45
Vermelding onderdeel organisatie February 1, 2012 1 Chapter 13: Construction methods for granular material ct5308 Breakwaters and Closure Dams H.J. Verhagen Faculty of Civil Engineering and Geosciences Section Hydraulic Engineering

Ct530813

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Ct530813

Vermelding onderdeel organisatie

February 1, 2012

1

Chapter 13: Construction methods for granular material

ct5308 Breakwaters and Closure Dams

H.J. Verhagen

Faculty of Civil Engineering and Geosciences Section Hydraulic Engineering

Page 2: Ct530813

February 1, 2012 2

Elements to consider

• Bed fixation or bed protection mattresses, etc.

• Shore connected and intermediate dam sections sand fill/quarry; execution

• Abutments sheetpile, caisson

• Breakwater core; dumped sills

• Cover layer, armour

Page 3: Ct530813

February 1, 2012 3

Scour prevention

• Change of flow in course of time

• Flow distribution over the vertical

• Flow is not saturated with sediment

• Turbulence intensity increases

Page 4: Ct530813

February 1, 2012 4

development of a scour hole

Page 5: Ct530813

February 1, 2012 5

length

Page 6: Ct530813

February 1, 2012 6

balance of material

Page 7: Ct530813

February 1, 2012 7

effective scour time

Page 8: Ct530813

February 1, 2012 8

development of a scour hole

Page 9: Ct530813

February 1, 2012 9

mattresses or granular filters

•limited construction height

•applicable on steep slopes

•difficult to remove

•presence of structural joints

•vulnerable to mechanical damage

•restricted lifetime

•self healing after minor damage

•absence of structural joints

•simple to remove by dredging

•no sudden change at the end; they can fade out gradually

•absence of structural coherence

•disintegration on steep slopes

•considerable construction height

Page 10: Ct530813

February 1, 2012 10

stability downstream of a sill

increase load withu

flow uniform u = K

c

cv

Page 11: Ct530813

February 1, 2012 11

Shields with corrections

2 2

2

1: 1

0.4

v c

s c

vt

K ud

K C

KIn Cress K

Rectangular Abutments: Kv = 1.7 => Kt= 2.75

Page 12: Ct530813

February 1, 2012 12

example bed protection

• Bs = 2.5 * 20 = 50 km2

• depth = 10 m

• B = 500 m

• tidal difference = 3 m

Page 13: Ct530813

February 1, 2012 13

Bed protection in case of horizontal closure width u0 (max) D (cm) W(kg)

500 2,13 5 0 80/200

450 2,35 6 0 80/200

400 2,60 8 1 80/200

350 2,90 11 2 80/200

300 3,26 17 7 80/200

250 3,68 23 20 10/60

200 4,16 35 65 60/300

150 4,63 50 192 60/300

100 5,13 71 653 300/1000

50 5,47 90 1161 1/3

25 5,68 105 1794 1/3

10 6,27 158 6166 special

Page 14: Ct530813

February 1, 2012 14

Mixing layers (from ct4310)

10°

Page 15: Ct530813

February 1, 2012 15

Jet equations (from ct4310) 2

2

0.693

0

0.693

0

3.50.1

6.30.1

z

b

m m

R

b

m m

uPlane jets : u = b = x u = u e

x B

uCircular jets : u = b = x u = u e

x D

x = distance from sill B = width of gap

Page 16: Ct530813

February 1, 2012 16

Bed protection in case of vertical closure

depth U0 u2 3*U2 D (cm) W(kg)

10 2.13 2.13 2.13 5 0 80/200

9 2.36 2.15 2.36 6 0 80/200

8 2.64 2.18 2.64 8 1 80/200

7 2.97 2.20 2.97 14 4 80/200

6 3.38 2.20 3.38 21 14 10/60

5 3.86 2.18 3.86 27 32 10/60

4 4.33 2.07 4.33 39 97 60/300

3 4.63 1.81 4.63 50 192 60/300

2 4.64 1.41 4.24 37 79 60/300

1 3.42 0.74 2.23 5 0

0 3.13 0.41 1.22 1 0

Conclusion: everywhere 60/300 is needed

Page 17: Ct530813

February 1, 2012 17

providing quarry material

• by road

• by rail

• by water

• a combination

Page 18: Ct530813

February 1, 2012 18

subsequent working fronts

Page 19: Ct530813

February 1, 2012 19

Construction phases of the Zeebrugge Breakwater (1)

Unsustainable material in the location of the

breakwater is removed by sea going cutter suction

dredge

Page 20: Ct530813

February 1, 2012 20

Construction phases of the Zeebrugge Breakwater (2)

Split-hopper replaces material with sea sand and sea

gravel

Page 21: Ct530813

February 1, 2012 21

Construction phases of the Zeebrugge Breakwater (3)

Willow mattresses are sunk with two sink pontoons

and specialised stone barges

Page 22: Ct530813

February 1, 2012 22

Construction phases of the Zeebrugge Breakwater (4)

Lateral berms are constructed with quarried stones of

3-6 tons with specialised stone barges

Page 23: Ct530813

February 1, 2012 23

Construction phases of the Zeebrugge Breakwater (5)

The dam core is built with quarry stone using heavy

duty earth moving equipment

Page 24: Ct530813

February 1, 2012 24

Construction phases of the Zeebrugge Breakwater (6)

The stones are faces with a layer of 1-3 tons stones

plus filter construction with Poclain 600

Page 25: Ct530813

February 1, 2012 25

Construction phases of the Zeebrugge Breakwater (7)

The seaward side is protected by 25-30 ton concrete

blocks with an American Hoist 11-310

Page 26: Ct530813

February 1, 2012 26

Construction phases of the Zeebrugge Breakwater (8)

Finishing: crown block, service road, lighting

Page 27: Ct530813

February 1, 2012 27

a breakwater under construction

Page 28: Ct530813

February 1, 2012 28

trucks waiting on the breakwater

Page 29: Ct530813

February 1, 2012 29

use of cheap local equipment

Page 30: Ct530813

February 1, 2012 30

build up of profiles

line dump

horizontal layers

Page 31: Ct530813

February 1, 2012 31

use of waterborne and land based equipment

Page 32: Ct530813

February 1, 2012 32

land based equipment

Page 33: Ct530813

February 1, 2012 33

tipper truck vs. dump truck

Page 34: Ct530813

February 1, 2012 34

space requirements for heavy equipment

Page 35: Ct530813

February 1, 2012 35

lifting capacity of a crane

Page 36: Ct530813

February 1, 2012 36

grab types

Page 37: Ct530813

February 1, 2012 37

Waterborne equipment

•Bulk

• Pipeline

• Floating

• flat deck barges

• bottom door barges

• split barges

• tilt barges

• side unloading vessels

• Individual placement

Page 38: Ct530813

February 1, 2012 38

closure by pumping sand

Page 39: Ct530813

February 1, 2012 39

barges for dumping material

Page 40: Ct530813

February 1, 2012 40

example of combined transport and crane vessel

Page 41: Ct530813

February 1, 2012 41

motion of a driven wheel

Page 42: Ct530813

February 1, 2012 42

temporary road on soft subsoil

Page 43: Ct530813

February 1, 2012 43

final closure with sand only

Page 44: Ct530813

February 1, 2012 44

closure with a cable car

Page 45: Ct530813

February 1, 2012 45

varying construction sequence