Page 1
Telecom Power Outdoor System Presentation
NTBU
Page 2
ContentsSystem Overview
Unpack(1.8M, 2.1 & 1.6M) System Check-->
AC Power Install -->
Battery Install--> (Very Heavy)
Telecom RBS Equipment Install--> (Very Heavy)
Power ON -->
Function Controller (Time & Battery Capacity Setting)
Q&A
Page 3
Un-packing process without separate cabinet(RBS2216, ESOA150-ABA01)
Plastic Strap
Roof
Rem ove direction
Lift wole cabinet w ith 4pcs eyebolt.
UNPACK DRAW INGATT.(2)
Left cabinetR ight cabinet
S tep 4Release screws from wooden fram e and pallet, then Rem ove wooden fram e.
Step 3Rem ove Roof.
Screw(Both side)
S tep 7Rem ove plinth cover and then release 8 pcs screws from pallet.
P linth cover(Both side)
S tep 1Rem ove Tray.
PE BAG
S tep 5Rem ove PE BAG.
Front Door
S tep 2Rem ove Tube.
S tep 6O pen front door.
S tep 8C lose front door before lift the cabinet up.
Page 4
RBS2216 (ESOA150-ABA01)
A S S E M B LY D R A W IN GA TT .(3 )
S tep 1R e lease screw s fo r the assem bly le ft & righ t cab ine t.R e lease a ll o f cab les and connecto rs be tw een le ft & righ t cab ine t.
S tep 5R elease screw s fo r fron t door and open the door then fab rica te screw s to o rig ina l loca tion .
Left cab ine t
S crew
S crew
S tep 6Fabrica te screw s fo r the assem bly le ft & righ t cab ine t.Then fab rica te screw s fo r the assem bly p lin th cover.
R igh t cab ine t
S crew ;x6pcs
S crew ;x6pcs
Le ft cab ine t
S crew (B oth s ide)
P lin th cover(B o th s ide)
R igh t cab ine tLe ft cab ine t
S tep 2R em ove p lin th cover from le ft & righ t cab ine t and then re lease 8 pcs screw s from pa lle t.
S tep 7P rin t s ilicone a round s ide o f cab ine t.Then fab rica te screw s fo r the assem bly roo f.
S ilicone
S crew
S tep 3R e lease screw s then fix doo r by p rev ious screw s to p reven t door open .
R oof
S tep 4C lose le ft door and righ t door.L ift by 2pcs eyebo lt fo r each cab ine t.
S crew
Un-packing process without separate cabinet
Page 5
S tep 4Take out screw s from w ooden box and pa lle t, then R em ove w ooden box.
R oof
S tep 5R em ove P E B A G .
P E B A G
P lin th cover(B oth s ide)
U N PA C K D R AW IN GA TT .(2)
S tep 2R em ove Tube.
S tep 3R em ove R oof.
S tep 6O pen fron t door.
S tep 7R em ove p lin th cover and then re lease 4 pcs screw s from pa lle t.
S tep 1R em ove T ray.
S crew (B oth s ide)
RBS2111 2.1m (ESOA150-ABB01, ESOA150-ABB02)Un-packing process without separate cabinet
Page 6
RBS2111, 1.6m (ESOA150-ABC01)
PE B A G
S tep 2R em ove Tube.
S tep 3Take out screw s from w ooden fram e and pa lle t, then R em ove w ooden box.
S tep 4R em ove P E B AG .
S tep 5O pen fron t door.
S tep 6R em ove p lin th cover and th en re lease 4 pcs screw s from pa lle t.
S tep 1R em ove Tray.
S crew (B oth s ide)
U N P A C K D R A W IN GATT .(2)
P lin th cover(B oth s ide)
Un-packing process without separate cabinet
Page 7
Preliminary Inspection
System CheckPrior to removing the system from the crate, not any damage to
the crate.
Remove the system cabinet from the crate and inspect the shelffor any dents or damage.
If any damage is noted, contact the carrier immediately
Battery and Accessories check (4 Blocks/string and Bus-bar*4)
Rectifier *3 modules check.
Un-packing process without separate cabinet
Page 8
AC main input Terminal BlockFor 3 phases and neutral connections
AC Grounding Bus Bar 4pcs of M6 insert nuts
AC cabling from outside wallslot (L150mm * W60mm)through cable glands and metal wiring ducts to main AC terminations
3pcs of MG32A 3-hole Cable Gland
For cable range (OD): 5~10mm
AC Power Install
Page 9
AC MAINS INPUT1 PHASE 220V 50/60Hz
S T
AC BREAKER 3P
N
R PE
SURGE ARRESTER
AC-T&SURGE-TAC-S&SURGE-S
R
TS
AC-R&SURGE-R
AC-N
N
SURGE-SSURGE-T
SURGE-R
L N
3P 380Vac Start Type
AC Power Install
1P 220Vac Type
AC MAINS INPUT3 PHASE 380V + N 50/60Hz
S T
AC BREAKER 3P
N
R PE
SURGE ARRESTER
AC-T&SURGE-TAC-S&SURGE-S
R
TS
AC-R&SURGE-R
AC-N
N
SURGE-SSURGE-T
SURGE-R
R S T N
Page 10
Battery Install
Every 4 months
Every 8 months
Recommended supplementary charge interval
Under 20℃ to 30℃(68℉ to 86℉ )
Under 20℃ (68℉)
Storage Temperature
Battery Tray
+-
Page 11
Battery Install
Battery Breaker 125A*2
Page 12
E/// RBS2216 System Install
Page 13
E/// RBS2216 System Install
Low Priority Load BK*4
High Priority Load BK*2/Light/HEX/FAN
High Priority BK*3
Page 14
E/// RBS2216 System Install
The shelf comes fully assembled and all the connections are made at the factory. There is no internal, shelf or module wiring required.
All wiring to the breaker are use lead with striped ends. Ensure to tight the screw and keep the wires are all into the breaker terminal, no any wires or threads are remain outside of the breaker to avoid short-circuit. Refer to the figure below.
Remain wires or threads
O.K. N.G.
Page 15
RBS2216 Power System Bays Configurations
Air Filter Frame mountedon Front Door
Power systemClimate Control Unit
Bottom cable entries
Fan tray mounted on inside of roof
4U Space for DDF-OVP
2nd Battery Shelf
1st Battery Shelf
AC termination
Changeover Switch
Cable gland for DC cables to equipment bay
Metal duct to AC termination
External Alarm Terminal
(Battery excluded in cabinet)
(Battery excluded in cabinet)
Estimated Weight: 127 Kg (With Power system)(Battery strings, DF-OVP excluded)
E/// RBS2216 System Install
Page 16
RBS2216 Equipment Bay Configurations
RBS2216
160 W/K Heat Exchanger
Plinth
7pcs of 3-hole Cable Gland reserved(Details show on later page)
10U(H) Max. Space for Transmission Equipment
4pcs of M10 insert nuts pre-installed in Bracket For RBS2216 Installation, Pitch: 572mm * 307mmLoad capacity(Tray): 300Kg
Micro Switch (Front Door)
Estimated Weight: 140 Kg (With HEX)(Transmission equipment excluded)
Add markings on base frame for for RBS2216 installation.
10mm
E/// RBS2216 System Install
Page 17
E/// RBS2111 System Install
Low Priority Load BK*3+1
High Priority Load BK*2 / Light/Fan
Return Bus-Bar Terminal
High Priority BK*4
Page 18
HEXAverage capacity case : 2pcs HEXHigh capacity case : 3pcs HEX
RBS2111 (2.1M) Configurations
Fan tray mounted on inside of side panel
Power system
Changeover SwitchClimate Control Unit
Genset Socket, 32A 3N~(R,S,T,N ,PE)
Air filter
TransmissionEquipment
10U(H) x 19”(W)208(D) Maxi.
Partition
Equipment Compartment
Power system and Battery compartment (Battery excluded in cabinets)
(Battery excluded in cabinets)
2nd Battery ShelfMax. Space suitable forCSB TPX122200 * 4pcs
1st Battery ShelfMax. Space suitable forCSB TPX122200 * 4pcs
Smoke Sensor
Humidity Sensor
DC Light mounted on inside of Frame
E/// RBS2111 System Install
Page 19
System Power On
System Power “ON” Check point belowAC Power Check (Multi-Meter check)
3Phases/Single phase confirm (AC Jumper by Terminal).
AC surge Protect Check.(Green Color)
Turn “OFF” all breaker(Load/Battery) in System
Plug-in one rectifier in system.
Power “ON” AC Beaker in System (System Operation)
Every all right then Plug-in other 2 rectifiers.
Page 20
System Controller Function Check
System Parameter Setting
Parameter/Relay SettingSystem Battery Capacity Setting.
System Date Rear Time Setting.
System Alarm Point Setting
Relay Setting & Demo
CCU Setting/Operation
Page 21
Controller Parameter Setting (Battery Capacity)
* Function architecture varies in different systems
DC SettingDCV settingCL setting
Batt. SettingBatt. Par.T-Comp BDT Test B-EQU
PasswordNew PW Cfm PW Default (0000)
HomeDCVDCI
Sys Status(FL/EQU)Alarm Existing
Sys Info Sys Setting Current Alarm
Alarm Setting ACV,
DCV,LVDS, OTP,EQU, Batt.Test.
Alarm ResetReset HVSD
Reset Com-fail
GeneratorON/OFF
Language English繁體中文簡體中文
Efficn.t Mgt.ON/OFF
Comm.ModbusBaudrate
Temp. UnitON/OFF
System Controller Function Check
Date SettingYear/month/
day/time
Page 22
Controller Parameter Setting (Date setting)
* Function architecture varies in different systems
DC SettingDCV settingCL setting
Batt. SettingBatt. Par.T-Comp BDT Test B-EQU
PasswordNew PW Cfm PW Default (0000)
HomeDCVDCI
Sys Status(FL/EQU)Alarm Existing
Sys Info Sys Setting Current Alarm
Alarm Setting ACV,
DCV,LVDS, OTP,EQU, Batt.Test.
Date SettingYear/month/
day/time
Alarm ResetReset HVSD
Reset Com-fail
GeneratorON/OFF
Language English繁體中文簡體中文
Efficn.t Mgt.ON/OFF
Comm.ModbusBaudrate
Temp. UnitON/OFF
System Controller Function Check
Page 23
Controller Parameter Setting (Alarm Point)
* Function architecture varies in different systems
DC SettingDCV settingCL setting
PasswordNew PW Cfm PW Default (0000)
HomeDCVDCI
Sys Status(FL/EQU)Alarm Existing
Sys Info Sys Setting Current Alarm
Alarm Setting ACV,
DCV,LVDS, OTP,EQU, Batt.Test.
Alarm ResetReset HVSD
Reset Com-fail
GeneratorON/OFF
Language English繁體中文簡體中文
Efficn.t Mgt.ON/OFF
Comm.ModbusBaudrate
Temp. UnitON/OFF
System Controller Function Check
Date SettingYear/month/
day/time
Batt. SettingBatt. Par.T-Comp BDT Test B-EQU
Page 24
PIN1PIN6
Relay Terminal Setting
Page 25
CCU setting Process
Page 26
Alarm IndicationItem Alarm Description Type LED 7-Segment
LED1 CCU Fail Alarm Climate Control Unit
shunt down2 Fan 1 Fail Alarm The fan or heat
exchanger that Fan 1port controlled isfailed.
Drycontact
Alarm(red)
3 Fan 2 Fail Alarm The fan or heatexchanger that Fan 2port controlled isfailed.
Drycontact
Alarm(red)
4 Heater Fail Alarm The heater thatHeater port controlledis failed.
Drycontact
Alarm(red)
5 Air Conditioner Fail Alarm The air conditionerthat A/C portcontrolled is failed.
Drycontact
Alarm(red)
6 Intrusion Alarm The door is opened. Drycontact
Alarm(red)
7 High Temperature Alarm The internaltemperature is overthe high limit setting.
Drycontact
Alarm(red)
8 Low Temperature Alarm The internaltemperature is underthe low limit setting.
Drycontact
Alarm(red)
9 High Water Alarm Water level in thecabinet is over thesensor limit.
Drycontact
Alarm(red)
10 Smoke / Fire Alarm Smoke or fire isdetected in thecabinet.
Drycontact
Alarm(red)
11 High Humidity Alarm The humidity in thecabinet is over thesensor limit.
Drycontact
Alarm(red)
Page 27
Q & A