Construction Pics Day by Day
before
1st day [lower Grade / lower west Sewer Line / expose House Ledger, Foundation]
2nd day [inspect Footings, install Posts / tamp Ground / lay Foam – 4ft horizontal from Foundation / lay Plastic, Stone]
3rd day [notch Addition Posts]
4th day [install Gutter n Curtain Drain / repair Sewer Line west / cover w stone]
5th day [install boundry Board / install Addition Beams, Joists, SubFloor / final Grade Area]
6th day [build n raise Addition west Wall, build east Wall]
7th day [raise Addition east Wall, build n raise north Wall, install Roof Rafters / temporary Tarp Floor]
8th day [build Ceiling Joists, Roof Extension , north Ceiling Studs / install east Wall OSB, north Wall OSB n Wrap]
9th day [install Roof OSB, flashing w Flat / install east Wall Wrap]
10th day [install west Wall Wrap / install new Roof Shingles w Ridge Vent, flash to Flat Roof]
11th day [install Deck Ledger Boards w Ice Shield, Beams / inspect Framing / Ceiling Fan Mount / east Windows / rough Electric]
12th day [Concealed Electric Inspection / install east west Deck Ledger Flashing, Deck Joists / install Sliding Door]
13th day [install east west Stair Stringers, Deck Posts
14th day [Trim out east Steps, start west Steps / install steel exterior Door
15th day [re install Siding no LR, Soffits west Addition, tear down east side old Soffit – vent, frame n cut screens for new]
16th day [install J and Soffett east side, form alum both ends; start Soffets north; install east and north Windows]
17th day (1/2 day) [finish install alum Soffit Boxes; Insulate]
18th day [shim House n Sliding Doors for Drywall; Inspect INSULATION; start Siding west Addition; start Decking west Deck]
19th day north face Siding, Soffit, alum Trim / west Deck Planks, install (7) Post Sleeves, Bases, Caps / hang Drywall, metal Edge
20th day finish east Siding, alum Fascia, J-block; texture Ceiling; finish west F Channel, Siding alum Fascia; mud floor gap
21st day mud n tape bottom Walls, cut n route Sill Plates, finish east-west Deck Planking, repl east lawn border, start Railing
22nd day SD Handle, Screen, west n east Deck Railing, Fascia; alum trim for Sill Plates, relocate Down Spouts, cover Microlams
23rd day PAINT Addition I/S, entry DOOR, Kitchen Door 1 side; add Dirt n Stone to border; install Screens
24th day install tack strip, backer, Carpet
25th day finish Electric
26th day Gutters