Telecom Power Outdoor System Presentation

NTBU

Page 2: 02 outdoor install process

Page 2

ContentsSystem Overview

Unpack(1.8M, 2.1 & 1.6M) System Check-->

AC Power Install -->

Battery Install--> (Very Heavy)

Telecom RBS Equipment Install--> (Very Heavy)

Power ON -->

Function Controller (Time & Battery Capacity Setting)

Q&A

Page 3: 02 outdoor install process

Page 3

Un-packing process without separate cabinet(RBS2216, ESOA150-ABA01)

Plastic Strap

Roof

Rem ove direction

Lift wole cabinet w ith 4pcs eyebolt.

UNPACK DRAW INGATT.(2)

Left cabinetR ight cabinet

S tep 4Release screws from wooden fram e and pallet, then Rem ove wooden fram e.

Step 3Rem ove Roof.

Screw(Both side)

S tep 7Rem ove plinth cover and then release 8 pcs screws from pallet.

P linth cover(Both side)

S tep 1Rem ove Tray.

PE BAG

S tep 5Rem ove PE BAG.

Front Door

S tep 2Rem ove Tube.

S tep 6O pen front door.

S tep 8C lose front door before lift the cabinet up.

Page 4: 02 outdoor install process

Page 4

RBS2216 (ESOA150-ABA01)

A S S E M B LY D R A W IN GA TT .(3 )

S tep 1R e lease screw s fo r the assem bly le ft & righ t cab ine t.R e lease a ll o f cab les and connecto rs be tw een le ft & righ t cab ine t.

S tep 5R elease screw s fo r fron t door and open the door then fab rica te screw s to o rig ina l loca tion .

Left cab ine t

S crew

S crew

S tep 6Fabrica te screw s fo r the assem bly le ft & righ t cab ine t.Then fab rica te screw s fo r the assem bly p lin th cover.

R igh t cab ine t

S crew ;x6pcs

S crew ;x6pcs

Le ft cab ine t

S crew (B oth s ide)

P lin th cover(B o th s ide)

R igh t cab ine tLe ft cab ine t

S tep 2R em ove p lin th cover from le ft & righ t cab ine t and then re lease 8 pcs screw s from pa lle t.

S tep 7P rin t s ilicone a round s ide o f cab ine t.Then fab rica te screw s fo r the assem bly roo f.

S ilicone

S crew

S tep 3R e lease screw s then fix doo r by p rev ious screw s to p reven t door open .

R oof

S tep 4C lose le ft door and righ t door.L ift by 2pcs eyebo lt fo r each cab ine t.

S crew

Un-packing process without separate cabinet

Page 5: 02 outdoor install process

Page 5

S tep 4Take out screw s from w ooden box and pa lle t, then R em ove w ooden box.

R oof

S tep 5R em ove P E B A G .

P E B A G

P lin th cover(B oth s ide)

U N PA C K D R AW IN GA TT .(2)

S tep 2R em ove Tube.

S tep 3R em ove R oof.

S tep 6O pen fron t door.

S tep 7R em ove p lin th cover and then re lease 4 pcs screw s from pa lle t.

S tep 1R em ove T ray.

S crew (B oth s ide)

RBS2111 2.1m (ESOA150-ABB01, ESOA150-ABB02)Un-packing process without separate cabinet

Page 6: 02 outdoor install process

Page 6

RBS2111, 1.6m (ESOA150-ABC01)

PE B A G

S tep 2R em ove Tube.

S tep 3Take out screw s from w ooden fram e and pa lle t, then R em ove w ooden box.

S tep 4R em ove P E B AG .

S tep 5O pen fron t door.

S tep 6R em ove p lin th cover and th en re lease 4 pcs screw s from pa lle t.

S tep 1R em ove Tray.

S crew (B oth s ide)

U N P A C K D R A W IN GATT .(2)

P lin th cover(B oth s ide)

Un-packing process without separate cabinet

Page 7: 02 outdoor install process

Page 7

Preliminary Inspection

System CheckPrior to removing the system from the crate, not any damage to

the crate.

Remove the system cabinet from the crate and inspect the shelffor any dents or damage.

If any damage is noted, contact the carrier immediately

Battery and Accessories check (4 Blocks/string and Bus-bar*4)

Rectifier *3 modules check.

Un-packing process without separate cabinet

Page 8: 02 outdoor install process

Page 8

AC main input Terminal BlockFor 3 phases and neutral connections

AC Grounding Bus Bar 4pcs of M6 insert nuts

AC cabling from outside wallslot (L150mm * W60mm)through cable glands and metal wiring ducts to main AC terminations

3pcs of MG32A 3-hole Cable Gland

For cable range (OD): 5~10mm

AC Power Install

Page 9: 02 outdoor install process

Page 9

AC MAINS INPUT1 PHASE 220V 50/60Hz

S T

AC BREAKER 3P

N

R PE

SURGE ARRESTER

AC-T&SURGE-TAC-S&SURGE-S

R

TS

AC-R&SURGE-R

AC-N

N

SURGE-SSURGE-T

SURGE-R

L N

3P 380Vac Start Type

AC Power Install

1P 220Vac Type

AC MAINS INPUT3 PHASE 380V + N 50/60Hz

S T

AC BREAKER 3P

N

R PE

SURGE ARRESTER

AC-T&SURGE-TAC-S&SURGE-S

R

TS

AC-R&SURGE-R

AC-N

N

SURGE-SSURGE-T

SURGE-R

R S T N

Page 10: 02 outdoor install process

Page 10

Battery Install

Every 4 months

Every 8 months

Recommended supplementary charge interval

Under 20℃ to 30℃(68℉ to 86℉ )

Under 20℃ (68℉)

Storage Temperature

Battery Tray

+-

Page 11: 02 outdoor install process

Page 11

Battery Install

Battery Breaker 125A*2

Page 12: 02 outdoor install process

Page 12

E/// RBS2216 System Install

Page 13: 02 outdoor install process

Page 13

E/// RBS2216 System Install

Low Priority Load BK*4

High Priority Load BK*2/Light/HEX/FAN

High Priority BK*3

Page 14: 02 outdoor install process

Page 14

E/// RBS2216 System Install

The shelf comes fully assembled and all the connections are made at the factory. There is no internal, shelf or module wiring required.

All wiring to the breaker are use lead with striped ends. Ensure to tight the screw and keep the wires are all into the breaker terminal, no any wires or threads are remain outside of the breaker to avoid short-circuit. Refer to the figure below.

Remain wires or threads

O.K. N.G.

Page 15: 02 outdoor install process

Page 15

RBS2216 Power System Bays Configurations

Air Filter Frame mountedon Front Door

Power systemClimate Control Unit

Bottom cable entries

Fan tray mounted on inside of roof

4U Space for DDF-OVP

2nd Battery Shelf

1st Battery Shelf

AC termination

Changeover Switch

Cable gland for DC cables to equipment bay

Metal duct to AC termination

External Alarm Terminal

(Battery excluded in cabinet)

(Battery excluded in cabinet)

Estimated Weight: 127 Kg (With Power system)(Battery strings, DF-OVP excluded)

E/// RBS2216 System Install

Page 16: 02 outdoor install process

Page 16

RBS2216 Equipment Bay Configurations

RBS2216

160 W/K Heat Exchanger

Plinth

7pcs of 3-hole Cable Gland reserved(Details show on later page)

10U(H) Max. Space for Transmission Equipment

4pcs of M10 insert nuts pre-installed in Bracket For RBS2216 Installation, Pitch: 572mm * 307mmLoad capacity(Tray): 300Kg

Micro Switch (Front Door)

Estimated Weight: 140 Kg (With HEX)(Transmission equipment excluded)

Add markings on base frame for for RBS2216 installation.

10mm

E/// RBS2216 System Install

Page 17: 02 outdoor install process

Page 17

E/// RBS2111 System Install

Low Priority Load BK*3+1

High Priority Load BK*2 / Light/Fan

Return Bus-Bar Terminal

High Priority BK*4

Page 18: 02 outdoor install process

Page 18

HEXAverage capacity case : 2pcs HEXHigh capacity case : 3pcs HEX

RBS2111 (2.1M) Configurations

Fan tray mounted on inside of side panel

Power system

Changeover SwitchClimate Control Unit

Genset Socket, 32A 3N~(R,S,T,N ,PE)

Air filter

TransmissionEquipment

10U(H) x 19”(W)208(D) Maxi.

Partition

Equipment Compartment

Power system and Battery compartment (Battery excluded in cabinets)

(Battery excluded in cabinets)

2nd Battery ShelfMax. Space suitable forCSB TPX122200 * 4pcs

1st Battery ShelfMax. Space suitable forCSB TPX122200 * 4pcs

Smoke Sensor

Humidity Sensor

DC Light mounted on inside of Frame

E/// RBS2111 System Install

Page 19: 02 outdoor install process

Page 19

System Power On

System Power “ON” Check point belowAC Power Check (Multi-Meter check)

3Phases/Single phase confirm (AC Jumper by Terminal).

AC surge Protect Check.(Green Color)

Turn “OFF” all breaker(Load/Battery) in System

Plug-in one rectifier in system.

Power “ON” AC Beaker in System (System Operation)

Every all right then Plug-in other 2 rectifiers.

Page 20: 02 outdoor install process

Page 20

System Controller Function Check

System Parameter Setting

Parameter/Relay SettingSystem Battery Capacity Setting.

System Date Rear Time Setting.

System Alarm Point Setting

Relay Setting & Demo

CCU Setting/Operation

Page 21: 02 outdoor install process

Page 21

Controller Parameter Setting (Battery Capacity)

* Function architecture varies in different systems

DC SettingDCV settingCL setting

Batt. SettingBatt. Par.T-Comp BDT Test B-EQU

PasswordNew PW Cfm PW Default (0000)

HomeDCVDCI

Sys Status(FL/EQU)Alarm Existing

Sys Info Sys Setting Current Alarm

Alarm Setting ACV,

DCV,LVDS, OTP,EQU, Batt.Test.

Alarm ResetReset HVSD

Reset Com-fail

GeneratorON/OFF

Language English繁體中文簡體中文

Efficn.t Mgt.ON/OFF

Comm.ModbusBaudrate

Temp. UnitON/OFF

System Controller Function Check

Date SettingYear/month/

day/time

Page 22: 02 outdoor install process

Page 22

Controller Parameter Setting (Date setting)

* Function architecture varies in different systems

DC SettingDCV settingCL setting

Batt. SettingBatt. Par.T-Comp BDT Test B-EQU

PasswordNew PW Cfm PW Default (0000)

HomeDCVDCI

Sys Status(FL/EQU)Alarm Existing

Sys Info Sys Setting Current Alarm

Alarm Setting ACV,

DCV,LVDS, OTP,EQU, Batt.Test.

Date SettingYear/month/

day/time

Alarm ResetReset HVSD

Reset Com-fail

GeneratorON/OFF

Language English繁體中文簡體中文

Efficn.t Mgt.ON/OFF

Comm.ModbusBaudrate

Temp. UnitON/OFF

System Controller Function Check

Page 23: 02 outdoor install process

Page 23

Controller Parameter Setting (Alarm Point)

* Function architecture varies in different systems

DC SettingDCV settingCL setting

PasswordNew PW Cfm PW Default (0000)

HomeDCVDCI

Sys Status(FL/EQU)Alarm Existing

Sys Info Sys Setting Current Alarm

Alarm Setting ACV,

DCV,LVDS, OTP,EQU, Batt.Test.

Alarm ResetReset HVSD

Reset Com-fail

GeneratorON/OFF

Language English繁體中文簡體中文

Efficn.t Mgt.ON/OFF

Comm.ModbusBaudrate

Temp. UnitON/OFF

System Controller Function Check

Date SettingYear/month/

day/time

Batt. SettingBatt. Par.T-Comp BDT Test B-EQU

Page 24: 02 outdoor install process

Page 24

PIN1PIN6

Relay Terminal Setting

Page 25: 02 outdoor install process

Page 25

CCU setting Process

Page 26: 02 outdoor install process

Page 26

Alarm IndicationItem Alarm Description Type LED 7-Segment

LED1 CCU Fail Alarm Climate Control Unit

shunt down2 Fan 1 Fail Alarm The fan or heat

exchanger that Fan 1port controlled isfailed.

Drycontact

Alarm(red)

3 Fan 2 Fail Alarm The fan or heatexchanger that Fan 2port controlled isfailed.

Drycontact

Alarm(red)

4 Heater Fail Alarm The heater thatHeater port controlledis failed.

Drycontact

Alarm(red)

5 Air Conditioner Fail Alarm The air conditionerthat A/C portcontrolled is failed.

Drycontact

Alarm(red)

6 Intrusion Alarm The door is opened. Drycontact

Alarm(red)

7 High Temperature Alarm The internaltemperature is overthe high limit setting.

Drycontact

Alarm(red)

8 Low Temperature Alarm The internaltemperature is underthe low limit setting.

Drycontact

Alarm(red)

9 High Water Alarm Water level in thecabinet is over thesensor limit.

Drycontact

Alarm(red)

10 Smoke / Fire Alarm Smoke or fire isdetected in thecabinet.

Drycontact

Alarm(red)

11 High Humidity Alarm The humidity in thecabinet is over thesensor limit.

Drycontact

Alarm(red)

Page 27: 02 outdoor install process