy Mineral Concentrate containing typically 80-90% heavy minerals.
Copyright Murray Zircon 18
Copyright Murray Zircon 19
5/30/2014 Ore mining by dozer push method
Overburden removal with scrapers
Ore
Slurry
Unit
Highlights of Operations
Only Heavy Mineral Concentrate (HMC) is produced at Mindarie.
HMC is transported from Mindarie by truck approximately 200km to the port in Adelaide at 7-10 B-Double trucks per day.
Transport by train is also an option but is not used at this time.
At the port, HMC is currently loaded into standard shipping containers with liners for export to China.
Bulk shipping is also an option but is not used at this time.
In China the HMC is separated into zircon and various titanium minerals.
OZC’s internal demand for zircon will support full production from the Mindarie project.
Copyright Murray Zircon 20
Copyright Murray Zircon 21
5/30/2014
HMC Storage Pad
Copyright Murray Zircon 22
5/30/2014
Typical Mining Equipment
Copyright Murray Zircon 23
5/30/2014 Slurry Pumping Skid
Copyright Murray Zircon 24
5/30/2014 Primary Concentration Plant
Copyright Murray Zircon 25
5/30/2014
Mining Camp
22/03/2012
Copyright Murray Zircon 26
Murray Zircon Pty Ltd
Orient Zirconic (China)
Orient Zirconic (Australia)
100%
Private Investors
Murray Zircon Pty Ltd
35% 65%
100%
Mindarie Project Exploration Tenements
100%
WIM 150 Project
Joint Venture
Partner
Orient Zirconic (China)
Guangdong Orient Zirconic Industry Science and Technology Co., Ltd (OZC), is one of China’s leading zircon processing companies and is headquartered at Shantou in Guangdong Province (about 480km northeast of Hong Kong).
OZC has the most comprehensive range of zirconium products in the world, including zirconium dioxide, zirconium oxychloride, fused zirconia, zirconia structural ceramic as well as zirconium sponge and other products.
OZC is listed on the Shenzhen Stock Exchange (Code:002167) with a market capitalisation approx. RMB 4.7 Billion (A$850 million*).
Copyright Murray Zircon
27
*Share price and exchange rate on 31/12/2013.
Copyright Murray Zircon 28
5/30/2014
Copyright Murray Zircon 29
5/30/2014
OZC Headquarters & Branch Locations in China
Chaoyang Branch, Liaoning
Headquarters, Shantou, Guangdong
Leiyang Branch, Hunan
Lechang Branch, Guangdong
Yanhong Branch, Shantou, Guangdong
New majority shareholder in March 2013;
Formerly Company Chairman – Mr Chaodian Chen at 30.8%
Now CNNC subsidiary at 15.7%
CNNC (China National Nuclear Corporation ) is the large state-owned enterprise under direct management of the central government.
January 2014 - OZC announced the acquisition of Zhejiang Zircon Valley Sci &Tech Pty Ltd; one of China’s largest producers of zirconium oxychloride for export.
February 2014 - OZC announced a merger with Hainan Wensheng High-Tech Materials Co., Ltd (Wingsheng or Winsheen); China’s biggest HMC importer and separator.
Copyright Murray Zircon 30
5/30/2014
Orient Zirconic - Recent Developments
Summary
Through Murray Zircon, Orient Zirconic has…
Made its initial investment and entered the mining community in South Australia;
Acted on its vertical integration strategy to securing steady supply of zircon;
Established a base for potential future investment.
Copyright Murray Zircon 31
For further information:
Website: www.murrayzircon.com.au Email: [email protected]
Patrick Mutz, CEO
Murray Zircon Pty Ltd
P.O. Box 3444 Level 6 West, 50 Grenfell Street
Adelaide, South Australia, Australia 5000
Phone: +61 8 8410 8884 ABN: 75 147 048 744