27
Importance of Microsoft Project and Primavera In Construction Industry November 03, 2015

Importance of Microsoft Project and Primavera

Embed Size (px)

Citation preview

Page 1: Importance of Microsoft Project and Primavera

Importance of Microsoft Project and Primavera In Construction Industry

November 03, 2015

Page 2: Importance of Microsoft Project and Primavera

Questions ? CEPT UNIVERSITY

Why Microsoft Project and Primavera ?

Why PMS ?

Planners only make schedules

Microsoft Project or Primavera ?

Microsoft Project cannot handle Complex Projects

Potential Used ?

Page 3: Importance of Microsoft Project and Primavera

Contents… CEPT UNIVERSITY

Project Management Challenges

Market Penetration

Project planning: PDM network Assign Resources and Cost Baseline the plan

Project review: Identify resource over-allocations Level if necessary

Project Execution: Generate Reports

Project Monitoring and Tracking: Update Baseline plan Compare Actual against Baseline Re-plan and Re-Baseline Earned Value Concept

Difference between MSP and Primavera

Microsoft Project or Primavera?

Page 4: Importance of Microsoft Project and Primavera

Work Performance Data/Info/Reports CEPT UNIVERSITY

PM PlanThe document which describes how the project will be documented, monitored and controlledWPDPhysical work completion, start and finish dates, change requests, actual costs, actual duration etc.WPIStatus of deliverables, status for change requests, forecasted estimates to complete

WPRStatus reports,memos,justifications, recommendations

Page 5: Importance of Microsoft Project and Primavera

Project Management Challenges CEPT UNIVERSITY

Geographic dispersion

Overbooked or Unutilized Resources

Project Scope Changes

Unnecessary Paperwork

Page 6: Importance of Microsoft Project and Primavera

Market Penetration CEPT UNIVERSITY

Middle East United StatesSource: The use of project management software in construction industry of Southeast EuropeMladen Vukomanović, Mladen Radujković, Zlata Dolaček Alduk

Page 7: Importance of Microsoft Project and Primavera

Project Planning CEPT UNIVERSITY

Schedule Baseline is established to control actual project performance

Page 8: Importance of Microsoft Project and Primavera

Project Planning: PDM Network CEPT UNIVERSITY

Page 9: Importance of Microsoft Project and Primavera

Project Planning : PDM Network CEPT UNIVERSITY

Page 10: Importance of Microsoft Project and Primavera

Project Review: Assigning resources and Cost CEPT UNIVERSITY

Page 11: Importance of Microsoft Project and Primavera

Project Review: Levelling Resources CEPT UNIVERSITY

Page 12: Importance of Microsoft Project and Primavera

Managing Floats in MS-Project and Primavera CEPT UNIVERSITY

Page 13: Importance of Microsoft Project and Primavera

Managing Floats in MS-Project and Primavera CEPT UNIVERSITY

Page 14: Importance of Microsoft Project and Primavera

Managing Floats in MS-Project and Primavera CEPT UNIVERSITY

Page 15: Importance of Microsoft Project and Primavera

Managing Floats in MS-Project and Primavera CEPT UNIVERSITY

Page 16: Importance of Microsoft Project and Primavera

Project Tracking: Setup Baseline CEPT UNIVERSITY

Go to: Project/Set baseline to set a baseline for your project

A Baseline is essentially a snapshot of your project schedule, it should be captured once your schedule is complete.

So that you can compare your original plan with the current progress.

Page 17: Importance of Microsoft Project and Primavera

Project Monitoring & Tracking: Tracking Gantt CEPT UNIVERSITY

Page 18: Importance of Microsoft Project and Primavera

CEPT UNIVERSITYEarned Value Analysis

5500049000

56000

0

20000

40000

60000

80000

100000

120000Jan-03

Feb-03

Mar-03

Apr-03

May

-03

Jun-03

Jul-0

3

Aug-03

Sep-03

Oct-03

Nov

-03

Dec

-03

BCWS

BCWP

ACWP

Cost Variance: 55,000-56,0000 = -1000 INR (Cost-Overrun)Schedule Variance: 49,000 – 55,000 = -6000 INR (Behind Schedule)

Page 19: Importance of Microsoft Project and Primavera

Project Monitoring & Tracking: EVA CEPT UNIVERSITY

Page 20: Importance of Microsoft Project and Primavera

Project Execution: Reports CEPT UNIVERSITY

Microsoft Project-2013 Primavera-P6

Page 21: Importance of Microsoft Project and Primavera

Primavera P6 Dashboard CEPT UNIVERSITY

Page 22: Importance of Microsoft Project and Primavera
Page 23: Importance of Microsoft Project and Primavera

MS-Project or Primavera? Decision Matrix CEPT UNIVERSITY

Source: https://precisionschedulingconsultants.com

Factor MS-Project Primavera

Small & medium building project (<200 activities)

Program-level analysis or simultaneous multiple project analysis Multiple user interface (more than one person updating/tracking the schedule)

Construction schedule oversight and detailed analysis 

Non-construction projects / simple schedules

Basic bar charts or timelines for display in MS PowerPoint™ presentation

System Integration (BIM,ERP)

Licensing Cost

User friendly , Beginner use, planning and scheduling

Recommended

Note: These decisions are based on professional opinion that were derived from years and $billions worth of construction scheduling experience.

Not-Recommended

Page 24: Importance of Microsoft Project and Primavera

MICROSOFT PROJECT PRIMAVERASimple and user friendly Detailed and complex

Allows user to make Macros and Switches with the help of VBA language

Macros , complex formulas cannot be made in Primavera

Limited Baselines (Only 11) Unlimited baselines

Project Tracking with multiple projects at same time is not possible.

Project Tracking with multiple projects at same time is possible.

Multiple activity relationship not possible It is possible to have a FF as well as SS relationship between two activities.

Relatively low cost of installation and maintenance.

High installation and maintenance cost

Appealing appearance Needs configuration to make it appealing.

Page 25: Importance of Microsoft Project and Primavera

Difference a decade makes (MS-Project) CEPT UNIVERSITY

Page 26: Importance of Microsoft Project and Primavera

Difference a decade makes….

1994

2000

2003

2006

2010

P3-V1 for Windows

P3 (V-02) incorporated EPS

P6- PrimaVision web based platform is released Incorporates

Risk management

Enterprise Project Portfolio is released

CEPT UNIVERSITY

Page 27: Importance of Microsoft Project and Primavera

The Competition—Endless……

Thank You For Your Attention….

Questions?