Edward McKeiver delivered the presentation at 2014 Major Rail Occurrence Forum (Derailments). The RISSB Major Rail Occurrence Forum (Derailments) has been designed to build on and continue the analysis of major occurrence reports and to seek Industry learning from them. By reviewing major occurrence reports, Rail Organisations have the opportunity to learn from the lessons without having to suffer the same occurrence. For more information about the event, please visit: http://www.informa.com.au/derailments14

Citation preview

Page 1: Edward McKeiver - Aurizon - An enterprise approach

An Enterprise Approach

Edward McKeiver

VP Service Delivery Coal Markets

Aurizon

30th April, 2014

Sydney Harbour Marriot

Page 2: Edward McKeiver - Aurizon - An enterprise approach

Aurizon• Operations across all

mainland States

• 2,670km of track owned,

managed and operated in

Central Queensland

• 267mtpa of volumes hauled in

FY13

• ~7970 employees

• $9.6bn of total assets

• Market capitalisation of ~$8bn

Page 3: Edward McKeiver - Aurizon - An enterprise approach

Derailments – Situational Appraisal

• FY12 – One derailment every 38hrs

• 230 derailments (33 Mainline, 197 Yard)

• A complex risk profile

• Legacy infrastructure conditions

• Human Factors (lapses, procedures not followed)

• 67% on QR National Infrastructure, 33% on 3rd

Party Infrastructure

• Investigation ownership, reporting and analysis

needs significant overhaul and improvement

• 80% in Queensland including 55 wheel

obstruction derailments

Page 4: Edward McKeiver - Aurizon - An enterprise approach

Focus

• Enterprise problems require Enterprise solutions

• Required a leadership paradigm shift in standards and

expectations to drive cultural change

• Derailments are not the norm or acceptable

• A significant training exercise needed to be undertaken to

heighten derailment risk awareness

• Accountable Line Management needed support

• Collaborative Leadership expected

Page 5: Edward McKeiver - Aurizon - An enterprise approach

Derailment Prevention Community of Competence (CoC)

• Representatives from across the enterprise with a specialized

focus and interest in preventing derailments (network)

• Charter - To develop and foster best practice derailment

prevention solutions and facilitate their implementation across

Aurizon to eliminate derailments

• New leadership

• Appointment of a full time resource

• Systematic approach and refocused enterprise strategy

Page 6: Edward McKeiver - Aurizon - An enterprise approach

Strategy – FY13

• 3 Core Areas

• Improved collection and utilisation of data – critical in

understanding the levers to drive future strategy

• Uplift capability - investigative talent and derailment

precursor awareness across the enterprise

• Creation of safe operational yard infrastructure – high risk

interventions in known “hot spots”

Page 7: Edward McKeiver - Aurizon - An enterprise approach

Data, Reporting and Analysis• Reinstatement and mandated requirement

for detailed derailment reporting (Form 7)

• Regular analysis of levers to drive strategy

12377%

3019%

42%

32%

FY13 - All Derailments by State

QLD

WA

NSW

VIC

230

115

160

0

50

100

150

200

250

FY12 Count FY13 Target FY13 Count

FY13 - All Derailment Performance

Total

Linear (Total)

Total FY12: 230Total FY13: 160

Improvement30.43% (Direct Count)

46.71% (Normalised Mtkm)

Rate FY12: 7.81Rate FY13: 4.16

129

53

125

17 14

64.5

26.5

62.5

8.5 7

82

37

1410 12

5

0

20

40

60

80

100

120

140

Bulk Coal Rollingstock Network Intermodal Iron Ore

FY13 - All Derailment Performance by Function

FY12 Count

FY13 Target

FY13 Count

10

8 8

7

6 6

4 4 4 4 4 4

3 3 3 3

2 2 2 2 2 2 2 2 2 2 2

0

2

4

6

8

10

12

FY13 - All Derailment Frequency by Location - Count > 1

Count of Location

103 out of 16065% of Sample

11041%

5018%

4517%

218%

145%

135%

93%

62%

21%

FY13 - All Basic Causation - All Levels

Engineering

Mental/psychological

Job Factors

Organisational

Motivational/communication

Physical/physiological

Knowledge, skill and experience

Management systems

Abuse or misuse

2440%

1423%

1423%

59%

35%

FY13 - Track, Roadbed, StructuresImmediate Causation

Track geometry

Points and Crossings

Roadbed

Rails, Joints, Fastenings, Sleepers

Other Way and Structures

Page 8: Edward McKeiver - Aurizon - An enterprise approach

Capability Uplift

• 60 Derailment Prevention

Champions (DPC’s) trained

across the enterprise

• Systems approach including use

of ICAM

• Support investigators and line

management to take proactive

approach in derailment

prevention

• “Tools” deployed in strategic

locations – quality investigations

Page 9: Edward McKeiver - Aurizon - An enterprise approach

Networking and the Learning Organisation

Page 10: Edward McKeiver - Aurizon - An enterprise approach

Enterprise Awareness

• Intranet site with

resources

• “Toolbox Talks””

• Learning Packs

• Video Resources

• DPC SharePoint site

• Awareness of every

derailment

• Shared reports for

learning

Page 11: Edward McKeiver - Aurizon - An enterprise approach

Sharing the Learnings – Salmon Gums

• Play Example of CoC Video

Page 12: Edward McKeiver - Aurizon - An enterprise approach

Infrastructure Interventions

• Targeted interventions in known

“hotspots”

• Closure/removal of high risk

locations

• Investment to restore to standard

• Townsville

• $1.9M

• 35 derailments down to 10 (FY13

compared to FY12)

Page 13: Edward McKeiver - Aurizon - An enterprise approach

Strategy – FY14

Page 14: Edward McKeiver - Aurizon - An enterprise approach

3rd Party Engagement

• Create tension and reinforce

accountabilities

• Collaborative approach including

joint investigation

Page 15: Edward McKeiver - Aurizon - An enterprise approach

Best Practice Standards

• Single Enterprise Standards (1/2

Distance Protection)

• Standards as reference point for

factual investigation

• Support for National Standards,

COP’s and Guidelines

• Rail Welding and Rail Stress

Management

Page 16: Edward McKeiver - Aurizon - An enterprise approach

Derailment Prevention Awareness Program• ½ day workshop for operational

staff including leadership teams

• Proactive approach to

identification of derailment

precursors

• Engaging and gaining

commitment

• Rollingstock, infrastructure and

human factor focus

• 5% of “front line” trained to date

Page 17: Edward McKeiver - Aurizon - An enterprise approach

Other Strategic Initiatives

• Establishment of Infrastructure Rail

Management Team (“blue” roads) –

“Whole of Life” asset management

• Replacement of “sensitive”

rollingstock – Minerva consists

• Improved ballast wagon design

• Wayside detection “supersites” and

use of ACFM technology

Page 18: Edward McKeiver - Aurizon - An enterprise approach

Results – On Target FY14

Page 19: Edward McKeiver - Aurizon - An enterprise approach

Summary

• Holistic enterprise/supply chain/industry approach required

• Given human factors, engagement and leadership is paramount

to drive change in the safety culture

• Success is underpinned by activities aimed at becoming a

“learning organisation”

• Use Standards as a factual reference base.

• Leverage Community - Collaborate to share, learn and grow.

• Never stop asking “why?” (systems approach and basic

causation)

• Improved Safety/Stakeholder outcomes for all.