25
DESIGN-BUILD PROCUREMENT APPROACHES John D. Doller, P.E. Carollo Engineers, Inc.

Design-Build Procurement Approaches

Embed Size (px)

DESCRIPTION

John Doller of Carollo Engineers discusses the procurement process as it relates to design-build projects at the American Water Works Association's ACE13 Annual Conference & Exposition.

Citation preview

Page 1: Design-Build Procurement Approaches

DESIGN-BUILD PROCUREMENT APPROACHES

John D. Doller, P.E. Carollo Engineers, Inc.

Page 2: Design-Build Procurement Approaches

Agenda

• Procurement Goals

• Evaluation Options

• Types of Procurement

• Considerations for Selection of Procurement Type

Page 3: Design-Build Procurement Approaches

Procurement Goals

• Attract the best competition from the qualified DB teams

• Obtain an acceptable market price for DB services

• Obtain acceptable contract terms to meet Owner’s project objectives with acceptable risk allocation

Page 4: Design-Build Procurement Approaches

Evaluation Options

Qualifications Cost

Page 5: Design-Build Procurement Approaches

Evaluation Options

Qualifications Cost

Qualifications Based Selection

Price Based Selection Best Value Selection

Page 6: Design-Build Procurement Approaches

Design-Build Procurement Approaches

Design-Builder is selected based on Qualifications

alone.

RFQ A price for the project is developed

at a specified level of design and could be GMP or Lump Sum

Qualifications Based Selection

Page 7: Design-Build Procurement Approaches

Design-Build Procurement Approaches

Design-Builder is selected based on price alone

(i.e. lowest responsive price)

RFP

(requires some level of design)

Qualifications Based Selection

Price Based Selection

Page 8: Design-Build Procurement Approaches

Design-Build Procurement Approaches

Design-Builder is selected based on a

combination of qualifications and

price

RFP or RFQ&RFP

Qualifications Based Selection

Price Based Selection

Best Value Selection

Page 9: Design-Build Procurement Approaches

Qualifications Based Selection

ADVANTAGES • Reduces procurement time and cost

• Most qualified Design-Builder is selected

• High degree of Owner control

• Owner defines/negotiates scope, quality, price and schedule

Project Definition

Predesign Final Design

Construction Startup

Page 10: Design-Build Procurement Approaches

Qualifications Based Selection

DISADVANTAGES

• May not be legally permissible

• Is counter to “public low bid” psyche

• Could be “tough sell”

• May need to engage a procurement advisor

Project Definition

Predesign Final Design

Construction Startup

Page 11: Design-Build Procurement Approaches

Qualifications Based Selection

QUALITATIVE CONSIDERATIONS * Qualifications * Experience

* Technical Approach * Management Approach

* Risk Allocation * Key Personnel

* Team Organization * Schedule Control

* QA/QC Approach * Insurance / Bonding

Project Definition

Predesign Final Design

Construction Startup

Page 12: Design-Build Procurement Approaches

Price Based Selection

ADVANTAGES

• Price certainty at time of proposal submission

• Detailed technical information provided

Project Definition

Predesign Final Design

Construction Startup

Page 13: Design-Build Procurement Approaches

Price Based Selection

DISADVANTAGES

• Large time investment in procurement

• Greater effort to review proposals

• Owner input only during procurement development

• Life-cycle cost considerations limited

Project Definition

Predesign Final Design

Construction Startup

Page 14: Design-Build Procurement Approaches

Price Based Selection

Predesign Final Design

Performance Based Prescriptive Based

INNOVATION CONTROL

Page 15: Design-Build Procurement Approaches

Performance vs. Prescriptive

Predesign Final Design

Performance Based Prescriptive Based

INNOVATION CONTROL

Performance Based Prescriptive Based

• Maximum potential for cost savings through innovation

• Maximum transfer of design-related performance risk

• Relatively low costs to prepare RFP / Proposal

• Substantial control over project design and O&M costs

• Proposal selection can emphasize project design build costs

• High level of project definition at time contract is signed

ADVANTAGES

Page 16: Design-Build Procurement Approaches

Performance vs. Prescriptive

Predesign Final Design

Performance Based Prescriptive Based

INNOVATION CONTROL

Performance Based Prescriptive Based

• May result in higher O&M costs

• Proposal evaluation and selection is more complex

• Potential for decreased participation due to higher preparation costs

• Limited Owner input into design after proposal is accepted

• Procurement duration is longer

• RFP preparation is more costly due to high level of design

• Design risk not clearly assumed by the Design- Builder

DISADVANTAGES

Page 17: Design-Build Procurement Approaches

Best Value Selection

Cost Qualifications

ADVANTAGES

• Price certainty at time of proposal submission (maybe)

• Detailed technical/qualifications information provided

• Depending upon cost component – collaboration can still exist

Best Value Selection

Page 18: Design-Build Procurement Approaches

Best Value Selection

Cost Qualifications

DISADVANTAGES • Large time investment in procurement

• Greater effort to review proposals

• Life-cycle cost considerations limited

Best Value Selection

Page 19: Design-Build Procurement Approaches

Weighting Costs and Quals

Progressive D-B

Page 20: Design-Build Procurement Approaches

Progressive Design-Build In a progressive design-build procurement, the design-builder is selected primarily based on qualifications before substantial design is completed. Together, the owner and the design-build team advance the design, incorporating the details desired by the owner and providing the owner with cost input regarding options the owner is considering. This open-book approach enables the owner to make well-informed decisions on the overall quality of the project. (Chapter 3, page 25)

Page 21: Design-Build Procurement Approaches

Progressive Design-Build

Design/Builder

Design Development and Construction Design Definition

Owner

PM/OA

100% Guaranteed maximum price established at the right time: Risk and contingency reduced, schedule needs met

Construction estimating can start very early in design, allowing comparison of specific technical solutions

First fully detailed estimate can be used to establish a scope baseline. Estimating process is “open book”

“Progressive” estimates keep owners informed and support-informed scope adjustment decisions

Owners can use third-parties to verify cost . . . . . . and go to the hard-bid market if needed (the “off-ramp”)

Page 22: Design-Build Procurement Approaches

Progressive Design-Build

Design/Builder

Design Development and Construction Design Definition

Owner

PM/OA

100%

• Investment in projects, not procurements

• Offers owners maximum flexibility/opportunity to collaborate on design/permitting

• Minimizes overall schedule

• Owners have an “off-ramp” in case of permitting issues or if GMP can’t be negotiated

• Very successful evolving model

Page 23: Design-Build Procurement Approaches

Considerations for Selecting Procurement Approach

• Project Goals and Objectives

• Legal Feasibility

• Level of Design Definition

Page 24: Design-Build Procurement Approaches

www.waterdesignbuild.org

www.awwa.org

Page 25: Design-Build Procurement Approaches