DELIVERING THAMES TIDEWAY DANNY TRUP APM Thames Valley - 26 April 2016

Delivering Thames Tideway, 26th April 2016

Embed Size (px)

Citation preview

Page 1: Delivering Thames Tideway, 26th April 2016

DELIVERING THAMES TIDEWAYDANNY TRUPAPM Thames Valley - 26 April 2016

Page 2: Delivering Thames Tideway, 26th April 2016

2

Page 3: Delivering Thames Tideway, 26th April 2016

3

YOU POO TOO

https://www.youtube.com/watch?v=eD_kmPIPd84

Page 4: Delivering Thames Tideway, 26th April 2016

4

LONDON

Page 5: Delivering Thames Tideway, 26th April 2016
Page 6: Delivering Thames Tideway, 26th April 2016

River Thames C16th

Page 7: Delivering Thames Tideway, 26th April 2016

7

Lost ‘rivers’ of London

Page 8: Delivering Thames Tideway, 26th April 2016

8

The Great Stink

Page 9: Delivering Thames Tideway, 26th April 2016

9

Bazalgette’s interceptor sewers

Page 10: Delivering Thames Tideway, 26th April 2016
Page 11: Delivering Thames Tideway, 26th April 2016
Page 12: Delivering Thames Tideway, 26th April 2016
Page 13: Delivering Thames Tideway, 26th April 2016

13

20138 million

18602 million

19104 million

Population of London

• In 2014, 62 million cubic metres of sewage discharged to the tidal River Thames.• 50 discharges on average in a typical year

Bazalgette design capacity

Page 14: Delivering Thames Tideway, 26th April 2016

14

CSO discharge

Page 15: Delivering Thames Tideway, 26th April 2016

15

FINDING A SOLUTION

Page 16: Delivering Thames Tideway, 26th April 2016

16

London Tideway Improvements

Riverside

Long ReachMogden

Crossness

Sewage Works UpgradesLee TunnelThames Tideway Tunnel

Beckton

Page 17: Delivering Thames Tideway, 26th April 2016

17

Page 18: Delivering Thames Tideway, 26th April 2016

18

Page 19: Delivering Thames Tideway, 26th April 2016

19

Impact of improvements

4

9

GreenwichPS

WesternPS

Existing System–CSOvolumeTypical YearCSOVolume(cubic metres)

5,000,000

4,000,000

3,000,000

2,000,000

1,000,000

0

19,418,500

AbbeyMills CSOvolume(cubic metres)

Tideway CSOHammersmith PS

AbbeyMills (see inset)

Page 20: Delivering Thames Tideway, 26th April 2016

20

Impact of improvements

4

9 No spill

GreenwichPS

WesternPSHammersmith PS

LeeTunnel and STWImprovements –CSOvolumeTypical YearCSOVolume(cubic metres)

5,000,000

4,000,000

3,000,000

2,000,000

1,000,000

0

Tideway CSO

AbbeyMills CSOvolume(cubic metres)

AbbeyMills (see inset)

Page 21: Delivering Thames Tideway, 26th April 2016

21

Impact of improvements

4

9 GreenwichPS

WesternPSHammersmith PS

ThamesTideway Tunnel –CSOvolumeTypical YearCSOVolumes(cubic metres)

5,000,000

4,000,000

3,000,000

2,000,000

1,000,000

0

AbbeyMills (see inset)

Tideway CSO

No spill

AbbeyMills CSOvolume(cubic metres)

Page 22: Delivering Thames Tideway, 26th April 2016

22

SCOPE

Page 23: Delivering Thames Tideway, 26th April 2016

23

The Thames Tideway Tunnel

Page 24: Delivering Thames Tideway, 26th April 2016

24

Tunnelling through London

Page 25: Delivering Thames Tideway, 26th April 2016

25

Interfaces with existing infrastructure

Bridges: 75

Page 26: Delivering Thames Tideway, 26th April 2016

26

Victoria Embankment

Page 27: Delivering Thames Tideway, 26th April 2016

Main Tunnel

Vortex Shaft

Existing CSO

Connection

Air Treatment

Image: CSO interception

Existing seweragenetwork

New reclaimed area

Page 28: Delivering Thames Tideway, 26th April 2016

28

Engineering challenges

• Variable ground conditions

• 120 year design life

• Dissipate energy

• minimise air entrapment

• ventilation and odour treatment

Page 29: Delivering Thames Tideway, 26th April 2016

29

PLANNING AND CONSULTATION

Page 30: Delivering Thames Tideway, 26th April 2016

30

Route to Development Consent

• Over six years of project development, planning and extensive consultation

• Planning Act 2008

• Public consultation

• DCO application

Page 31: Delivering Thames Tideway, 26th April 2016

31

Consultation and Community Engagement

30Months

development

9,400Responses

during consultation

Over 200meetings attended

114 days of public

exhibitions held

Page 32: Delivering Thames Tideway, 26th April 2016

32

PROCUREMENT AND DELIVERY

Page 33: Delivering Thames Tideway, 26th April 2016

33

Delivery model

• Thames Water, Government and Ofwat

- a range of models to ensure a value for money solution

• A new regulated Infrastructure Provider (IP),

• Bazalgette Tunnel Limited (BTL),

- formed under the Flood and Water Management Act 2010

- Regulated by Ofwat

- Tendered through a competitive process

- build, manage and maintain the tunnel.

• Thames Water will operate

- £1.1bn of investment is from Thames Water,

- £3.1bn is from BTL

Page 34: Delivering Thames Tideway, 26th April 2016

34

IP at a glance

Revenue collection/ operator of Sewer Network/TWUL Works

Debt Equity Secretary of State

Ofwat

TWUL

System Integrator Contractor

Construction Contractors Project Manager

West Central East

Insurers

100% ownership

Project Licence

Government Support Package

Tideway

Page 35: Delivering Thames Tideway, 26th April 2016

35

Bazalgette Tunnel Limited (BTL)

1.7 million UK pensioners will have an indirect investment in Tideway.

Page 36: Delivering Thames Tideway, 26th April 2016

36

Main Contractors

West Central East System Integrator

Page 37: Delivering Thames Tideway, 26th April 2016

37

OUR VISION

Page 38: Delivering Thames Tideway, 26th April 2016

38

Page 39: Delivering Thames Tideway, 26th April 2016

39

More than just a sewer

Coping with population

growth

Jobs and skills Tourism Economic

Ecological SMEs Public Health

Environmental Increased river use

Health and Safety

Recreation

Page 40: Delivering Thames Tideway, 26th April 2016

40

Leaving a legacy

Environment

Health and Safety

Economy

People

Place

• Dramatic reduction in discharges from more than 50 to only 3 or 4 in a typical year

• Three Zeros commitment• Introduce leading lorry and cycling safety initiatives

• Use river transport to remove 90 per cent of spoil from Main Drive sites

• Engage local businesses and SMEs

• 4,000 direct, sustainable jobs• 1:50 apprentice and 1:100 ex-offenders

• Three acres of new foreshore • Enhance Thames Path

Page 41: Delivering Thames Tideway, 26th April 2016

41

Timetable

2016

Main works preliminary constructionbegins

2017

Tunnelling begins

2021

Tunnelling ends

2023

Project completion

2015• BTL granted

licence by Ofwat

• Main Works contracts awarded

Page 42: Delivering Thames Tideway, 26th April 2016

42

Blackfriars: Before

Page 43: Delivering Thames Tideway, 26th April 2016

43

Blackfriars: After

Page 44: Delivering Thames Tideway, 26th April 2016

44

QUESTIONS?