133
Passion for Excellence COMPANY PROFILE Ammico Contracting Co. W.L.L. www.ammico.biz QATAR SAUDI ARABIA Ammico Contracting Co. W.L.L. Ammico Int'l Contracting Co. Ltd. P.O. Box 14330, Doha P.O Box 9530, Jeddah 21423 Tel: +974 4488 6531 Tel: +966 2 206 9491 Fax: +974 4488 6507 Fax: +966 2 206 9591 CHINA – BEIJING CHINA – HONG KONG Ammico Contracting Co. (Beijing) Ltd. Ammico Contracting Co. (Hong Kong) Ltd. P.O. Box: 341 Level 12, Infinitus Plaza Tel: +86 10 69773728 Tel: +852 3796 3557 Fax: +86 10 69773728 Fax: +852 3796 3000

Company profile[1]

Embed Size (px)

Citation preview

Page 1: Company profile[1]

Passion for Excellence

COMPANY PROFILE

Ammico Contracting Co. W.L.L. www.ammico.biz

QATAR SAUDI ARABIA Ammico Contracting Co. W.L.L. Ammico Int'l Contracting Co. Ltd.

P.O. Box 14330, Doha P.O Box 9530, Jeddah 21423

Tel: +974 4488 6531 Tel: +966 2 206 9491 Fax: +974 4488 6507 Fax: +966 2 206 9591

CHINA – BEIJING CHINA – HONG KONG

Ammico Contracting Co. (Beijing) Ltd. Ammico Contracting Co. (Hong Kong) Ltd.

P.O. Box: 341 Level 12, Infinitus Plaza

Tel: +86 10 69773728 Tel: +852 3796 3557

Fax: +86 10 69773728 Fax: +852 3796 3000

Page 2: Company profile[1]

AMMICO COMPANY PROFILE  

TABLE OF CONTENTS

DESCRIPTION SECTION

Introduction to the Company 1

Company Organization 2

List of Key Personnel 3

Details of Equipment Owned by Ammico 4

List of Projects in Progress 5

List of Piling Works Projects Completed 6

List of Marine Works Projects Completed 7

List of Earthworks Projects Completed 8

Resumes of Key Personnel 9

Copies of Various Trade Licenses 10

Photo Gallery 11

ISO & OHSAS Certificates and Company Policies 12

Safety Awards 13

Page 3: Company profile[1]

AMMICO COMPANY PROFILE  

1

Introduction to the Company

Page 4: Company profile[1]

INTRODUCTION TO AMMICO

Ammico is a leading specialist contracting company with forty years international experience. Over these years, Ammico has developed expertise that is second to none in the following: Foundation Engineering

BORED CAST-IN-SITU PILING INCLUDING SECANT PILES

DIAPHRAGM WALL INSTALLATION

EARTH RETENTION SYSTEMS FOR DEEP EXCAVATIONS

DEWATERING FOR DEEP EXCAVATIONS

INSTALLATION OF PERMANENT, TEMPORARY AND REMOVABLE GROUND ANCHORS

JET GROUTING, MICROPILING, SOIL NAILING, SHOTCRETING

SOIL IMPROVEMENT USING VIBROFLOTATION TECHNIQUE & DYNAMIC COMPACTION

Ground Engineering & Civil Works SITE PREPARATION & EARTHWORKS

DEEP EXCAVATION WORKS / ROCK CUTTING

LAYING OF UNDERGROUND UTILITIES AND ASSOCIATED CIVIL WORKS

Marine Works OFFSHORE PILING

CONSTURCTION OF JETTIES

SHORE PROTECTION, BREAKWATERS

The company maintains a fleet of state of the art equipment for execution of its works and invests heavily each year in purchase of new equipment and in maintaining the existing equipment in prime working order. Ammico’s true strength, however, is its dedicated and highly professional team, each member of which excels in his respective discipline. The capabilities of this resource are continuously enhanced by encouraging teamwork and by rewarding initiative and innovation, by regular training of existing staff and by induction of new personnel with promising potential. The company gives utmost importance to honouring of commitments and establishing harmonious working relationships with its clients. It is a source of great pride for Ammico that all projects it has undertaken so far have been completed to the entire satisfaction of the clients. During the past four decades, Ammico has established a reputation for speed and quality of work, technical skill and know-how of its staff and its ability to deliver under demanding site conditions and tight schedules. We cherish this reputation and shall strive tirelessly to improve in all our present and future endeavours.

Page 5: Company profile[1]

AMMICO COMPANY PROFILE  

2

Company Organization

Page 6: Company profile[1]

Design Engineers Admin Officers Site Managers Site Managers Site Managers Chief Mechanic Safety Supervisors QA/QC Engineers

Planning Engineers Procurement Officers Site Superintendents Site Superintendents Site Superintendents Safety Officers

Estimation Engineers Material Expeditors Senior Project Engineers Senior Project Engineers Senior Project Engineers Assistant Mechanics Document Controller

Quantity Surveyors HR Officers Project Engineers Project Engineers Project Engineers Fabricators / Fitters

Draftsman Stores Officers Site Engineers Site Engineers Site Engineers Welders

Operators

Drivers

PROJECT MANAGERSPROJECT MANAGERS

MANAGER

MARINE DIVISION

Uygar Koprucu

PROJECT MANAGERS

CONTRACTS MANAGER

Shehzad Akmal

DEPUTY GENERAL MANAGER

(PILING WORKS)

Muzaffar Iqbal Anjum

DEPUTY GENERAL MANAGER

(EARTHWORKS)

Sher Ali Ismaily

DESIGN & PROPOSALS

MANAGER

QA/QC InspectorsMechanics

QA/QC MANAGERPLANT & EQUIPMENT

MANAGER

Gorkem Dora Toheed Ahmed

ADMIN & COMMERCIAL

MANAGER

Balaji Pattabbiraman

HSE MANAGER

Hammad HakeemMuhammad Imran

Site Foremen

Surveyors

Site Foremen

Surveyors

Site Foremen

Surveyors

AMMICO ORGANIZATION CHART

CHIEF EXECUTIVE OFFICER

Jamal Nasir

DIRECTOR

Fazal Kazi

MANAGER

EARTHWORKS DIVISION

Pankaj Kohli

MANAGER

GEOTECH DIVISION

P.Kumaresan

Page 7: Company profile[1]

AMMICO COMPANY PROFILE  

3

List of Key Personnel

Page 8: Company profile[1]

Sr.No.

Name Designation Education Experience

1 Jamal Nasir Chief Executive Officer M.S.Civil Engineering 29 years

2 Muzaffar Iqbal Anjum Deputy General Manager B.S.Civil Engineering 19 years

3 Mohammad Ashfaq Anwar Country Manager - Saudi Arabia M.S. Civil Engineering 20 years

4 Sher Ali Ismaily Manager - Earthworks Division B.S. Civil Engineering 28 years

5 Uygar Koprucu Manager - Marine Division B.S.Civil Engineering 15 years

6 Shehzad Akmal Contract Manager B.Tech (Hons) Degree 19 years

7 Gorkem Dora Design & Proposal Manager B.S.Civil Engineering 18 years

8 Hammad Hakeem HSE Manager B.S. Chemical Engineering 12 years

9 Toheed Ahmed QA/QC Manager B.S. Civil Engineering 12 years

10 Muhammad Imran Superintendent Plant and Equipment B.S Mechanical Engineering 14 years

11 Mohammad Ramzan Saqib Asst. General Manager M. Com 21 years

12 Mohammad Imran Farooqi Asst. General Manager - KSA M.B.A 20 years

13 Balaji Pattabhiraman Admin & Commercial Manager M. Com 27 years

14 Hafiz Ashfaq Ahmed Procurement Manager M. Com 9 years

15 P. Kumaresan Project Manager B.S.Civil Engineering 21 years

16 Pankaj Kohli Project Manager - Earthworks Division B.S.Civil Engineering 17 years

17 Uday Shankar Shah Project Manager B.S. Civil Engineering 20 years

18 Joel E. Santayo Project Manager B.S. Civil Engineering 15 years

19 Shahid Baig Project Manager B.Technical Civil Eng. 15 years

20 Umair Farooq Project Manager B.S. Geological Eng. 6 years

21 Mo. Mahmoud Hamed Omran Project Manager B.S. Civil Engineering 9 years

22 Hussein Yousry Abdelhameed Project Manager B.S. Mechanical Engineering 9 years

23 Rajesh Belle Sadananda Project Manager B.S. Civil Engineering 22 years24 Gurvant Singh Construction Manager Dip. in Civil Engineering 20 years25 John Mathai Construction Manager Dip. in Civil Engineering 19 years26 Hashim Khan Project Cordinator Post Graduate 15 years27 Amjad Hussain Civil Engineer B. Tech Civil Engineering 14 years28 Uday Kumar Das Civil Engineer B.S. in Civil & Environmntal E 8 years29 Md Shiful Islam Civil Engineer B.S. in Civil Engineering 7 years30 Nareshkumar Venugopal Civil Engineer B.S. in Civil Engineering 3 years31 Selvamurugan Chellasamy Civil Engineer B.S. in Civil Engineering 1 year32 Dave Castano Site Engineer B.E. Electrical Eng. 20 years33 Ibrar Hussain Site Engineer Dip. in Civil Engineering 8 years34 Ismail Khan Site Engineer Dip. in Civil Engineering 8 years35 James Ryan Riotita Site Engineer B.S. Civil Engineering 9 years36 Yub Raj Yonghang Site Engineer B.S. Civil Engineering 1 year37 Warlito Balbuena Site Engineer B.S. Civil Engineering 15 years38 Muhammad Waqas Arshad Site Engineer B.Sc Civil Engineering 3 years39 Muhammad Zaheer Site Engineer Dip[. In Civil Engineering 9 years40 Farrukh Saleem QA/QC Engineer B.S. Geological Engineering 3 years41 Joel Sto.Thomas QA/QC Engineer B.S. Civil Engineering 11 years42 Kafayat Ullah QA/QC Engineer B.S. Geological Engineering 3 years43 Mudassar Altaf Butt QA/QC Engineer B.S. Civil Engineer 1 year44 Muhammad Asad QA/QC Engineer B.S. Civil Engineer 1 year45 Muhammad Irfan QA/QC Engineer B.S. Geological Engineering 3 years46 Vamsi Krishna QA/QC Engineer B. Tech Civil Engineering 5 years47 Ghulam Hussain Sr.Quantity Surveyor Dip. in Civil Engineering 21 years

CORPORATE MANAGEMENT

SITE MANAGEMENT

LIST OF KEY PERSONNEL

List of Key Personnel 1/5

Page 9: Company profile[1]

Sr.No.

Name Designation Education Experience

LIST OF KEY PERSONNEL

48 Muhammad Azam Javaid Site Superintendent Dip. in Civil Engineering 33 years49 Khursheed Ahmad Khan Sr. Supervisor Intermediate 7 years50 Mohammad Niyaz Ahmed Sr. Supervisor Dip.in Civil Engineering 13 years51 Muhammad Arshad Gill Site Supervisor Dip. in Civil Engineering 22 years52 Muhammad Khalil Site Superintendent Dip. in Civil Engineering 24 years53 Zaffar Iqbal Sr. Supervisor Dip. in Civil Engineering 24 years54 Nilesh Thakkar In-Charge Excavation Dip. in Civil Engineering 11 years55 Abhay Kanta Thakur Site Supervisor Intermediate 14 years56 Ali Raza Site Supervisor D.A.E. (Civil Enginering) 2 years57 Basker Thommai John Site Supervisor S.S.L.C. 9 years58 Hasan Ablak Site Supervisor Intermediate 3 years59 Husnain Abbas Site Supervisor Intermediate 4 years60 Masood Javed Site Supervisor B.A. 23 years61 Muhammad Asad Site Supervisor Dip. in Civil Engineering 1 year62 Muhammad Kaleem Site Supervisor Dip. in Civil Engineering 3 years63 Nasar Iqbal Site Supervisor Intermediate 4 years64 Padam Bahadur Karki Site Supervisor Intermediate 9 years65 Rabindra Kumar Bhagat Site Supervisor Dip. in Civil Engineering 9 years66 Raja Muntazer Mehdi Site Supervisor P.M.D.C. 7 years67 Muhammad Zia Usman Site Supervisor Dip. in Civil Engineering 17 years68 Romeo Umbao Escana Logistic Co-ordinator Secondary Graduate 20 years69 Kaushal Kumar Mandal Logistic Co-ordinator Intermediate 9 years70 Suryaman Dev Katuwal Site Supervisor Dip. in Civil Engineering 10 years71 Tahir Mehmood Site Supervisor Post Graduate 1 year72 Naresh Prasad Gupta Rauniyar Site Supervisor Dip. in Civil Engineering 15 years73 Ajay Kumar Panday Foreman S.S.L.C. 4 years74 Arman Ahmad Foreman M.A. 6 years75 Benudhara Patro Foreman B.S.C. 4 years76 Jeganathan Karuppusamy Foreman S.S.L.C. 13 years77 Karuppiah Muthu Foreman S.S.L.C. 15 years78 Lok Bahadur Kutawal Foreman Intermediate 9 years79 Mahendra Kuwar Foreman Dip. in Civil Engineering 16 years80 Muhammad Pehalwan Foreman Intermediate 12 years81 Musha Muslim Abdul Karim Foreman Intermediate 21 years82 Necmi Elici Foreman Intermediate 20 years83 Racleo Guanzon Foreman Intermediate 5 years84 Sanjit Mandal Foreman Intermediate 3 years85 Sujit Kumar Pande Foreman I. Com 4 years86 Kalai Arasan Dumaipandi Foreman Intermediate 17 years87 Someswara Rao Erkudalai Foreman Intermediate 16 years88 Venkatesh Pokale Foreman S.S.L.C. 9 years89 Zaheer Ahmed Boat Captain Tug Master 24 years90 Sebastin Mathew Boat Master Tug Master 22 years91 Khalid Hussain Construction Manager Dip. in Civil Engineering 24 years92 Bam Bahadur Basnet Surveyor Dip. in Civil Engineering 12 years93 Jalal Din Surveyor Dip. in Civil Engineering 8 years94 Muhammad Sidique Ahmed Surveyor Dip. in Civil Engineering 5 years95 Vivek Chaudhary Surveyor Dip. in Civil Engineering 14 years96 Waqar Ali Surveyor Dip. In Land Surveying 5 years97 Waqas Haider Surveyor Dip. in Civil Engineering 4 years98 Raman Bam Surveyor SLC 6 years99 Kumar Shrestha Surveyor Intermediate 8 years100 Keshab Lal Shrestha Asst. Surveyor Intermediate 3 years101 Thangamani Maria Iruthayam Lab Technicator S.S.L.C. 5 years102 Sanjay Kumar Purve Lab Technicator SLC 8 years

List of Key Personnel 2/5

Page 10: Company profile[1]

Sr.No.

Name Designation Education Experience

LIST OF KEY PERSONNEL

103 Zeeshan Haider Raza Planning Manager B.S. Civil Engineering 6 year104 Umair Javaid Warraich Planning Engineer B.S. Civil Engineering 1 year105 Md Arifur Rahman Khan Planning Engineer B.S. Civil Engineering 3 years106 Majid Naeem Civil Engineer B.S. Civil Engineering 1 year107 Muhammad Mujtaba Khadeer Autocad Operator Dip. in Architecture 14 years108 Muhammad Aurangzeb Autocad Operator B.A. Journalism 14 years109 Nilo C. Jalco Autocad Operator Civil Engineering Technology 15 years110 Muhammad Shahid Autocad Operator B. Civil Technology 11 years

111 Salaovdeen Sulaiman A.M Finance B.B.A. 10 years112 Asif Ali Accounts Officer B.Com 6 years113 Badi Uz Zaman Accounts Officer M.B.A 7 years114 Maaz Anser Accounts Officer A.C.C.A. 8 years115 Mohamed Irshath Sihabudeen Accounts Officer Intermediate 6 years116 Kalai Chelvan Accounts Officer M.B.A. Finance 8 years117 Phajle Rabbani Asst. Accounts Officer Intermediate 3 years118 Khaled Taher Admin Officer Intermediate 30 years119 Ali Ahmed Fadul Admin Officer Intermediate 20 years120 Ramesh Putti Admin Officer Intermediate 10 years121 Adrian Willam Lalangan Admin Officer B.S. Management Accounting 6 years122 Raheel Khalid HR Officer B.B.A. 8 years123 Qaisar Iqbal HR Officer M.B.A 7 years124 Mushtaq Hussain HR Officer Intermediate 2 year125 Sandip Kumar Mandal Document Controller Intermediate 9 years126 Anil Kumar Bodige Document Controller Intermediate 1 year127 Bhogendra Raj Dhungana Document Controller S.S.L.C. 2 years128 Jefry Sanchez Document Controller Intermediate 5 years129 Nasir Ahmed Document Controller Intermediate 1 year130 Prem Prasad Lamichhane Document Controller B.A. 5 years131 Srinu Jagiri Document Controller Intermediate 6 years132 Iftikhar Ul Hassan Procurement Officer DAE (Mechanical) 6 years133 Ram Mohan Kodicharla Purchaser Intermediate 5 years134 Nabaraj Ghimire Purchaser Intermediate 10 years135 Suresh Kumar Mahato Purchaser Intermediate 7 years136 Amit Kumar Mandal Purchaser Intermediate 4 years137 Kashif Imran Store In Charge B.A. 6 years138 Usmani Shakeel Ahmed Store Officer T.Y.B.Com 13 years

139 Subash Chand HSE Superintendent Dip. In Fire and Safety 14 years140 Abid Hussain Abid Safety Supervisor BA 6 years141 Asraf Iqbal Usmani HSE Officer Dip.in Safety Management 7 years142 Imtiaz Ahmad Khan Lodhi Safety Officer Dip. In HSE Engineering 13 years143 Jaikesh Kumar Yadav Safety Officer Dip. In Industrial Safety 5 years144 Jawed Alam Safety Officer Intermediate 4 years145 Obaidullah Safety Officer B.A. Geography 7 years146 Taimoor Abbas Safety Officer D.A.E (Electronics) 1 year147 Vinod Kumar Yadav Safety Officer D.A.E (Electronics) 5 years148 Dedevendra Singh Safety Officer Bachelor of Art 4 years149 Meraj Usmani Safety Officer Dip. in Civil Engineering 6 years150 Mohammad Musharraf Khan Safety Officer Dip. In Industrial Safety 5 years151 Kashifur Rahman Safety Officer Dip. In Industrial Safety 5 years152 Hem Sagar Katuwal Safety Officer SLC 4 years153 Thakur Prasad Mishra Safety Officer SLC 5 years154 Mohammad Aamir Khan Safety Officer SLC 5 years

PLANNING & ENGINEERING

SUPPORT SERVICES

HEALTH, SAFETY & ENVIRONMENT

List of Key Personnel 3/5

Page 11: Company profile[1]

Sr.No.

Name Designation Education Experience

LIST OF KEY PERSONNEL

155 Gopal Bahadur Khatri Safety Supervisor SLC 7 years156 Jayvi Espinosa Male Nurse B.S. Nursing 3 years157 Shiju Mathew Male Nurse B.S. Nursing 1 year

158 Ghulam Muhammad Muddasir Mechanical Engineer B.S. Mechanical Engineering 1 year159 Muhammad Nasir Jaffar Mechanical Engineer B.S. Mechanical Engineering 1 year160 Muhammad Raza Mechanical Engineer B.S. Mechanical Engineering 1 year161 Zafar Iqbal Mechanical Engineer B.S. Mechanical Engineering 1 year162 Abdul Wahid Abdulsamthu Mechanical Engineer B.E. Mechanical Engineering 3 years163 Imran Afzal Mechatronics Engineer B.E Mechatronics Eng. 1 year164 Kashif Shabir Mechatronics Engineer B.E Mechatronics Eng. 3 years165 Muhammad Umair Nazar Mechatronics Engineer B.E Mechatronics Eng. 9 years166 Rashid Khalid Mechatronics Engineer B.S. Mechanical Engineering 1 year167 Mohsin Ali Manzoor Workshop Superintendent D.A.E. (Mechanical) 8 years168 Khuram Shehzad Assoc. Mechatronics Engr. D.A.E (Mechatronics Tech.) 3 years169 Muhamad Tahir Abid Assoc. Mechatronics Engr. B.T. (Eectrical) 3 years170 Kashif Razzaq Assoc. Mechanical Engr. D.A.E. (Mechanical Eng.) 1 year171 Muhammad Nasir Assoc. Mechanical Engr. D.A.E. (Mechanical Eng.) 1 year172 Shahbaz Ahmad Assoc. Mechanical Engr. D.A.E. (Mechanical Eng.) 1 year173 Waheed Khan Assoc. Mechanical Engr. D.A.E. (Power Mechanical) 6 years174 Yasir Ali Assoc. Mechanical Engr. D.A.E. (Mechanical Eng.) 1 year175 Muhammad Awais Mechanical Supervisor D.A.E. (Mechanical Eng.) 6 years176 Jatinder Singh Mechanical Supervisor Dip. In Automobile Engr. 5 years177 Muhammad Abdulah Sarwar Mechanical Foreman Intermediate 10 years178 Sajjad Ahmed Mechanical Foreman D.A.E. (Mechanical Eng.) 11 years179 Seran Krishnamurthy Mechanical Foreman Intermediate 15 years180 Mohammed Akram Chief Mechanic D.A.E. (Mechanical Eng.) 29 years181 Javed Anwar Hydraulic Mechanic Intermediate 3 years182 Muhammad Anwar Hydraulic Mechanic Intermediate 4 years183 Mohammad Sarfaraz Hydraulic Mechanic Non Matric 15 years184 Madhesan Nadesan Hydraulic Mechanic Intermediate 2 years185 Swami Bhargav Vijaykumar Hydraulic Mechanic Intermediate 14 years186 Kapil Kumar Pathak Heavy Diesel Mechanic ITI 3 years187 Swaminath Rajdev Gupta Heavy Diesel Mechanic Intermediate 14 years188 Krishnapradeep SuriyanarayananHeavy Diesel Mechanic Intermediate 5 years189 Mohammad Gouse Shaikh Heavy Diesel Mechanic Intermediate 5 years190 Alejandro Salamanca Mechanic Intermediate 3 years191 Arnel Gabaca Mechanic Intermediate 5 years192 Ghulam Abbas Mechanic Intermediate 4 years193 Hasta Bahadur Bk Mechanic Intermediate 14 years194 Khadim Hussain Mechanic Intermediate 13 years195 Krishna Prasad Paudel Mechanic Intermediate 14 years196 Kumar Rai Mechanic Intermediate 14 years197 Mahboob Hussain Mechanic Intermediate 20 years198 Md. Nadeem Arshad Mechanic Dip. In Auto Mechanic 1 year199 Mingmar Gole Mechanic Intermediate 14 years200 Muhammad Afzal Mechanic Intermediate 8 years201 Muhammad Aslam Babar Mechanic Intermediate 11 years202 Muhammad Murtaza Mechanic Intermediate 7 years203 Muhammad Riaz Mechanic Intermediate 15 years204 Multan Chand Mechanic Intermediate 14 years205 Rustam Alam Mechanic Intermediate 6 years206 Saman Pradeep Arachilage Mechanic Intermediate 15 years207 Zaheer Abbas Mechanic Intermediate 7 years208 Dilip Rajbanshi Mechanic Intermediate 4 years

PLANT & EQUIPMENT

List of Key Personnel 4/5

Page 12: Company profile[1]

Sr.No.

Name Designation Education Experience

LIST OF KEY PERSONNEL

209 Radhey Kumar Ray Mechanic Intermediate 5 years210 Surendran Chinnaian Mechanic Intermediate 6 years211 Ali Hussain Assistant Mechanic Intermediate 4 years212 Amir Bhakta Shrestha Assistant Mechanic Intermediate 5 years213 Binod Kumar Singh Assistant Mechanic Intermediate 4 years214 Mastakim Miya Assistant Mechanic Intermediate 6 years215 Dinesh Bk Assistant Mechanic Intermediate 5 years216 Md. Rahmatulla Assistant Mechanic Intermediate 14 years217 Surendra Kumar Dastatma Assistant Mechanic Intermediate 3 years218 Suresh Kumar Sah Assistant Mechanic Intermediate 4 years219 Suman Basnet Assistant Mechanic Intermediate 3 years220 Man Kumar Gurung Assistant Mechanic Intermediate 3 years221 Tekraj Kuwar Assistant Mechanic Intermediate 3 years222 Prem Prasad Dangal Assistant Mechanic Intermediate 3 years223 Dipendra Lama Assistant Mechanic Intermediate 3 years224 Ehtesham Ul Haq Electrical Engineer B.S. Electrical Egineering 15 years

225 Umesh Chandra Gupta Electrical EngineerBachelor of Electrical & Electronics Engr. 3 years

226 Babar Rasool Electical Diploma D.A.E. (Electrical) 1 year227 Nasir Majeed Electical Diploma D.A.E. (Electrical) 3 years228 Shakil Anjum Electrical Diploma D.A.E. (Electrical) 21 years229 Mohan Kumar Sah Electrical Diploma Dip. In Electrical Engr. 5 years230 Ram Kripak Sah Electrical Motor Winder Dip. In Electrical Engr. 10 years231 Hem Bahadur Buddhathoki Electrician D.A.E. (Electrical) 5 years232 Man Bahadur Thapa Electrician Intermediate 7 years233 Mohammad Irshad Alam Electrician Intermediate 4 years234 Muhammad Ashraf Electrician D.A.E. (Electrical) 7 years235 Renato Alburo Electrician Electrical Technology 8 years236 Tol Bahadur Chhetri Electrician Intermediate 4 years237 Umar Ikabal Electrician SLC 4 years238 Santosh Kumar Bhandari Electrician SLC 3 years239 Jamil Ahmad Usmani Electrician SLC 3 years240 Iftikhar Ahmad Auto Electrician Dip. In Electrical Tech. 7 years241 Mahammed Aqeel Auto Electrician Intermediate 5 years242 Nauman Nazir Auto Electrician Intermediate 3 years243 Mohammad Faiyaz Ahmed Auto Electrician Intermediate 6 years244 Harbhajan Singh Auto Electrician Intermediate 9 years245 Toufiq Siddique Auto Electrician Intermediate 5 years246 Sherfuddin Abdul Karim Auto Electrician Intermediate 8 years247 Mohammad Mustakim Auto Electrician Intermediate 7 years248 Sajid Ali Auto Electrician Intermediate 6 years249 Zahid Rasool Auto Electrician D.A.E. (Electrical) 10 years

List of Key Personnel 5/5

Page 13: Company profile[1]

AMMICO COMPANY PROFILE  

4

Details of Equipment Owned by Ammico

Page 14: Company profile[1]

PILING EQUIPMENT OWNED BY AMMICO

Type of Equipment ManufacturerCountry of

ManufactureYear of

ManufactureNo. of Units

CUTTERS / DIAPHRAGM WALLDiaphragm Wall Cutter Bauer BC - 40 Germany 2009 - 2010 2

Details of Equipment Owned by Ammico 1/5

ap ag Wa Cutte aue C 0 Germany 2009 2010 2Diaphragm Wall Cutter Bauer BC - 32 Germany 2007 - 2008 3Diaphragm Wall Cutter Casagrande FD-60 Italy 2008 1

Total : 6PILING / DRILLING RIGHydraulic Rotary Rig Bauer BG- 40 Germany 2009 2Hydraulic Rotary Rig Bauer BC - 36 Germany 2009 3Hydraulic Rotary Rig Bauer BG - 30 Germany 1999 2Hydraulic Rotary Rig Bauer BG 28 Germany 2007 2008 5Hydraulic Rotary Rig Bauer BG - 28 Germany 2007-2008 5Hydraulic Rotary Rig Bauer BG - 25 Germany 2004- 2005 2Hydraulic Rotary Rig Casagrande C600HD Italy 2007 1Hydraulic Rotary Rig SANY SR280 China 2007 1Hydraulic Rotary Rig SANY SR260 China 2008 7Hydraulic Rotary Rig SANY SR250 China 2008 1Hydraulic Rotary Rig SANY SR220C China 2005-2006 4Hydraulic Rotary Rig Bauer BG - 14 Germany 1990 1Hydraulic Rotary Rig Mait HR - 110 Italy 1989 1Hydraulic Rotary Rig HEMCO HR 35 China 2011 1Hydraulic Rotary Rig HEMCO HR 22 China 2011 4Pile Driver Nippon DH658-135M-M9SD Japan 1996 1

Total : 36CRANESCrawler Crane 250 Ton Fushan QUY 250 China 2011 1Crawler Crane 120 Tons Fushan QUY 120 A China 2010 1Crawler Crane 120 Tons Fushan QUY 120 A China 2010 1Crawler Crane 120 Tons Liebher HS885 HD Germany 2005 1Crawler Crane 100 Tons Liebher H875 HD Germany 2008 2Crawler Crane 100Tons Bauer MC64 Germany 2010 2Crawler Crane 90Tons Casagrande C900 Italy 2008 1Crawler Crane 80 Tons Fushan QUY80A China 2008 4Crawler Crane 55 Tons Sumitomo SC550-02 Japan 1998 2Crawler Crane 50 Tons Sany SCC500D China 2006-2007 6C l C 50 T S CX500 C K 1997 1Crawler Crane 50 Tons Samsung CX500 C Korea 1997 1Crawler Crane 50 Tons XCMG 50 China 2006 2Crawler Crane 35 Tons Hitachi KH - 125 Japan 1996 1Mobile Crane 50 Tons XCMG 50 China 2011 2Mobile Crane 25 Tons XCMG 25 China 2011 2Rough terrain Crane 25 Tons KATO KR255 Japan 1995 2

Total : 30ANCHOR DRILL RIGANCHOR DRILL RIGHydraulic Anchor Drill KR-806-2D Germany 2009 2Hydraulic Anchor Drill KR-806-3D Germany 2000-2009 2Hydraulic Anchor Drill KR-807D Germany 1990 1Hydraulic Anchor Drill Casagrande C-6 Italy 2006-2007 2

Total : 7DESANDING PLANTSDesander Unit (CENTER) Bauer - GS-500 Germany 2007 3Desander Unit (LEFT) Bauer BE 250 60 Germany 2007 3Desander Unit (LEFT) Bauer - BE-250-60 Germany 2007 3Desander Unit (RIGHT) Bauer - BE-250-60 Germany 2007 3Desander Unit (CENTER) ZX500 China 2009 1Desander Unit (LEFT) ZX500 China 2009 1Desander Unit (RIGHT) ZX500 China 2009 1

Total : 12

Details of Equipment Owned by Ammico 1/5

Page 15: Company profile[1]

Type of Equipment ManufacturerCountry of

ManufactureYear of

ManufactureNo. of Units

VIBRATORY HAMMERSVibratory Hammer ICE815L Holland - 4Vibratory Hammer ICE416L Holland - 2

Total : 6GROUTING EQUIPMENTGrout Pump Bauer - KP60 Germany 2009 2

Details of Equipment Owned by Ammico 2/5

Grout Pump Bauer - KP60 Germany 2009 2Grout Pump Risen - RG70S China 2007 1Grout Pump Hany - 2515-AX-00 Switzerland 2010-2011 2Grout Pump Chuan Chan C500A China 2009 2Jet Grouting Plant Metax (CIMA) Italy 2010 1Concrete Pump with Mixer Eurodrill UK 2008 2Blast Machine UK-CBSC-100 UK 2011 2Shortcrete Machine Aliva UK 2010 2

lTotal : 14MISCELLANEOUS EQUIPMENTMobile Concrete Pump SANY SY5292THB-37 China - 2Mobile Concrete Pump SANY SY5295THB-37 China - 2Diesel Generator 500 KVA Caterpillar USA - 6Diesel Generator 250 KVA Caterpillar USA - 8Diesel Generator 100 KVA Caterpillar USA - 10Diesel Generator 72 KVA Caterpillar USA - 2Diesel Generator 72 KVA Caterpillar USA 2Diesel Generator 625 KVA Cummins USA - 1Diesel Generator 100 KVA Cummins USA - 6Welding Generator Shindawa China - 7Welding Generator Miller U.K - 2Air Compressor 900 CFM Ingersolrand USA - 4Air Compressor 750 CFM Atlas Capco USA - 5Air Compressor 400 CFM Denyo Japan - 2

N th l d /Vibratory Jack Hammers Caterpillar

Netherland / Holland

- 7

Surveying Total Station Various Various - 3Surveying Theodolites Various Various - 2Survey Levels Various Various - 4Prestressing Equipment Various UAE - 5Drilling Buckets & Augers Various UAE - 70Tremmie Pipes Various Qatar - 6p QConcrete Buckets Various UAE - 3Bentonite Tanks & Silos Various UAE - 70Water Pumps P&W U.K - 38Submersible Pumps Tsurumi Japan - 60

Total : 325TRANSPORTPickup Mitsubishi Japan - 28Pickup Nissan Japan - 11Pickup Nissan Japan - 11Cars Honda / Nissan / Toyota Japan - 16Bus - 55 Seater GMC USA - 5Bus - 55 Seater Tata India - 6Bus - 24 Seater Nissan Japan - 7Van - 14 Seater Nissan Japan - 5

Total : 78

Details of Equipment Owned by Ammico 2/5

Page 16: Company profile[1]

EARTHWORKS EQUIPMENT OWNED BY AMMICO

Type of Equipment ManufacturerCountry of

ManufactureYear of

ManufactureNo. of Units

EXCAVATORExcavator Hitachi Zaxis 870 Japan 2007 1

Details of Equipment Owned by Ammico 3/5

pExcavator Hitachi Zaxis 800 Japan 2004 - 2006 2Excavator Hitachi EX 550E Japan 1998 1Excavator Hitachi Zaxis 800 Japan ₋ 2Excavator Hitachi 210/350 Japan 2006 - 2009 18Excavator Hitachi EX240 Japan 2011 3Excavator Hyundai Rolex 300-305-LC-7 Korea 2009 - 2011 9Excavator Caterpillar 375C USA 2008 - 2009 6Excavator Caterpillar 330C USA 2008 - 2009 2Excavator Caterpillar 330C USA 2008 - 2009 2Excavator Caterpillar 320C USA 2003 - 2009 24Excavator Volvo 210/360 Sweden 2000 - 2009 14Long Boom Excavators Various 2003 - 2009 5Mini Excavator Yanmar 5T ₋ 2

Total: 89DUMP TRUCK/ LOADERDump Truck - 32 m3 Mercedes / Volvo Germany ₋ 65Dump Truck - 19 m3 Mercedes / Volvo Germany ₋ 35Shovel (Loader) Caterpillar 950G/966G/966H USA ₋ 15Shovel (Loader) XCMG China ₋ 4Shovel (Loader) Komatsu WA-420 Japan ₋ 2Shovel (Loader) Hitachi 966H / 310/ 250 Japan 2007 - 2008 8Backhoe Loader JCB Site Master U.K. 1998 - 2008 8

Total: 137TRENCHER/ BULLDOZERTRENCHER/ BULLDOZERTrencher (Drum Cutter) Tesmec TRS 1475-186RH U.K. 2011 1Bulldozer Komatsu D155A / D275 Japan 2010 - 2011 2Bulldozer Caterpillar D9 / D8R USA 2005 - 2011 8

Total: 11MOTOR GRADER/ MOBILE CRUSHERMotor Grader Caterpillar 140 G/H USA ₋ 4Motor Grader Caterpillar 14 G USA ₋ 2M t G d C t ill 12 G USA 4Motor Grader Caterpillar 12 G USA ₋ 4Mobile Crusher Extec C-12+ U.K. ₋ 1Mobile Crusher McCloskey I54 CANADA ₋ 1

Total: 12PRIME MOVER/ VIBRATORY ROLLERPrime mover with low bed 100T Mercedes Germany ₋ 2Prime mover with low bed 50T Daff Netherland ₋ 1Vibratory Roller 10T Dynapac CA250 Sweden 2006 - 2008 8y y pVibratory Roller 20T Bomag BW219 UK 2004 - 2007 2Vibratory (Tandem/ Hand Rollers) Various Capacities Various ₋ 26

Total: 39WATER/ DIESEL TANKERWater Tankers Hino Japan ₋ 6Water Tankers Mercedes Germany ₋ 4Diesel Tanker WOQOD Leased China ₋ 3

Total: 13Total: 13

Details of Equipment Owned by Ammico 3/5

Page 17: Company profile[1]

MARINE EQUIPMENT OWNED BY AMMICO

Type of Equipment ManufacturerCountry of

ManufactureYear of

ManufactureNo. of Units

BARGE / TUG BOATL.O.A.: 123ft

Details of Equipment Owned by Ammico 4/5

Jackup Barge ( Emirate Provided)

Breadth: 78.7ftDepth: 14.7ftLeg Length: 174ft Location: Mesaieed

Holland 1979 1

Spud Barge - S224

Dimension: 180ftX50ftX14 ftSpuds: 02 No's, spud + crane truck & boom rest

Japan 1976 1truck & boom rest.Location: Mesaieed

Grouper Ann (Tug)BHP Main Engine: 1000bhp01 no's Deutz EngineLocation: Mesaieed

Germany 1969 1

Mullet Ann (Tug)BHP Main Engine: 1000bhp2 No's Cummin EnginesLocation: Mesaieed

Malaysia 1994 1

Crew Boat (Ammico)

Craft Name: Ammico34ft Fiber Glass Boat equiped with 2 Yanmar Engines Location: Mesaieed

Sweden - 1

Crew Boat (Ammico1)Craft Name: Ammico136ft Fiber Glass BoatLocation: Doha

UAE - 1Location: Doha

Total : 6

Details of Equipment Owned by Ammico 4/5

Page 18: Company profile[1]

JACK-UP BARGE OWNED BY AMMICO

4 Leg Self Elevating Barge

“Emirates Provider”

GENERAL SPECIFICATION

BUILD Flag : Monrovia, Liberia Year : Rebuilt Year 2011 Builder : Scheepswerf

Heusden –Holland Verolme

Call Sign : A8YZ5 Class : GL + 100A5 Construction Rig,

+ AMC

Official No. : 15160

GRT : 2361

DIMENSIONS L.O.A : 37.5m Breadth : 24.0m Depth : 4.5m Draft Moving : 2.6m Leg Length : 53m Deck Area : 900m2

TANK CAPACITY Fresh Water : 43,500 USG Ballast : 69,000 USG Fuel Oil : 12,500 USG

JACKING SYSTEM Type : Reciprocating pistons Variable Load : 1500 Short Tons Total Elevating Capacity : 2,000 Short tons max. Total Holding Capacity : 3,600 Short tons Jacking Speed : 8m per hour Jacking Capacity Per Leg : 600 Short tons Maximum Water Depth : 35m Air Gap (at maximum water depth) : 5m Penetration : 3m

MACHINERY Generators : Two Caterpiller 3412 375KW M.S.D : Marine Sanitation Treatment Plant & Holding Tank

DECK & MOORING EQUIPMENT Crane : 2 no 3.5 Ton each, Pedestal Mounted Mooring System : Four single drum 20 Ton hydraulic winches with 914.40m,

38mm Wire Rope

Page 19: Company profile[1]

AMMICO COMPANY PROFILE  

5

List of Projects in Progress

Page 20: Company profile[1]

No: Project Name Location (City & Country) Type of Facility Contract Value (QR) Period (mm/yy) Owner Name & Repres. Contact Telephone # & Fax #

1 Bitumen Tank Foundation at MesaieedIndustrial port Mesaieed Industrial Piling Works 5,564,579.00 Dec-2014 to April-2015

Qatar Fuel - Woqod - Saad J AlMuraikhi - procurement &Contracts Manager

P.O.Box: 7777 - Doha QatarTelfax - 4430 9240

2

Construction of Abu Hamour(Musaimeer) Surface & Ground WaterDrainage Tunnel Phase 1 -Construction of Cut-Off Wall

Abu Hamur Cut-Off Wall Work 25,000,000.00 Dec-2014 to Feb-2015Salini Impregilo S.p.A. - Mr.Simone Centis - Contractor'sRepresentative

P.O.Box: 30637 - Tel: 4474 7272 ,Fax: 4414 3418

3Al Bidaa Park - Construction,Completion and Maintenance ofUnderground Car Park nos. 5 7 6

Al Corniche - Doha Piling works 6,516,605.00 Dec-2014 to Apr-2015Bojamhoor Trading & Contracting- Mr. Abdel Nasir Abu Hijleh -Project Manager

P.O.Box: 24159 - Tel 4488 0468Fax; 4488 0471

4Construction of South Central Plant No.05 (CP5) for Qatar Foundation -Education City

Doha, Qatar Excavation works & Disposal 6,999,900.00 Nov-2014 to Jan-2015Gulf Contracting Co. W.L.L.Mr.Grahame McCaig -General Manager

P.O.Box: 3886 - Tel 4499 4499Fax: 4499 4500

5 Qatar Integrated Metro Project - GoldLine Package - RTC/040/2014 Al Sadd, Doha Qatar Installation of Diaphragm Wall 34,000,000.00 July-2014 To June 2015

ALYSJ Joint Venture - Mr. Andreas Tauschinger -Project Director

P.O.Box; 24375, Tel: 4410 9400Fax; 4410 9500

6 Abraj Quartier (AQ 3 & AQ 4) BP-1 - The Pearl Qatar The Pearl Qatar Enabling & Piling Works 23,500,000.00 Mar-2014 to Dec-2015 AKY Real Estate - Mr. Medhat

Sleem P.O.Box: Tel: 4443 9333 Fax:4450 5588

7 Abraj Quartier (AQ 5 & AQ 6)BP-1 - The Pearl Qatar The Pearl Qatar Enabling & Piling Works 23,500,000.00 Mar-2014 to Dec-2015

Al Oraiq Real EstateDevelopment - Mr. Medhat Sleem-

P.O.Box: 560 - Tel: 4493 3344Fax: 4450 5588

8 Al Maroona Beach House in Shamal -Jetty Works Shamal, Qatar Jetty Piling Works 9,472,025.00 May-2014 To Dec-2014-

2014Consolidated Gulf Co.W.L.L. Nr.Faris Abur - Executive Direcror

P.O.Box: 1231 Tel: 4444 1941Fax: 4444 1947

9 Qatar Integrated Railway Project - MajorStations Doha, Qatar Diaphragm Wall, Excavation &

Ground Anchors Works – Msheireb 70,000,000.00 Dec-2013 to Feb -2015SAMSUNG – OHL – QBC JV -Mr. Mr. Sung Uk Ji - ProjectDirector

P.O.Box: 207471Tel: +974 44663752 Fax: +974 4466 4570

10 Qatar Integrated Railway Project -Metro - 1 - Green Line Underground Doha, Qatar Diaphragm Wall, Piling, Anchoring,

Soil Nailing and Shotcrete Works 62,000,000.00 Dec-2013 to Dec-2014POOR-SBG-HBK Joint Venture -Mr. Mr.Michael Ferguson -Procurement Manager

P.O.Box: 207471Tel: +974 44313973 Fax: +974 4432 5688

11 Link Road to the Pearl LusailExpressway Package 1 Lusail, Qatar Secant Piling, Excavation, Disposal

& Backfilling works 126,321,660.89 Jan-2012 to April-2015

Hyundai Engineering &ConstructionMr. Young II CHA - GeneralManager

T: +8227462889 │ F:

+8227463344

LIST OF PROJECTS IN PROGRESS

PROJECT INFORMATION CONTRACT INFORMATION OWNER INFORMATION

Page 1 of 1

Page 21: Company profile[1]

AMMICO COMPANY PROFILE  

6

List of Piling Works Projects Completed

Page 22: Company profile[1]

Description of Work Plot

Area (m2)

Earth

Retention

System

Retaining

Wall

Length

Retaining

Wall Depth

Excavation

Depth

Volume of

Excavation

Ground Water

Depth Prior to

Dewatering

Ground Water

Depth after

Dewatering

Pile Dia

(mm)

Pile Depth

(m)

No. of

Piles

1RasGas Onshore Flow Assurance Project in

Ras Laffan Ras Laffan

Chiyoda Almana Engineering LLC - Mr. Gordon

Clarke Sr. Project Manager. P.O.Box: 22961Tel:

4407-5939 Fax: 4407 4650

Chiyoda Almana Engineering

LLCPiling works - - - - - - - - 800 7m 250 Apr-14 Jul-14

2Al Shareef Residential Tower, Res-15, Lusail

Development, Marina District Lusail, Qatar

Al Shareef Enterprises - Mr. Khalid Shareef Al Emadi

- CEO - P.O.Box: 536 - Tel: 4450 544 Fax: 4450

5588

Medad Engineering Enabling & Piling Works - - - - - - - - 1000mm 9m 211 Apr-14 Sep-14

3 Seef Lusail Presentation Center Lusail, Qatar

Seef Lusail Real Estate Development Company -

Hazem El-Maghraby - Senior Project Manage - P.O.

Box 22438 | Doha | Qatar Tel: +974.4425.3350 |

Mobile: +974.3308.9085

Time Qatar Piling & Shoring works - - - - - - - - 1000mm 10m 100 Nov-13 Apr-14

4Sheraton Park Project

- Doha Qatar Infrastructure, Doha Doha, Qatar

QDVC

Mr. Emmanuel Launay - Deputy Project Manager,

Tel:+974 4453 8436

Fax:+974 4467 7278

QDVCShoring and excavation works

for Sheraton Park Project. 79,276m2

Diaphragm

Wall &

Contiguous

Pile Wall

846m 8.5m-12.5m 7m ~ 18m 960,000m3 - - - - - Dec-14 Dec-2013

5Doha Oasis Mixed Use Development -

Musheirib - Package 1Doha, Qatar

Halul Real Estate Investment Co.

Mr. Victor Agha

T: 44288332/3 │ F: 4428 8444

Projacs / NEB JV

Enabling, Shoring,

Excavation, Dewatering and

Piling Works

73,000m2Soldier Piles

340m 19m - 23m 14m 912,150m3 2.91m 14.75m

800mm

1000mm

11m

17m

742

36 Nov-13 Jan-14

6QNB - Underground Parking & Park in

Towers Area - GE0156

West Bay,

Qatar

Ashghal Public Works Authority

Mr. Lahdan Sager Al-Mohanadi

Chairman of Urgent & Emergency Works Committee

T:4495 1218 │F: 4495 1221

KEO International Consultants Ground Anchoring 200,500m3 - - - - - Jun-13 Feb-14

7 Construction of Lusail Tower - Com-11 Lusail, Qatar

Gulf Contracting Co.W.L.L., Mr.Martin Castles -

Acting General ManagerTel: 4499 4555 Fax; 4499

4500

GHD Piling & Shoring Works - Soldier Piles

64 12m - - - -

600mm

900mm

1200mm

7m-14m 351 Jul-13 Dec-13

8Lusail Package 03 - A3 Pedestrian Bridge

(Bridges 4 A and 6 A)Lusail, Qatar

FCC Citizen Services

Mr. Armando Lazaro Gonzalez

Tender Manager

T: 4414 5611 | F: 4414 5612

-

Piling, Shoring, Excavation,

Back fill and Installation of

MS Pipe works

- Sheet Pile - - - - - - 800mm 10m-18m 72 Mar-2013 Jul-13

9 T.J. Pearl Mansion The Pearl, Qatar

Private Engineering Office

Mr. Nasser Rashid Al-Naimi

-Managing Director

T: 4499 8555 │F: 4499 8585

KEO International Consultants Enabling Works Package 735 640mm 11m 600mm 8m-10m 698 Feb-13 Jun-13

10Musheireb Heart of Doha Project -

Phase 2 & 3

Musheireb,

Doha

Musheireb Properties

Eng. Issa M Al -Mohannadi - CEO

T: 4459 0459 │ F: 4421 6125

Turner International Installation of diaphragm wall,

excavation, dewatering and

piling works

91,528m2

Diaphragm

Wall

&

Secant Pile

Wall

1,148m 19m - 23m 16m - 19m 1,901,406m3 3m 17.7m - 21.2m

900mm

1500mm

1800mm

9m

11m

13m

2,385

209

837

Jul-11 May-13

11 Sheraton Park ProjectWest Bay,

Qatar

QDVC - Mr. Emmanuel Launay - Dty. Project

Manager

T: 4453 8436 │ F: 4467 7278

- Shoring and excavation works Dec-10 May-13

12Residential Villa @ The Pearl Qatar for Mr.

Omar AlfardanThe Pearl, Qatar

Savings Development Company

Mr. Muhibullah Mani

- Chief Operating Manager

T: 4440 8370 │ F: 4440 8407

Arab Engineering Bureau Piling Works - - 550mm - 600mm 13m 259 Nov-12 Jan-13

13Enabling works Phase II for Le Boulevard for

Commercial Bank of Qatar Al Sadd, Doha

Piling Tech W.L.L.

Mr. Emad El Bendery - EPT Gen. Mngr.

T: 4451 0007 │ F: 4451 0006

Enabling works package,

Installation of diaphragm wall -

Diaphragm

Wall 278 22.5 15.5 5016 - - - - - Jun-12 Nov-12

14Centro Hotel by Rotana at Bin Mahmoud for

Mr. Ali Ibrahim Al Malki Doha, Qatar

Al Malki Group

Mr.Ibrahim Al Malki

T: 4441 888 │ F: 4432 2021

Enabling works package - Secant Pile

Wall Apr-12 Nov-12

15 National Library - BP # 7A Education City,

Qatar

Brookfield Multiplex Medgulf JV W.L.L.

Mr. Michael Izzi - Project Director

Tel: +974 4483 0768 / Fax: +974 4483 0663

Astad Project Management

Piling/

Excavation/

Demolition works

- - 500mm - 1200mm 19m 438 Sep-11 May-12

16 Qatar Facilities of Islamic Studies Project Education City,

Qatar

CCC & Teyseer Contracting JV

Mr.Mahdi Salem - Project Manager

Tel: 4467 4842 / Fax: 4467 4258

Astad Project Management Piling works - - 500mm - 1500mm 4m-10m 707 Jun-11 Nov-11

17 North Jeddah Pump Station KSA

Abuljadayel Co. for Contracting & Maintenance Ltd

Eng. M.R. Al Subei - General Manager

Tel: +966 2672 8216 / Fax: +966 2672 7965

Abuljadayel Company

Installation of 1200mm thick

diaphragm wall for circular

shaft

1346 m2

Shaft Area

Diaphragm

Wall

41m dia

circular

shafts

76.5m 65m - - - - - - Oct-10 Mar-11

18 Hurmain High Speed Rail Project (HHSR) Madina, KSA KSA - Piling works for rail bridge - - 21mm - 27mm 1.2m 50 Jan-11 Jun-11

Not Applicable

Not Applicable

LIST OF PILING PROJECT COMPLETED INCLUDING PILING, EXCAVATION, SHORING & DEWATERING WORKS

Sr.

No.Project Name Location Name & Address of the Client Consultant / Project Manager

Details of Project

Commencement

Date

Completion

Date

LIST OF PILING PROJECT COMPLETED INCLUDING PILING, EXCAVATION, SHORING & DEWATERING WORKS

Not Applicable

Not Applicable

Not Applicable

Total 1245 Anchors

List of Piling Works Projects Completed 1/4

Page 23: Company profile[1]

Description of Work Plot

Area (m2)

Earth

Retention

System

Retaining

Wall

Length

Retaining

Wall Depth

Excavation

Depth

Volume of

Excavation

Ground Water

Depth Prior to

Dewatering

Ground Water

Depth after

Dewatering

Pile Dia

(mm)

Pile Depth

(m)

No. of

Piles

Sr.

No.Project Name Location Name & Address of the Client Consultant / Project Manager

Details of Project

Commencement

Date

Completion

Date

LIST OF PILING PROJECT COMPLETED INCLUDING PILING, EXCAVATION, SHORING & DEWATERING WORKS

19 Al-Mardoof Project Madina, KSA - -

Piling works including drilling

of 1000mm diameter bored /

secant piles, assembling &

lowering of steel cages &

concrete pouring for bridges

no. 4 & 5

- - 10000mm 30m 429 Apr-11 Nov-11

20 Jizan Engineering College Jizan, KSA - -

Piling works including

installation of temporary

casing, boring, steel cage

lowering & concrete pouring

- - 750mm - 1000mm 21m 356 May-11 Sep-11

21Construction Package for Museum of Islamic

Art Park Phase - 1Doha, Qatar

Baytur Construction

Mr. Bekir Basir Ecevit

Project Manager

Tel: 4466 2524 / Fax: 4467 8174

Baytur Construction

Piling and sheet piling works

for Meseum of Islamic Art

Park Project

- - 900mm 32m 2 Dec-10 Feb-12

22

Design and Construction of Secant piles for

Micro Tunnelling shafts

Lusail Project - Sewage Treatment Works

(Four shafts of 6.5m to 10m diameter)

Lusail, Qatar

Qatar Building Company Co (QBC)

Mr. Hazem Gazarin - Project Manager

Tel: 4462 5555 / Fax: 4462 5544Hyder ConsultingMiddle East

Installation of Secant Piles,

Excavation and Dewatering

Works

- Secant Pile

Wall

6.5m to 10m

dia circular

shafts

17m ~ 27m 11m ~ 21m 4,930m3 - -880mm

1200mm

17m

22m

27m

98

122Jul-10 Mar-11

23 Kingdom Tower Project Jeddah, KSA - Solentanche BachyExcavation of test piles & test

Barrettes - - 1500mm 75m 2 Aug-10 Oct-10

24Construction Completion and Maintenance of

Ras Ummleigi Beach Villa

Ras Ummleigi,

Qatar

Contraco W.L.L. - Mr. Mohsen Humdoun

- Construction Division Manager

Tel: 4451 0399 / Fax: 4451 0783

PEOConstruction of maintenance

of piling works - - Dec-10 Jan-11

25Construction of Temporary Berth at

MarsarabiaThe Pearl, Qatar

Mr.Omar Alfardan - Director of Marsarabia

Tel: 44208898 / Fax: 44208897Dar Al Handasah

Complete construction of

Temporary Berth,

including installation of

marine piles

- - Jun-10 Oct-10

26 12 New Deprature Gates Project at DIA NDIA, Qatar

Gulf Contracting Co. WLL

Tel: 4477000 / Fax: 4477555

Email: [email protected]

GHD Piling works - - 600mm - 750mm 8m 140 Jul-10 Oct-10

27

Design and Construction of Secant piles for

Micro Tunnelling shafts

Lusail Project - Sewage Treatment Works

(Four shafts of 6.5m to 10m diameter)

Lusail, Qatar

CCC/Teyseer JV

Mr. Rolf Klockow - Project Director

Tel: 4410 2333 / Fax: 4410 2429

Halcrow Piling works - - 900mm 23m 382 Jan-2010 Nov-2010

28

Upgrading Football Fields Lightings -

(Design & Build) at First Grade Sports Clubs

(Al Arabi, Al Rayyan, Al Saad, Al Gharafa

& Qatar Sports Club)

Doha, Qatar

Qatar Olympic Committee (QOC)

Marbu Contracting Co.

Mr. Adnan Mousa - Project Manager

Mob: 5556 5401

Marbu Piling works - - 750mm 10m 128 Mar-2010 Mar-2010

29Al -Quds Tower Development

(5B+G+100 Storeys)West Bay, Doha

Private Engineering Office

Hassan Mohd. Al Neimi

- Acting Director of Project Department

Tel: 4499 8555 / Fax: 4499 8585

Hyder Consulting Middle East

/Arab Engineer Bureau

Installation of diaphragm wall,

excavation , dewatering and

piling works

17,937 m2 Diaphragm

Wall 670m 30m 22m ~ 24m 400,000m3 -8 -25m

1500mm

1200mm

1500mm

18m

15m

28m

139

346

41

Jun-09 Feb-10

30

Qatar National Bank Headquarters Tower

Project

(5B+G+105 Storeys)

West Bay,

Doha, Qatar

Mr. Ebrahim Al Sulaiti - Asst. General Manager

Business Services

Tel: 4425 2008

Email: [email protected]

KEO International Consultants

Installation of diaphragm wall,

excavation, dewatering and

piling works

18,000 m2 Diaphragm

Wall 550m 22m 17m ~ 27m 350,000 m3 4m 22m

1000mm

1200mm

1500mm

14m

24m-36m

24m-46m

60

172

339

Jul-08 Jul-09

31Doha Convention Center & Tower Project

(2B/3B+G+110 Storeys)

West Bay,

Doha, Qatar

Qatari Diar

Mr. Yasir Al Jamal - Projects Manager

Tel: 4485 8333

Email: [email protected]

Turner International /

Hyder Consulting /

STS Consultants

Installation of diaphragm wall,

excavation, dewatering and

piling works

125,912 m2 Diaphragm

Wall 1,600m 12m ~ 17m 8m ~ 16m 1,172,109 m3 6m 12m

900mm

1500mm

10.5m-15m

25m-34m

2,030

104 May-07 Nov-08

32 Energy City Project Lusail, Qatar

Energy City Qatar

Hasham Al Emadi - Chief Executive Officer

Tel: 4499 9111

Web: http://www.energycity.com

ABS International Consultants

Installation of diaphragm wall,

excavation, dewatering and

piling works

25,000 m2 Diaphragm

Wall 565m 16m 11m 185,000 m3 3m 11m

600mm

900mm

1200mm

7m

5m

7m

77

175

20

Nov-08 Jul-09

33 The Pearl Qatar - VB-09 The Pear, Qatar Mr. Mahmoud Abdul Aziz - Area Manager

Tel: 4465 5815 Khatib & Alami Piling works - - - - - - - -

600mm

900mm

1200mm

8m-20m

15m-27m

14m-38m

418

248

428

Oct-08 Mar-09

34Cultural Village Commercial Plaza Car Park

Project

West Bay,

Doha, Qatar

Marbu

Mr.Sudhir Thakur - Project Manager

Tel: 4432 9608 / Fax: 4442 9180

Email: [email protected]

ProjacsInstallation of diaphragm wall

and piling works 36,779 m2

Diaphragm

Wall 173m 12m 6m - - -

750mm

1200mm8m-18m 1,106 May-08 Nov-08

35 Qatalum Project - Mesaieed "A' Mesaieed, Qatar

Mr. Thomas Downs - Sr. Contracts Administrator

Tel: 6659 9551

Email: thomas,[email protected]

SNC-Lavalin Piling works - - - - - - - - 1000mm 22m 1,240 Apr-08 8-Sep

36Lusail Development Marina District Car Park

ProjectLusail, Qatar

Fabrice Martin - Executive Manager

Tel: 4479 2439

Email: [email protected]

QDVCExcavation & piling works for

3 storey car parks (4 Nos.) - - - - - - - - 600mm 10.6m 2,088 Sep-07 Jun-08

37Woqod Tower Project

(4B+G+25 Storeys)

West Bay,

Doha, Qatar

Qatar Fuel Company

Mr. Saad Jumah Al-Meraikhi

- Procurement & Contracts Manager

Tel: 4430 8822

Email: [email protected]

Romatre Projects

Installation of diaphragm wall,

excavation, dewatering and

piling works

3,500 m2Diaphragm

Wall238m 20m 16m 50,855 m3 3m 6m

900mm

1200mm

12m-14m

12m-14m

185

79Nov-07 Mar-08

38 The Pearl Qatar - VB-11 & 17 The Pear, Qatar

Erga Group

Zikar bou chedid - Sr.Project Manager

Tel: 4483 9631 / Fax: 4483 9812

Email: [email protected]

Erga Group Piling works - - - - - - - -

600mm

900mm

1200mm

8m-20m

15m-27m

14m-38m

235

198

285

Nov-07 Feb-08

List of Piling Works Projects Completed 2/4

Page 24: Company profile[1]

Description of Work Plot

Area (m2)

Earth

Retention

System

Retaining

Wall

Length

Retaining

Wall Depth

Excavation

Depth

Volume of

Excavation

Ground Water

Depth Prior to

Dewatering

Ground Water

Depth after

Dewatering

Pile Dia

(mm)

Pile Depth

(m)

No. of

Piles

Sr.

No.Project Name Location Name & Address of the Client Consultant / Project Manager

Details of Project

Commencement

Date

Completion

Date

LIST OF PILING PROJECT COMPLETED INCLUDING PILING, EXCAVATION, SHORING & DEWATERING WORKS

39 2000MW CCPP Project Mesaieed "A" Mesaieed, Qatar

Mr. Carlon Duran - Procurement Manager

Tel: 4427 0833

E-mail: [email protected]

Iberdrola Piling works - - - - - - - -600mm

1000mm

21m

22m

545

415Jul-07 Nov-07

40 The Pearl Qatar - VB-06 & 07 The Pear, Qatar

Projacs International

Mr. Robert Perkins - Sr. Project Manager

Tel: 4442 0902 / Fax: 4442 0857

Email: [email protected]

Projacs International Piling works - - - - - - - -

600mm

900mm

1200mm

10m-15m

20m

19m-25m

284

164

283

Sep-07 Feb-08

41 The Pearl Qatar - VB - 03,04 & 05 The Pear, Qatar

Erga Group

Zikar bou chedid - Sr.Project Manager

Tel: 4483 9631 / Fax: 4483 9812

Email: [email protected]

Erga Group Piling works - - - - - - - -

600mm

900mm

1200mm

8m-20m

15m-27m

14m-38m

418

248

426

Sep-07 Nov-07

42 The Gate Development Project

(3B+G+17 Storeys)

West Bay,

Doha, Qatar

Cansult Limited

Mr. Arne Johansen - Sr. Project Manager

Tel: 4466 7427

Email: [email protected]

Cansult AecomInstallation of diaphragm wall,

piling and excavation works 24,000 m2

Diaphragm

Wall 700m 18m ~ 20m 13m ~ 15m 254,641 m3 4m 15m

900mm

1200mm

6.5m-7.5m

10.0m

607

73Oct-06 Jun-07

43 Qatofin LLDPE Project Mesaieed, Qatar

Snamprogetti - Italy

Pier Paolo Merello - Site Manager

Tel: +39 025201 / Fax: +39 02 52043226

Email: [email protected]

Snamprogetti - Italy Piling works - - - - - - - - 750mm 24.0m 207 Oct-06 Mar-07

44 Al Shamal Beach Villa Project Al Khore, Qatar

Pravite Engineering Office

Mr.Hassan Mohamed Al

-Naemi - Acting Director of Project Dept.

Tel: 4499 8555 / Fax: 4499 8585

GHD Piling works - - - - - - - -

600mm

750mm

900mm

20m-24m

23.5m-25.5m

24m

276 Dec-06 Jul-07

45 Silos for Qatofin Project Mesaieed, Qatar

Vos Logistics

Mr.Rane Bastiaan - Project Manager

Tel: +31 412 699 982

Email: [email protected]

Vos Logistics Piling works - - - - - - - - 750mm 24.0m 106 Dec-06 Jan-07

46 The Pearl Qatar - LPW -10 & 11 The Pear, Qatar

Ahmed Hassan Bilal Trading & Co.

Sanjay Khosla - General Manager

Tel: 4442 8877 / Fax: 4441 9002

Email: [email protected]

GHD Piling works - - - - - - - - 500mm 16.0m 188 Dec-06 Jan-07

47 The Pearl, Qatar - Bilal Pearl Suites VB-10 The Pear, Qatar

Ahmed Hassan Bilal Trading & Co.

Sanjay Khosla - General Manager

P.O.Box 7848, Doha Qatar

Tel: 4442 8877 / Fax: 4441 9002

Email: [email protected]

GHD Piling works - - - - - - - -

600mm

900mm

1200mm

4.5m-8.0m

11.5m

11m-16m

130

92

159

Nov-06 Dec-06

48 The Pearl Qatar - Parcel 13A & 13B The Pear, Qatar

Projacs International

Mr.Ayman S. Badr

Tel: 4442 0902 / Fax: 4442 0857

Email: [email protected]

Projacs Piling works - - - - - - - -500mm

1200mm- - Jul-06 Oct-06

49 The Pearl Qatar - Parcel 2A & 8A The Pear, Qatar

KEO International Consultants

Mr.Christopher Mark Davey - Resident Engineer

Tel: 4462 6400 / Fax: 4462 6500

Email: [email protected]

KEO International Consultants Piling works - - - - - - - -500mm

1200mm

16m

22m

203

185May-06 Jun-06

50 The Pearl Qatar - Parcel 1,2 & 9 The Pear, Qatar

United Development Company (UDC)

Mr. Abdulrahman K. Jowhari - General Manager

Tel: 4446 3400

Email: [email protected]

Dar Al Handasah Piling works - - - - - - - -

500mm

750mm

1000mm

1200mm

18m

12m

24m

28m

2,100

100

50

200

Jan-06 Jul-06

51 The Pearl Qatar - Parcel 6 The Pear, Qatar

Afrina Trading & Contracting Co.

Eng. Sadek Al Madani - General Manager

Tel: 4467 0613 / Fax: 4467 5897

Afrina Trading Piling works - - - - - - - -

500mm

1000mm

1200mm

18m

24m

28m

429

46

467

Jan-06 Jun-06

52

Power Supply to High Rise Building

Qatar General Electricity & Water

Corporation (Kahrammaa)

West Bay,

Doha, Qatar

Gulf Housing Construction Co. WLL

Tel: 4447 7000 / Fax: 4447 7555

Email: [email protected]

Gulf Contracting Co Piling works - - - - - - - -750mm

900mm

4m

20m

50

500Dec-05 Feb-06

53Mishal Appartment Tower at

H.E. Shk. Meshal Al Thani

West Bay,

Doha, Qatar

Arab Engineering Bureau

Mr. Samer Hudhud - Project Director

Tel: 4447 7969 / Fax: 4447 7868

Email: [email protected]

Arab Engineering Bureau Piling works - - - - - - - -600mm

900mm

10m

12m

150

175Dec-05 Feb-06

54Doha International Airport Terminal

Expansion - Package 3 Doha, Airport

Gulf Housing Construction Co. WLL

Mr. Andrew Ford - Construction Manager

Tel.: 4447 7000

Email: [email protected]

Bectel Piling works - - - - - - - - 600mm 6m 430 Nov-05 Feb-06

55 Residential Tower for Sheikha Hanadi West Bay,

Doha, Qatar

MZ&Partners

Youssef Hayak - Project Manager

Tel: 4431 3863 / Fax: 4436 3812

Email: [email protected]

MZ & Partners Piling works - - - - - - - - 750mm

900mm7m12m 170 Dec-05 Jan-06

56 Qasco Bar Mill Project Mesaieed, Qatar

Qasco - Vai Pomini S.r.l.- Italy

Mr. Attilio Sacchi - Project Director

Tel: +39 0331 741420

Email: [email protected]

Viapomini - Italy Piling works - - - - - - - - 600mm

750mm

20m

21m850 Sep-05 Dec-05

57 LNG Tanks ProjectRas Laffan,

Qatar

IHI

Mr. Toshihisa IshigakiIHI Piling works - - - - - - - - 1000mm 9.6m 1,158 May-05 Oct-05

58Amwal Tower Project

(3B+G+16 storeys)

West Bay,

Doha, Qatar

Mr. Arne Johansen - Sr. Project Maanger

Email: [email protected] Aecom

Excavation, shoring & piling

works 4,600 m2

Soldier piles

with I-Beams 275m 12m 8m 65,000 m3 5m 13m

600mm

900mm

6m

12m439 Jan-05 Aug-05

59Seed Al Misnad Tower Project

(2B+G+29 storeys)

West Bay,

Doha, Qatar

MZ&Partner

Mr. Youssef Hayek - Project Manager

Tel: 4436 3813

Email: [email protected]

MZ & PartnersShoring, dewatering,

excavation and piling works 5,000 m2

Contiguous

piles and

Soldier piles

with I-Beams

280m 12m 8m 40,000 m3 7m 8m

600mm

750mm

1000mm

1200mm

8m

12m

16m

20m

211 Apr-05 Jul-05

List of Piling Works Projects Completed 3/4

Page 25: Company profile[1]

Description of Work Plot

Area (m2)

Earth

Retention

System

Retaining

Wall

Length

Retaining

Wall Depth

Excavation

Depth

Volume of

Excavation

Ground Water

Depth Prior to

Dewatering

Ground Water

Depth after

Dewatering

Pile Dia

(mm)

Pile Depth

(m)

No. of

Piles

Sr.

No.Project Name Location Name & Address of the Client Consultant / Project Manager

Details of Project

Commencement

Date

Completion

Date

LIST OF PILING PROJECT COMPLETED INCLUDING PILING, EXCAVATION, SHORING & DEWATERING WORKS

60Umm Bab Tower Project

(2B+G+22 storeys)

West Bay,

Doha, Qatar

Mr. Stuart Allen - Manager

ProjectsP.O.Box 559, Doha Qatar

Tel.: 4421518

Cico ConsultantsShoring, dewatering,

excavation and piling works 7,600 m2

Soldier piles

with I-Beams 350m 12m 8m 4m 8m 8m

600mm

900mm

9m

18m230 Apr-05 Jul-05

61Residential Tower Project

(1B+G+45 storeys)

West Bay,

Doha, Qatar

Qatar Design Consortium

Mr. Partap Parelkar Project Manager

Tel: 4442 5269

QDCExcavation, shoring & piling

works 5,000 m2

Soldier piles

with I-Beams 300m 12m 8m 40,000 m3 4m 8m

600mm

750mm

1000mm

1200mm

8m

12m

20m

24m

250 Feb-05 Mar-05

62Office Tower Project

(2B+G+35 Storeys)

West Bay,

Doha, Qatar

United Consultants

Mr. Abdullah Darwesh - General Maanger

Tel: 4431 5312

United ConsultantsExcavation, shoring & piling

works 5,000 m2

Soldier piles

with I-Beams 280m 12m 8m 40,000 m3 6m 8m

750mm

1000mm

12m

25m193 Oct-04 Dec-04

63Abdullah Al Misnad Tower Project

(2B+G+44 Storeys)

West Bay,

Doha, Qatar

ECG Group

Mr. Salim M.Elhadi - Project Manager

Tel: 4435 7771

Mob: 5593 5612

Email: [email protected]

ECGExcavation, shoring & piling

works 5000 m2

Soldier piles

with I-Beams 310m 12m 8m 40,000 m3 3m 8m

750mm

1000mm

10m

22m300 Jul-04 Oct-04

64

Mr. Khalid Bin Naser Abdullah Al Misnad -

Residential Tower Project

(2B+G+30 Storeys)

West Bay,

Doha, Qatar

ITD

Mr. Louise Saleh - Project Director

Mob: 5581 5082

MZ & PartnersExcavation, shoring & piling

works 5,000 m2

Soldier piles

with I-Beams 280m 12m 8m 40,000 m3 4m 8m 750mm 10m 250 Jul-04 Sep-04

65Al Dana Tower Project

(2B+G+27 Storeys)

West Bay,

Doha, Qatar

ITD

Mr. Louise Saleh - Project Director

Mob: 5581 5082

MZ & PartnersExcavation, shoring & piling

works 8,500 m2

Soldier piles

with I-Beams 380m 12m 8m 68,000 m3 3m 8m

750mm

1000mm

16m

26m178 May-04 Jul-04

66 Propane & Butane TanksRas Laffan,

Qatar

CMS&A

Mr. Katsuki Ninomiya - Site Manager

Tel: 4473 5333

CMS&A Piling works - - - - - - - - 1000mm 9m 576 Nov-03 Feb-04

67Qatar National Library Project

Ministry of Agriculture & Municipal Affairs

Corniche, Doha,

Qatar

Contraco W.L.L

Mr.Mohsen Hamdon Maged - Project Manager

Tel: 4451 0399 / Fax: 4451 0788

Email: traco.com.qa

Dar Al Handsah /

ContracoPiling works - - - - - - - -

600mm

1200mm

14m

20m1,600 May-03 Nov-03

68 Crushed Stone Import Facility Mesaieed, Qatar Qatar Petroleum Grandi Lavori Fincosit Piling works - - - - - - - - 750mm 19m 220 Mar-03 Sep-03

List of Piling Works Projects Completed 4/4

Page 26: Company profile[1]

AMMICO COMPANY PROFILE  

7

List of Marine Works Projects Completed

Page 27: Company profile[1]

Sr.No:

Project Name Project Location Clients Name Description of WorkStarting

DateCompletion

DateLIST OF MARINE PROJECTS COMPLETED

1 Qatar Navigation ShipyardNew Port Doha,

Qatar

Milaha Logistics (Qatar Navigation)Mr. Md. A. Yasin Saleh - VPT: 4494 9789 │ F: 4410 2255

Dredging Works Under Floating Dock "Al Rufaa II" Sep-12 May-13

2 Banana Island - Holiday ResotBanana Island,

Qatar

Doha Marine CompanyMr. Ramon BayT: 4432 9099 │F: 4476 0096

Sheet Piling Works - temporary Jetty Pile Installation Feb-13 May-13

3Gas Sweetening Facilities (GSF) Project New Jetty marine works

Mesaieed, Qatar CCC & Teyseer JVMr. Oussama El Jarbi - Project Manager T: 4433 9555 │ F: 4433 942

Jetty Marine WorksJun-11 Nov-12

4 New Doha Port Project New Doha Port, QataMiddle East Dreading Co. (MEDCO)Mr. Robby Van den BrandenTel: 5575 1263 / Fax: 4464 7492

Fabrication and Installation of Tidal Beacom Jun-12 Aug-12

5EPIC of Berths & Port Infrastructure for Ras Laffan Port Expansion Project

Ras Laffan, QatarCCC & Teyseer JVMr. Imad Khaled - Project DirectorTel: 4410 2333 / Fax: 4410 2429

Silt Removal Works at Southern Container Berth Jun-12 Sep-12

6Piling Works to Fixed Walkway @ Al Jassasia

Al Shamal, QatarMilaha Logistics (Qatar Navigation)Mr. Md. Raihan Bin OmarTel: 4477 1690 / Fax: 4477 1687

Supply & Installation of Steel PilesMay-12 Jul-12

7 Banana Island Project Near NDIA, QatarUrbacon International Co.Mr. Mowafaq KharbatTel: 4429 2220 / Fax: 4429 2244

Sheet Piling 2 Loading Ramp @ Banana Island Apr-12 May-12

8Construction of Temporary Berth at Marsarabia

The Pearl, QatarMr.Omar Alfardan -Director of MarsarabiaTel: 4420 8898 / Fax: 4420 8897

Complete construction of Temporary Berth, including installation of marine piles

Jun-10 Oct-10

9Ras Laffan Port Expansion Project Main Contractor : Boskalis Westminster

Ras Laffan, Qatar

BoskalisMr.Oscor - Site ManagerTel: 5816646

Construction of Major Breakwater for Expansion of RLIC Port by filling 350,000 cu m of fill material, including placement of rock armour for slope protection.

Feb-06 Apr-06

AMMICO CONTRACTING CO. W.L.LLIST OF MARINE WORKS PROJECTS COMPLETED

List of Marine Works Projects Completed 1/2

Page 28: Company profile[1]

Sr.No:

Project Name Project Location Clients Name Description of WorkStarting

DateCompletion

DateLIST OF MARINE PROJECTS COMPLETED

10

Jetty & Light House Project at Corniche for Civil Engineering Department,Ministry of Municipal Affairs & Agriculture

West Bay, Qatar

Ministry of Municipal Affairs & Agriculture, Doha

Installation of piles 500mm & 700mm for Jetty & Light House Project at Corniche (Piling Sub-Contractor to AMCON)

Nov-02 Feb-03

11 Temporary Jetty for Halul Project QatarArchiredon Construction Co.S.A Mr. Khaled El Sayed - Poject ManagerTel: 4467 7706 / Fax: 4467 1886

Installation of piles for Temporary Tetty for Halul Island. May-02 Nov-02

List of Marine Works Projects Completed 2/2

Page 29: Company profile[1]

AMMICO COMPANY PROFILE  

8

List of Earthworks Projects Completed

Page 30: Company profile[1]

No: Project Name Location (City &Country) Type of Facility Contract Value (QR) Period (mm/yy) Owner Name & Repres. Contact Telephone # & Fax #

1 New Solar Power Plant Foundation - SitePreparations and Chain link Fencing Works Ras Laffan, Qatar

Site Stripping, Backfill, RockCrushing and Installation of ChainLink Fencing Works

2,101,800.00 May-2014 to July-2014 Qatar Solar TechnologiesMr.Khalid Al Hajri - CEO Tel: 4454 6700 / Fax:4454 6701

2 Temporary Dewatering Works - Hotel BufferLagoon at Doha Festival City Duhail, Qatar Excavation and disposal works 155,922.00 July-2014 to July-2014 Mace International - Mr. Innes Alexander -

Project Director Tel: 44917070 Fax: 44917075

3Water Desalination Plant for Qatar Electricityand Water Company Q.S.C. Ras Abu FontasA2

Doha, Qatar Excavation, Backfill, Rock Armorinstallation and Disposal works. 629,884.00 Dec-2013 to Nov-2014

Gulf Contracting Co. W.L.L.Mr.Grahame McCaig -General Manager

P.O.Box: 3886 - Tel 4499 4499Fax: 4499 4500

4 Qstec Polysilicon Project - Phase 1 Ras Laffan, Qatar Excavation and Earthworks 22,000,000.00 Mar-2012 to April-2014 Punj Lloyd Limited, Mr. Sarab Pal Singh -Project Manager,

Tel: 44407 4555 Fax: 444074500

5 Qatar New Port Project Mesaieed, Qatar Rock Excavation using surfacedrum cutter 582,629.00 May-2013 to Nov-2013

China Harbour Engineering Co.Mr. Hui Chen - Dty. Commercial Mgr.T: 4406 6456 │M: 6604 3888

T: 4406 6456 │M: 6604 3888

6 LRT Lusail - Phase 2C1A Viaduct and Depot Lusail, Qatar Excavation and Earthworks 6,545,750.00 Jul-2012 to Oct-2013QDVC - Mr. Philippe Tavernier- ProjectManagerT: 4453 8400 │ F: 4483 7479

T: 4453 8400 │ F: 4483 7479

7 Dukhan Highway (Central Contract) Project Dukhan, Qatar Excavation and disposal works 330,446.80 May-2013 - Jun-2013

Consolidated Contractors Group S.A.L.Mr. Khalid Al Naas - Project ControlsMgr. T: 4423 7444 | F: 4423 7488

8 Shell GTL ProjectPermanent Cabin for Waste Transfer Area Ras Laffan, Qatar

Asphalt and concrete pavingdemolition and laying,excavation, backfill andconstruction of concrete stormwater drain

165,483.60 Apr-2013 - Jun-2013Madina GroupMr. P.S.Wijeratne - Project Manager, T: +974 4460 0818 | M: +974

6622 9429

9 Shell GTL Project8684 Tank Remedial Works Ras Laffan, Qatar

Excavation , Backfill, HDPE andGeoTextile Installation and Wetsand mix laying works

956,216.05 Nov 2012 - Feb-2013

Madina GroupMr. P.S.WijeratneProject Manager

T: +974 4460 0818 | M: +9746622 9429

10 National Museum of Qatar Doha, Qatar Excavation and BackfillingWorks 1,825,196.00 Sep 2012 -May 2013

Hyundai Engineering & ConstructionMr. H.J. (Ho Jun) Lee- Deputy Procurement Manager

T: +974 4427 9390

11 GASAL O2/N2/H2 Pipeline Backbone Project Ras Laffan, Qatar Excavation, Rock Crushing andBack Filling works. 11,382,077.91 Jul -2012 - Apr -2014 Qcon - Mr. R. Krishna Moorthy -

Project Manager T: +974 5550 5734

LIST OF EXCAVATION WORKS COMPLETED BY AMMICO

PROJECT INFORMATION CONTRACT INFORMATION OWNER INFORMATION

Page 1 of 4

Page 31: Company profile[1]

No: Project Name Location (City &Country) Type of Facility Contract Value (QR) Period (mm/yy) Owner Name & Repres. Contact Telephone # & Fax #

LIST OF EXCAVATION WORKS COMPLETED BY AMMICO

PROJECT INFORMATION CONTRACT INFORMATION OWNER INFORMATION

12 LRT Lusail - Phase 2C1A Viaduct and DepotEarthworks Lusail, Qatar Excavation and Earthworks 6,545,750.00 Jul-2012 to May-2013 QDVC - Mr. Philippe Tavernier - Project

Manager Tel- 4453 8400 Fax: 4483 7479

13 Shell GTL ProjectHOT Slope Tank Repair Works Ras Laffan, Qatar

Wet sand mix removal andlaying, aluminized steel shapefabrication and fixing and peagravel laying works

262,073.13 Mar-2013 - May-2013CB&I Eastern AnstaltMr. Wasim Iqbal - Project In-charge M: 6659 9200

14 Barzan Onshore Gas Project (CR) Ras Laffan Crushing Services 5,500,000.00 Mar-2012 to May-2012 Descon Engineering Qatar - Mr. Talha

Tariq - Manager Commercial

Tel: 4456 9127Fax: 4456 9126

15Lusail Development LRT - ESE Phase 2B -Lusail Lusail, Qatar Geotextile Reinforced Backfilling

ESE Phase B-Lusail. 4,984,200.00 Oct-2009 to Aug-2011 QDVC (LRT) Mr. Philip Tavernier - LRTProject Manager Tel :44538400,Fax :44677278

16Lusail Development LRT - ESE Phase 2A-Lusail Lusail, Qatar Excavation & Backfilling works 47,769,119.10 Sep-2010 to Nov-2011 QDVC (LRT) Mr. Philip Tavernier - LRT

Project Manager Tel :44538400,Fax :44677278

17 Early works Package 1 Polysilicon Project Ras Laffan, Qatar Site Preparation works 17,500,000.00 Sep-2011 to Dec-2011 Qatar Solar Technologies - Mr.Khalid AlHajri - CEO Tel: 44546700 Fax:44546701

18 Doha Festival City Project - 220 - IKEA BoxBulk Excavation works

Shamal Road Duhail,Qatar Bulk Excavation works 6,511,172.00 Sep-2011 to Dec-2011 Mace International - Mr. Innes Alexander -

Project Director Tel: 44917070 Fax: 44917075

19

EPIC of New Access Road and InternalRoads, RLIC Interface Roads, New MainEnterance & Guardhouses at Oryx GTL RasLaffan

Ras Laffan, Qatar

Construction of pipe sleepers, pipesupports, culverts, drain pits,construction of AOC manholes,COC manholes, firewater pits, RCbund walls

4,105,400.00 Dec-2011 to Feb-2011Qatar Engineering & ConstructionCo.W.L.L.( Qcon), Mr. Mazen AbuNaba'a - Managing Directo

Tel 4458 7200, Fax 4458 7201

20Shell Pearl GTL Project - Civil Works forOnsite and Offsite Tanks Ras Laffan, Qatar

Construction of pipe sleepers, pipesupports, culverts, drain pits,construction of AOC manholes,COC manholes, firewater pits, RCbund walls

79,591,305.00 Sep-2007 to Jan-2011 CB&I - Pearl GTL - Mr. Tony . Clegg -Sub Contracts Administrator Mob. +974 5842663

21Shell Pearl GTL Project - Earthworks forOnsite and Offsite Tanks Ras Laffan, Qatar

Construction of earthen bundwalls, installation ofgeomembranes (HDPE liner &LGXPRO), underground services(AOC/COC/Firewater lines), layingof cement sand and wet sandlining on bund walls

139,000,000.00 Sep-2007 to Feb-2011 CB&I - Pearl GTL - Mr. Tony . Clegg -Sub Contracts Administrator Mob. +974 5842663

Page 2 of 4

Page 32: Company profile[1]

No: Project Name Location (City &Country) Type of Facility Contract Value (QR) Period (mm/yy) Owner Name & Repres. Contact Telephone # & Fax #

LIST OF EXCAVATION WORKS COMPLETED BY AMMICO

PROJECT INFORMATION CONTRACT INFORMATION OWNER INFORMATION

22 TTMTA Inaguration Event Project Ras Laffan, QatarBulk Excavation and Civil Worksfor event including grading androck wall

2,500,000.00 Feb-2010 to Jan-2011 WRG. UK - Mr.Crish - 33146020 Mob-33146020

23 Nakhilat Shipyard Project Ras Laffan, QatarPlacement of subbase type Amaterial for laydown areasincluding sheds for ship repairs

4,390,000.00 Feb-2010 to Dec-2010

Gulf Contracting Co. WLLP.O.Box:3886, Doha Qatar Tel:4477000 Fax: 4477555 Email:[email protected]

Tel: 4477000 Fax: 4477555

24 Common Cooling Water Project - Phase IIClient: QP; EPC Contractor: DODSAL Ras Laffan, Qatar

Site preparation for laydown area,including rock lining for sabkhatreatment; Excavation of 5300sleepers, Excavation of dischargechannel to sea (Approx. 180,000cu. m.) Excavations for all relatedunderground utilities.

38,500,000.00 Sep-2006 to Mar-2008 Mr. Arun Dupker Resident ConstructionManager, Mob : 55542497

25RasGas Storage TankEPC Contractor : CMS&AMain Contractor : Vinci Contractor

Ras Laffan, Qatar Site preparation and earthworksfor Tank No. 6, Mesaieed, Qatar. 1,250,000.00 Mar-2007 to July-2007 Venci Construction - Mr. Alexander

Buzani Project Manager Tel : +316-206-91813

26 Ras Laffan Port Expansion ProjectMain Contractor : Boskalis Westminster Ras Laffan, Qatar

Construction of MajorBreakwater for Expansion ofRLIC Port by filling 350,000 cu mof fill material. Includingplacement of rock armour forslope protection.

3,550,000.00 Feb-2006 to Apr-2006 Mr.Oscor Site Manager , Boskalis Tel : 55816646

27 Dolphin Project , Ras Laffan Main Contractor : Scilsaldo, Italy Ras Laffan, Qatar

Construction of temporaryaccess road for Onshore PipeProject, Ras Laffan.

1,000,000.00 Feb-2006 to Mar-2006 Mr. Luciano Giulietti Site Manager ,Scilsaldo Tel : 44748661

28 Dolphin Project , Ras Laffan Main Contractor : Saipam Ras Laffan, Qatar

Construction of temporaryaccess road for Onshore PipeProject, Ras Laffan

1,500,000.00 Jan-2006 to Mar-2006 Mr. Conner Site Manager , Saipam Tel : 971-50-2647581

29 Ras Gas, Ras LaffanMain Contractor : Spacemaker Ras Laffan, Qatar

Earthworks for TemporaryFacilities,Tank Train 6 & 7, Ras Laffan.Site preparation of laydown area850,000 sq m, includingbackfilling, levelling, grading andcompaction.

6,500,000.00 Jan-2006 to May-2006 Mr. Krishnan Business DevelopmentManager ,Spacemaker Tel : 55788211

30Dolphin Project , Process Area Ras LaffanEPC Contractor : JGC Middle EastSub Contract to Gama Qatar

Ras Laffan, QatarEarthworks for construction ofmaterial handling Laydown Area,Ras Laffan.

14,000,000.00 Dec-2005 to Aug-2006 Mr. Yamasaki Sr. Civil Engineer ,JGC Tel : 5856578

Page 3 of 4

Page 33: Company profile[1]

No: Project Name Location (City &Country) Type of Facility Contract Value (QR) Period (mm/yy) Owner Name & Repres. Contact Telephone # & Fax #

LIST OF EXCAVATION WORKS COMPLETED BY AMMICO

PROJECT INFORMATION CONTRACT INFORMATION OWNER INFORMATION

31Qatar Electricity & Water CorporationEPC Contractor : CMS&AMain Contractor : Siemens AG

Ras Laffan, Qatar Earthfilling works for Ras Laffan"B" CCPP Project, Ras Laffan. 4,600,000.00 Jun-2006 to Mar-2007 Mr. Chang ,CMS&A Tel : 55845987

32Common Cooling Sea Water System Phase IIat Ras LaffanMain Contractor : Afcons

Ras Laffan, Qatar Earthworks for Cofferdams ofPump House 1 & 3, Ras Laffan. 6,000,000.00 May-2005 to Mar-2006 Mr. Sheisodia Tel: 5989253

33Qatar Gas II - Tank Foundations at Ras Laffan Contractor : CMS&AMain Contractor : Vinci Contractor

Ras Laffan, Qatar

Site preparation & soilimprovement work by dynamiccompaction for Tank No.4 & 5,Ras Laffan.

3,750,000.00 Mar-2005 to Sep-2006 Mr. Alexander Buzani Tel : +316-206-91813

34 Qatar Gas II - Tank Foundations at Ras LaffanMain Contractor : IHI Ras Laffan, Qatar Site preparation works for QG II -

Qatar Gas, Ras Laffan. 32,000,000.00 Dec-2004 to Jul-2006 Mr. Toshihisa Ishigaki Project Manager IHI Tel : 4735564

35 Ras Gas Onshore Expansion ProjectRas Laffan, Sub Contract to CMS&A Ras Laffan, Qatar Site preparation & earthworks for

Train - 5, Ras Laffan. 4,000,000.00 Jul-2004 to Mar-2005 Mr. Chang CMS&A Tel : 5845987

36 Dolphin Project, Ras Laffan EPC Contractor : JGC Middle East Ras Laffan, Qatar

Site preparation works -excavation and earthfilling, RasLaffan.

10,500,000.00 Jun-2004 to Feb-2005 Mr. Yamasaki Sr. Civil Engineer ,JGC Tel : 5856578

37 Sub-Contractors - National Contracting Co.w Doha QatarExcavation & earthworks for32kV & 66kV ElectricTransmission Line.

4,000,000.00 Mar-2003 to Feb-2004 Qatar General Electricity & WaterCorporation -

38Qatar PetroleumEPIC Contractor : Sumsung Corp.Sub-Contractors - Gulf Housing & Construction

Mesaieed, QatarExcavation and earthfilling worksfor 2 numbers of LPG StorageTanks, Mesaieed.

1,600,000.00 Aug-2002 to Sep-2002 Mr. John Kennedy ,GH&C Tel : 4994499,4994544

39 Common Cooling Water Project Ras Laffan,Sub Contract to CCIC Ras Laffan, Qatar Rock excavation, Ras Laffan. 4,600,000.00 Jul-2002 to Mar-2003 Consolidated Contractors Co. -

40 Ras Gas /CMS&A Ras Laffan,Sub Contract to Gulf Housing Ras Laffan, Qatar

Site preparation works for RGXProject-Train 3, & 4 Ras Gas ,Ras Laffan.

4,600,000.00 Aug-2001 to Apr-2003 Mr. Chang ,CMS&A Tel : 5845987

Page 4 of 4

Page 34: Company profile[1]

AMMICO COMPANY PROFILE  

9

Resumes of Key Personnel

Page 35: Company profile[1]

JJAAMMAALL NNAASSIIRR

Page 1 of 1

1983 – 1984 After completing his education at M.I.T., worked with (a)

Steveson & Associates / Vibration Engineering Consultants and (b) LeMessurier Associates. Both these firms were leading structural engineering consultants in U.S.A. The work involved analysis and design of structures.

Designation : Chief Executive Officer

Date of Birth : September 26, 1962

Nationality : Pakistani

Education : Massachusetts Institute of Technology, USA.

B.Sc. Civil Engineering, 1983

M.Sc. Civil Engineering, 1983

Awards : Richard Lee Russel Award given to the top undergraduate student entering graduate study at M.I.T. Civil Engineering Department, 1982.

Membership to Chi Epsilon, Civil Engineering Honour Society of USA.

Aga Khan Foundation International Scholarship for Graduate Study, 1982.

Dean A. Horn Award for Undergraduate Study in Marine Research, 1982.

Massachusetts Construction Advancement Program Scholarship, 1981.

PRACTICAL EXPERIENCE 2001 – Present Ammico Contracting Co. W.L.L. Doha Year 2000 Ammico Foundations Dubai 1984 – 1999 Ammico Constructors Pakistan

Established Ammico in Qatar in January 2001 and as C.E.O. played his vital role in turning the company into a leading geotechnical and marine contracting company in the region. The company presently employs more than 1000 persons and its turnover in Year 2008 and Year 2009 exceeded US$150 million. As Managing Director of the company was responsible for execution of various piling and shoring projects in Dubai. Returned to Pakistan in 1984 from USA to join Ammico Constructors (Pvt) Ltd as Executive Director and helped the company become one of the leading infrastructure and piling contractors in the country. He was directly responsible for construction of a number of canal and river bridges on flowing water, underpasses, interchanges and piling works for all types of bridges, buildings and industrial plants.

Page 36: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 1 of 9

Designation : Deputy General Manager

Date of Birth : 25 December, 1971

Nationality : Pakistani

Education : B.Sc. Civil Engineering, UET, Lahore – Pakistan, 1994

Years of experience : Nineteen

With Ammico since : March 1997

SUMMARY OF EXPERIENCE

: Mr. Muzaffar Iqbal Anjum is a highly a capable manager and has nineteen years of experience in the field of geotechnical and marine works. He has personally managed the execution and completion of a number of large and medium scale projects involving installation of diaphragm wall, secant wall, ground anchor, contiguous wall, cast in-situ piling, marine piling, soil stabilization, earthworks, dewatering, jetty construction and marine maintenance projects. Since March 2008, as a Deputy General Manager of the company, he is responsible for all the operations of the geotechnical division of Ammico as well as looking after marine projects.

PRACTICAL EXPERIENCE Jan-2014 to Present Jan-2013 to Present July 2013 – Dec 2013 Jun 2013 – Dec 2013

AMMICO CONTRACTING CO. W.L.L., DOHAMr. Muzaffar Iqbal Anjum, in the capacity of Deputy General Manager, is responsible for planning and execution of all works at site. Qatar Integrated Railway Project – Major Station –Musheireb Scope of work for the project included:

- Installation of diaphragm wall - Installation of ground anchors

Qatar Integrated Railway project – Metro 1 – Green Line Underground Scope of work for the project included:

‐ Installation of Diaphragm Wall Workas ‐ Installation of Soil Nailing and Shotcrete Work ‐ Installation of Anchoring Works ‐ Piling works

Construction of Lusail Tower, Com-11, Lusail, Qatar. Managing the project in the capacity of Deputy General Manager. Scope of work for the project included; installation of soldier piles as shoring system for a length of 70lm and 351 nos. working piles with diameters of 600mm to 1200mm. Re-work Package for Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) Managing the project in the capacity of Deputy General Manager. Scope of work for the project includes design and installation of removable ground anchors for a previously installed diaphragm

Page 37: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 2 of 9

Feb 2013 – Jun 2013 Jan 2013 – Dec Jan 2013 – Dec 2013 Sep 2012 – Jan 2013 Jan 2012 – Present Nov 2012 – Mar 2013 July 2012 – Jan 2013 Jun 2012 – Jan 2013

wall 550lm in length. T.J Pearl Mansion, Isola Dana, The Pearl Qatar. Managing the project in the capacity of Deputy General Manager. Scope of work for the project includes 80,500 m3 excavation, dewatering and installation of 640mm thick and 11m deep cantilever diaphragm for a length of 785lm. It also includes 659 nos. of working piles with 400-600mm diameter and 4-10m depth. Doha Oasis Mixed Use Development, Musheireb, Doha. Managing the project in the capacity of Deputy General Manager. Scope of work for the project includes 912,150 m3 excavation, installation of 340 lm shoring system consisting of contiguous piles of diameter 750mm & length 19 meter at a centre to centre distance of 1.4 meters, shotcrete, 800 nos. of working piles with 800mm diameter & 11m length and 40 nos. of working piles with 1000mm diameter & 17m length. Lookout Restaurant & SPA, Banana Island, Doha, Qatar Managing the project in the capacity of Deputy General Manager. Scope of work for the project included 80m sheet pile for SPA area. Installation of 62 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles. Installation of 28 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Lookout area. Installation of 143 nos. of 16 - 19m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Over water villa area. Qatar Navigation Shipyard, Messaieed, Qatar Managing the project in the capacity of Deputy General Manager. Scope of work for the project involved dredging and silt removal works under floating dock "Al Rufaa II" at Mesaieed Industrial City (MIC). Link Road to Pearl Lusail Expressway Package 1, Doha, Qatar Managing the project in the capacity of Deputy General Manager. Scope of work for the project involved secant piling works, excavation disposal and backfilling for 49 no. of shafts. Residential Villa at Pearl Qatar for Mr. Omar Alfardan Managing the project in the capacity of Deputy General Manager. Scope of work for the project involved installation of 203 nos. piles of diameter 800mm and length 11m and 56 piles of 1000mm diameter having length 12m. Al-Wahab Tower, For Ezdan Real Estate, Al Dafna, Doha, Qatar Managing the project in the capacity of Deputy General Manager. Scope of work for the project involved installation king post and timber beam shoring works for 2 storey basement. Le Boulevard Project @ Al Saad, Doha, Qatar Managing the project in the capacity of Deputy General Manager. Scope of work for the project involved the installation of 277lm concrete diaphragm wall 22.5m depth with a 17.5m deep excavation for four basement structure. Gas Sweetening Facilities (GSF) Project, Mesaieed Industrial

Page 38: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 3 of 9

Aug 2011 – Nov 2012 Jun 2011 – Mar 2013 Sep 2011 – Jun 2012 Jul 2011 – Nov 2011

Dec 2010 – Jun 2011 July 2010 – Aug 2011 Aug 2010 – Oct 2010 June 2010 – Oct 2010

City.This project is situated in live plant facilities of Qatar Petroleum in Mesaieed, Qatar. The scope of work for this project included procurement, fabrication and installation of 43 no., 762mm diameter steel tubular piles with 25mm thickness. The fabrication and installation of precast pile caps, beams and slabs as well as cast in situ concrete in various stages. Land reclamation and revetment works and construction of culvert is also included in the project scope. Mr. Muzaffar Anjum was personally involved in all the physical activities of the project. He handled this project with meticulous planning skills, with concise communication among project team members and an active approach towards decision making and negotiations with the client and subcontractors.

Doha Land Phase-2 & Phase-3 Project, Doha, Qatar The scope of work included the installation of 625lm concrete diaphragm wall to 18m & 23m depth, removable anchors, excavation to 13.7m & 17.2m below existing ground level for the 4 & 5 basements respectively, dewatering and installation of 900mm, installation of 1500mm & 1800mm diameter concrete piles. The project had a total of 3500 number piles. National Library, Education City, Rayyan, Qatar. The scope of works included the installation of 438 no. of 500mm – 1200mm diameter concrete piles. Qatar Faculty of Islamic Studies, Education City, Rayyan, Qatar. The scope of work for this project included the installation of 698 nos concrete piles with 500mm – 1500mm diameter piles. Earthworks, Shoring, Anchors & Soil Nailing Works at Sheraton Park Project, West Bay, Doha. The scope of work for this project included; excavation of approximately 1,100,000 m3, backfilling of approximately 250,000 m3, installation of 605 lm concrete secant pile wall, 241 Lm of concrete contiguous pile wall, 380 no. anchors and installation of 1700 no. soil nails. Jetty Boil-Off Gas Recovery Project, Ras Laffan Industrial City, Ras Laffan, Qatar The scope of work for this project included the installation of 1036 concrete piles of 600mm diameter and 8m long below cut off level. Lusail Development Sewage Treatment Works The scope of work for this project included installation of concrete secant piles for shafts, excavation & De-watering for shafts. Construction of Temporary Berth at Marsa Arabia Project, The Pearl Qatar The scope of work for this project was the installation of steel offshore piles 900mm dia and the design & construction of

Page 39: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 4 of 9

Feb 2010 – Oct 2010 July 2010 – Sep 2010 Apr 2009 – Jan 2010 Sep 2007 – June 2010 Mar 2008 – May 2010 Jun 2009 – Feb 2010 Jul 2009 – Feb 2010 Jul 2008 – Jul 2009 May 2007 – Nov 2008

temporary berth at Marsarabia, The Pearl Qatar, including associated concrete works, marine grade painting and miscellaneous metal works and accessories. Ras Laffan Port Expansion Project, Ras Laffan, Qatar The scope of work for this project was the installation of concrete piles dia 900mm and depth up to 27m for coast guard, liquid petroleum berth and container berth. 12 New Departure Gates Project at Doha International Airport The scope of work for this project included installation of 600mm dia bored piles 101 number and 750mm dia concrete bored piles 39 number. Lusail Transit System / CP 13 – Phase ESE for QDVC The scope of works for this project included reinforced earth wall using geotextile membrane upto 7m depth, excavation upto 14m depth below ground level. Shell GTL Project – CB&I Condensate Tanks Foundations Phase II Common off plot project at Ras Laffan The scope of work for this project included site preparation, earthworks for thirty eight tank forms of world’s largest GTL plant project. Shell GTL Project –CB&I Civil works at Ras Laffan The scope of work for this project included on-site and off-site civil works. Perlita Gardens - The Pearl Qatar The scope of work for this project included installation of 500mm dia concrete piles of 14m depth. Al Quds Tower Project, West Bay, Doha (5B + G + 100) The scope of work for this project included installation of 670m concrete diaphragm wall to 30m depth, removable ground anchor, excavation to 24m below existing ground level for the five level basement car park, dewatering and installation of 1200mm and 1500mm dia concrete piles for the one hundred storey tower. Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) The scope of work for this project included installation of 550 meter long concrete diaphragm wall to 22m depth, removable ground anchor, excavation up to 20m below existing ground level for five level basement car park, dewatering and installation of 1200mm and 1500mm dia concrete piles for the hundred and five storey tower. Mr. Muzaffar Iqbal Anjum, in the capacity of Deputy General Manager, was responsible for planning and execution of all works at the site. This challenging project was executed in an exemplary manner and completed within time and budget. Doha Convention Center & Tower Project, West Bay, Doha (3B + G + 114) The scope of work for this project (which covers an area of 130,000 m2 in the West Bay area of Doha) included the following: Installation of 1600 meter concrete diaphragm wall up to 17m depth, excavation up to 21m under the tower footprint,

Page 40: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 5 of 9

Nov 2008 – Jul 2009 Oct 2008 – Mar 2009 May 2008 – Nov 2008 Apr 2008 – Sep 2008 Nov 2007 – Mar 2008 Nov 2007 – Feb 2008 Sep 2007 – Feb 2008 Sep 2007 – Nov 2007

removable ground anchor,excavation for the triple and double level basement car parks, dewatering, installation of 1500mm dia concrete piles for the one hundred and fourteen storey tower and 900mm concrete piles for the convention center. Mr. Muzaffar Iqbal Anjum, in the capacity of Deputy General Manager, was responsible for planning and execution of all work at the site. This landmark project (the design height for the tower is 570m making it one of the tallest under construction buildings in the world) was executed in an exemplary manner and completed within time and budget. Headquarters for The Energy City Qatar, Lusail (2B+G+M+2) The scope of work for this project included installation of a 561m concrete diaphragm wall to 16m depth, excavation to 11m below existing ground level for the three level basement car park, dewatering and installation of 600mm, 900mm & 1200mm dia concrete piles for the building structure. The Pearl, Qatar, VB-09 at Viva Bahriya, for Hamad Al Mana This project involved installation of 600mm, 900mm and 1200mm dia concrete piles for the tower structure. Cultural Village Commercial Plaza Car Park project at West Bay, Doha, Qatar. The scope of works for this project included installation of 173m of concrete diaphragm wall and 600mm, 900mm and 1200mm dia piles. Alumina & Coke Silos and Liquid Pitch Tanks, Qatalum Project, Mesaieed – SNC Lavlin International This project involved installation of (a) 844 concrete piles of 1000mm dia and 25m depth and (b) 402 concrete piles of 1000mm dia and 23m depth (c) 400 concrete piles of 750mm dia and 22m depth. Woqod Tower Project, West Bay, Doha (4B + G + M + 30) The scope of work for this project included installation of 238m concrete diaphragm wall to 24m depth, excavation up to 21m below existing ground level for the four level basement car park, dewatering and installation of 900mm and 1200mm dia concrete piles for the thirty storey tower. Mr. Muzaffar Iqbal Anjum as Projects Manager has executed completely and successfully following projects: The Pearl, Qatar, VB 11 & 17 – Viva Bahriya, for Dorrat Al Doha This project involved installation of 600mm, 900mm and 1200mm dia concrete piles with 8m to 38m depth. The Pearl, Qatar, VB 6 & 7 – Viva Bahriya for First Qatar The project involved installation of 600mm, 900mm and 1200mm dia concrete piles with 10m to 25m depth. The Pearl, Qatar, VB 3,4 & 5 – Viva Bahriya for Dorrat Al Doha This project involved installation of 600mm, 900mm and 1200mm dia concrete piles with 8m to 38m depth.

Page 41: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 6 of 9

Sep 2007 – Jun 2008 Jul 2007 – Nov 2007 Dec 2006 – Jul 2007 Dec 2006 – Jan 2007 Dec 2006 – Jan 2007 Oct 2006 – Jun 2007 Nov 2006 - Dec 2006 Oct 2006 – Mar 2007 Jul 2006 – Oct 2006 Jul 2006 – Oct 2006 May 2006 – Jun 2006 May 2006 – Jun 2006

Lusail Development Marina District Car Park project The scope of work for this project included excavation and installation of 600mm dia concrete piles of 11m depth. 2000MW CCPP Project at Mesaieed “A” for Iberdrolla Engg The scope of work for this project included (a) installation of 545 nos 600mm and 415 nos 1000mm dia concrete piles of 22m depth for the main plant (b) installation of 135 m of concrete diaphragm of 19.5m depth for the pump house (c) excavation to 15.5m depth for the pump house (c) construction of the pump house structure. Al Shamal Beach Villa Project for Private Engineering Office This project involved installation of 276 nos 750mm dia concrete piles of 24m depth. Silos for Qatofin Project at Mesaieed for Vos Logistics This project involved installation of 750mm dia concrete piles of 24m depth. The Pearl, Qatar, Parcel LPW 10 & 11- Bilal Pearl Suites project for M/s. Ahmed Hassan Bilal This project involved installation of 500mm and 1200mm dia concrete piles with 16m and 22m depth respectively. The Gate Development Project, West Bay, Doha (3B+G+17) The scope of work for this project included installation of 700m concrete diaphragm wall of 20m depth, excavation to 13m below existing ground level for three level basement car park, dewatering and installation of 900mm and 1200mm dia concrete piles. The Pearl, Qatar, Parcel VB 10 project at Viva Baharia, Bilal Pearl Suites This project involved installation of 600mm, 900mm and 1200mm dia concrete piles of 4.5m, 16m and 22mm depth respectively. Qatafin LLDPE Project at Mesaieed for M/s. Snamprogetti, Italy This project involved installation of 207 nos of 750mm dia concrete piles with 24m depth. The Pearl, Qatar, Parcel 7A project at Porto Arabia for Al Darwish United Real Estate & Investment Co. W.L.L. This project involved installation of 500mm and 1200mm dia concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 13A & 13B projects at Porto Arabia for General Retirement and Pension Authority This project involved installation of 500mm and 1200mm dia concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 2A project at Porto Arabia for M/s. Ali Alfardan This project involved installation of 500mm and 1200mm dia concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 8A project at Porto Arabia for M.s, Ali Alfardan and M/s. Jamil Mattar This project involved installation of 500mm and 1200mm dia

Page 42: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 7 of 9

Jan 2006 – Dec 2006 Jan 2006 – Jun 2006 Dec 2005 – Feb 2006 Dec 2005 – Feb 2006 Nov 2005 – Feb 2006 Dec 2005 – Jan 2006 Sep 2005 – Dec 2005 Apr 2005 – Jul 2005 May 2005 – Oct 2005 Apr 2005 – Jul 2005

concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 1, 2, 3, 4, 5, 10C, 14 and 18 projects for United Development Co. The scope of work for this project included installation of 500mm, 600mm, 900mm and 1200mm dia concrete piles with depth between 12 to 28m for a large number of high rise towers and low rise structures at The Pearl Qatar. The Pearl, Qatar, Parcel 6 project at Porto Arabia for M/s. Sabban Property Investments This project involved installation of concrete piles 500mm, 1000mm and 1200mm with depths of 18m, 24m and 28m respectively. Power Supply to High Rise Building project at West Bay for Gulf Housing & Construction The scope of works for this project included piling works for installation of 750mm and 900mm dia concrete piles with depth of 14m below the cut-off level of piles for Qatar General Electricity & Water Corporation (Kahramaa). Dukhan Apartment Tower (B + G + 32) project at West Bay for H.E. Sheikh Meshal Al Thani This project involved installation of 600mm and 900mm dia concrete piles with depth of 10m and 12m respectively. Doha International Airport Terminal Expansion – Package 3 project for Gulf Housing & Construction Co. W.L.L. This project involved installation of 600mm dia concrete piles at the New Doha International Airport (NDIA) Project. Residential Tower project for Sheikha Hanadi at West Bay The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 170 piles for the tower structure. QASCO Bar Mill Project at Mesaieed for VIAPOMINI This project involved installation of 512 nos concrete piles of 600mm dia and 20m depth and 131 nos piles of 750mm dia with 20m depth. Office Tower (2B +G + 29) project at West Bay for M/s. Saeed Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 600mm, 750mm, 1000mm and 1200mm dia concrete piles. LNG Tanks Project at Qatar Gas II, Ras Laffan for IHI This project involved installation of 1158 nos concrete piles of 1000mm dia for three number LNG tanks for Qatar Gas II Project. Umm Bab Residential Tower (2B + G + 31) project at West Bay for Qatar Islamic Bank The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 600mm and 900mm dia concrete piles for the tower structure. Amwal Commercial Tower (3B + G+ 22) project at West Bay The scope of work for this project included shoring, excavation

Page 43: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 8 of 9

Jan 2005 – Aug 2005 Feb 2005 – Mar 2005 Oct 2004 – Dec 2004 Jul 2004 – Oct 2004 Jul 2004 – Sep 2004 Jun 2004 – Aug 2004 May 2004 – Jun 2004 May 2004 – Jul 2004 Nov 2003 – Mar 2004 May 2003 – Nov 2003 May 2003 – Nov 2003

and dewatering for the three level car park and installation of 600mm and 900mm dia concrete piles. Residential Tower (B1 + G + 45 + 3PH) project at West Bay for H.E. Shk. Khalid Ahmed Al Misnad The scope of work for this project included shoring, excavation and dewatering and installation of 600mm, 750mm, 1000mm and 1200mm dia concrete piles. Office Tower (2B + G + 35) project at West Bay for H.E. Shk. Dr. Jassim Bin Nasser Al Thani (Qatar Islamic Bank) The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 750mm and 1000mm dia concrete piles. Residential Tower 44 West Bay (2B + G + 44) project at West Bay for Shk. Abdullah Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 750mm and 1000mm dia concrete piles. Residential Tower (B + G + 40) project at West Bay for Shk. Khalid Bin Naser Abdullah Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 750mm dia concrete piles. Al Zaabi Residential Tower project at West Bay for H.E. Shk. Ahmed Juma Al Zaabi This project involved installation of 750mm and 900mm dia. concrete piles of 19m depth. Dolphin Tower (Commercial 25 Floors) project at West Bay for H.H. Sheik. Hamadan Bin Zayed Al Nahyan This project involved installation of 750mm dia concrete piles 17m depth. Al Dana Office Tower (2B + G + 29) project at West Bay for Shk. Khalid Bin Nasr Abdullah Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 750mm and 1000mm dia concrete piles of 18m depth. Propane and Butane Tanks project at Ras Laffan for Ras Gas/CMS&A, EPIC Contractor: CBI. This project involved installation of 576 nos concrete piles of 1000mm dia for two number LPG tanks for Al Khaleej Project at Ras Laffan. Qatar National Library project for Ministry of Agriculture & Municipal Affairs – Piling sub contractors to M/s Contraco. The scope of works for this project included installation of 1600 number concrete piles totally of 600mm dia with 14m depth and 1200mm dia with 20m depth respectively. Crushed Stone Import Facility at Mesaieed for Qatar Petroleum- Piling sub contractors to Grandi Lavori Fincosit This project involved installation of 750mm, 1000mm and 1200mm dia concrete piles of 19m depth for landside crane rail

Page 44: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 9 of 9

Dec 2002 – Jan 2003 Oct 2002 – Mar 2003 Nov 2002 – Feb 2003 May 2002 – Nov 2002 Feb 2002 – Apr 2002 Sep 2001 – Oct 2001 Mar 2000 – Dec 2000 Mar 1997 – Feb 2000

beam and bridge for the Gabro Berth at Mesaieed Port. Common Cooling Water Project at Ras Laffan for Qatar Petroleum – Piling sub contractors to C.C.I.C. The scope of works for this project included installation of 300mm dia concrete micro-piles for big anchor sleepers for this major project at Ras Laffan. Transmission Line Towers for Qatar General Electricity & Water Corporation – Piling sub contractors to National Contracting Co. The scope of works for this project included installation of concrete piles 600mm to 1300mm dia for the transmission line towers. Jetty & Light House Project at Corniche for Civil Engineering Department, Ministry of Municipal Affairs & Agriculture, Doha – Piling sub contractor to AMCON This project involved piling in marine conditions using floating barge. Concrete piles of 500mm and 760mm dia were installed to 12m depth below sea bed. Temporary Jetty for Halul Project – Piling sub contractors to Archirdon construction Co. S.A Installation of piles for temporary jetty for Halul Island Secant Pile Wall for Sea Water Intake Structure for Ras Gas Expansion Project at Ras Laffan – Rental of Equipment to piling sub contractor of C.C.I.C. Ammico’s scope of work involved rental of piling equipment and personnel for installation of 1000mm dia concrete secant pile wall for sea water intake structure. Giant Stores shopping mall project for Qatar Central Markets Company – Piling sub contractors to Al Alia Trading & Contracting Co. This project involved installation of 450mm and 600mm dia concrete piles. AMMICO FOUNDATIONS L.L.C, DUBAI Worked as Project Manager. Responsibilities included execution of piling works for the following projects:

- German Cars Showroom project at Port Saeed, Dubai - Twin G + 1 Villas project at Al Garhoud, Dubai - External Signage project at City Centre, Ajman.

AMMICO CONSTRUCTORS (P) LTD, LAHORE, PAKISTAN Worked as Site Engineer/Site Manager. Responsibilities included piling and civil works for the following projects:

- Piling & Civil works for Saba Power Plant Project, Pakistan

- Re-construction of Railway Bridge over river Horro, Taxila.

- Construction of flyover at Taxila. - Construction of underpass at new campus canal

crossing, Lahore. - Construction of access road & bridge for Nishat Mills Ltd,

Lahore. - Piling for 220KV transmission line crossing of river Indus

near Chashma. Work involved piling in flowing waters of

Page 45: Company profile[1]

MMUUZZAAFFFFAARR IIQQBBAALL AANNJJUUMM

Page 10 of 9

EXPERIENCE PRIOR TO JOINING AMMICO Jan 1996 – Feb 1997 Jan 1994 – Dec 1995

river Indus. ITALCONSULT S.P.A, LAHORE, PAKISTAN Worked as Site Inspector. Responsibilities included consultancy inspection on Sargodha – Talibwala Road project at Pakistan. HANBO STEEL & GENERAL CONSTRUCTION CO, LAHORE, PAKISTAN Worked as Site Engineer. Responsibilities included construction of Sargodha – Talibwala Road project at Pakistan.

Page 46: Company profile[1]

SSHHEERR AALLII IISSMMAAIILLYY

Page 1 of 5

Designation : Deputy General Manager – Earth Works Division

Date of Birth : December 16, 1960

Nationality : Pakistani

Education : Master of Science – Construction Management, 1985, G.W.

University, U.S.A.

Bachelor of Science, 1984, G.W. University, U.S.A.

Certificates:

Engineering in Training, State of Virginia

Soil Mechanics construction safety, Soil erosion, asphalt,

concrete and quality assurance

Years of experience : Twenty Four

With Ammico since

:

May 2000

SUMMARY OF EXPERIENCE

: Mr. Sher Ali is highly a capable manager and has twenty four years experience in the field of earthworks specialist contracting. He has personally managed execution and completion of a number of large and medium scale projects involving installation of diaphragm walls, secant piles, cast-in-situ piling, deep excavations, dewatering and associated civil works.

PRACTICAL EXPERIENCE May 2012 – Present Dec 2011 – Present

AMMICO CONTRACTING CO. W.L.L. Was responsible in the capacity of Deputy General Manager for following projects:

Gasal O2/N2 PIPE LINE BACK BONE Qatar Construction and Engineering Company (QCon). Ras-Laffan industrial city, Qatar. The scope of work for this project includes machine and manual excavation for 19 kilometre trench for pipe laying, sand bedding and filling trench with processed excavated and imported fill material including making bund.

Poly Silicon Plant Project –Phase-1 Punjlloyd Engineering Limited, Ras LaffanI Industrial City , Qatar

The scope of works Includes Excavation and Crushing of excavated materials.

Page 47: Company profile[1]

SSHHEERR AALLII IISSMMAAIILLYY

Page 2 of 5

Aug 2011 – Dec 2011 Sep 2011 - Nov 2011

May 2011 – Aug 2011 May 2011 – June 2012 Mar 2011 – May 2011

Dec 2010 – Mar 2011 Aug 2010 – Dec 2010 Sep 2007 - Dec 2010 Mar 2008 – Dec 2010 Jul 2009 – Feb 2010

Poly Silicon Plant Project–Early Works Site Preparation Project, Qatar Solar Technologies, Ras Laffan Industrial City , Qatar. The Scope Of work for this Projects Site Preparation Including Excavation, grading leveling Backfilling and Installation Of 4 Km chain link fence and gates For Entry, Exit And Emergency. IKEA Mall Bulk Excavation, Doha Festival City, Qatar The scope of work for this project includes Construction site Facilities, Installation of Site Hoarding and Bulk Excavation and Back Fill Works.

Waste Water Disposal Surface Facilities Project, Qatar Gas, Ras Laffan Industrial City , Qatar.

The Scope of work for this projects Includes Road works, Site Exploratory Trenches Excavation and Backfilling works. Doha West Sewage Treatment Plant, Marubeni Corporation, Saheliya, Doha ,Qatar The scope of work for this projects Includes Excavation and Backfilling Jetty Boil off Gas Recovery Project, QATAR GAS, Ras Laffan Industrial City , Qatar. The Scope of work for this projects Includes Road works, Site Exploratory Trenches Excavation and Backfilling works. EPIC of New Access Road, RLIC Interface Roads, Oryx GTL Plant, Ras Laffan Industrial City , Qatar. The scope of work for this project includes Road Works and Backfilling Works. WRG Project, Qatar Gas & Ras Gas Event Project, 77MTA achievement Ceremony, Ras laffan, Qatar The scope of work for this project includes Civil works , Earth works, Roads and Piling works Was responsible in the capacity of Projects Manager for following projects: Shell GTL Project – CB&I Condensate Tanks Foundations Phase II Common offplot project at Ras Laffan The scope of work for this project includes site preparation, earthworks for thirty eight tank forms of world’s largest GTL plant project. Shell GTL Project –CB&I Civil works at Ras Laffan The scope of work for this project includes on-site and off-site civil works. Al Quds Tower Project, West Bay, Doha (5B + G + 100) The scope of work for this project includes installation of 670m of diaphragm wall to 30m depth, excavation to 24m below existing ground level for the five level basement car park, dewatering and

Page 48: Company profile[1]

SSHHEERR AALLII IISSMMAAIILLYY

Page 3 of 5

Jul 2008 – Jul 2009 May 2007 – Nov 2008 Jan 2006 – May 2008 Jan 2006 – Dec 2006 Dec 2004 - Aug 2006 Dec 2004 – Jul 2006 Nov 2008 – Jul 2009 Nov 2007 – Mar 2008 Sep 2007 – Nov 2007

installation of 1200mm and 1500mm dia piles for the hundred storey tower. Qatar National Bank Head Quarters Building Project, We Bay, Doha (5B + G + 105) The scope of work for this project included installation of 550 meter diaphragm wall to 22m depth, excavation up to 20m below existing ground level for five level basement car park, dewatering and installation of 1200mm and 1500mm dia piles for the hundred and five storey tower. Doha Convention Center & Tower Project, West Bay, Doha (3B + G + 114) The scope of work for this project (which covers an area of 130,000 m2 in the West Bay area of Doha) included following: Installation of 1600 meter diaphragm wall up to 17m depth, excavation up to 21m under the tower footprint, excavation for the triple and double level basement car parks, dewatering, installation of 1500mm dia piles for the hundred and fourteen storey tower and 900mm piles for the convention center. Ras Laffan Common Cooling Project, Phase II, Ras Laffan The scope of work included (a) earthworks, rock cutting and backfilling at discharge channel & pipe Sleeper foundation and pump house I, II and III (b) rock excavation works for foundations, sleeper for pipe racks carrying multiple cooling Water and gas lines. Ras Gas onshore expansion project, Ras Laffan The scope of work included (a) site preparation, rock breaking and backfilling for Train 5 (b) site preparation, rock breaking and backfilling for RGX Train 3 and 4 (c) construction of roads for temporary facilities for Train 4 and 5. Dolphin Project, Process Area, Ras Laffan The scope of work included earthworks, excavation and backfilling for construction of material handling lay down area and site preparation works. Qatar Gas II Expansion project, Ras Laffan The scope of work included site preparation, rock cutting, site grading and structure filling works. Headquarters for The Energy City Qatar, Lussail (2B+G+M+2) The scope of work for this project included installation of 561m diaphragm wall with 16m depth, excavation to 11m below existing ground level for the three level basement car park, dewatering and installation of 600mm, 900mm & 1200mm dia piles for the building structure. Woqod Tower Project, West Bay, Doha (4B + G + M + 30) The scope of work for this project included installation of 238m diaphragm wall to 24m depth, excavation up to 21m below existing ground level for the four level basement car park, dewatering and installation of 900mm and 1200mm dia piles for the thirty storey tower. Lusail Development Marina District Car Park project

Page 49: Company profile[1]

SSHHEERR AALLII IISSMMAAIILLYY

Page 4 of 5

Jul 2007 – Nov 2007 Dec 2006 – Jul 2007 Oct 2006 – Jun 2007 Dec 2005 - Feb 2006 Apr 2005 – Jul 2005 Apr 2005 – Jul 2005 Jan 2005 – Aug 2005 Feb 2005 – Mar 2005 Oct 2004 – Dec 2004 Jul 2004 – Oct 2004

The scope of work for this project included excavation and installation of 600mm dia piles of 11m depth. 2000MW CCPP Project at Mesaieed “A” for Iberdrolla Engg The scope of work for this project included (a) installation of 545 nos 600mm and 415 nos 1000mm dia piles of 22m depth for the main plant (b) installation of 135 m of diaphragm of 19.5m depth for the pump house (c) excavation to 15.5m depth for the pump house (c) construction of the pump house structure. Al Shammal Beach Villa Project for Private Engineering Office This project involved installation of 276 number 750mm dia piles of 24m depth. The Gate Development Project, West Bay, Doha (3B + G + 17) The scope of work for this project included installation of 700m diaphragm wall of 20m depth, excavation to 13m below existing ground level for three level basement car park, dewatering and installation of 900mm and 1200mm dia piles. Residential Tower project for Sheikha Hanadi at West Bay The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 170 piles for the tower structure. Office Tower (2B +G + 29) project at West Bay for M/s. Saeed Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 600mm, 750mm, 1000mm and 1200mm dia piles. Umm Bab Residential Tower (2B + G + 31) project at West Bay for Qatar Islamic Bank The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 600mm and 900mm dia piles for the tower structure. Amwal Commercial Tower (3B + G+ 22) project at West Bay The scope of work for this project included shoring, excavation and dewatering for the three level car park and installation of 600mm and 900mm dia piles. Residential Tower (B1 + G + 45 + 3PH) project at West Bay for H.E. Shk. Khalid Ahmed Al Misnad The scope of work for this project included shoring, excavation and dewatering and installation of 600mm, 750mm, 1000mm and 1200mm dia piles. Office Tower (2B + G + 35) project at West Bay for H.E. Shk. Dr. Jassim Bin Nasser Al Thani (Qatar Islamic Bank) The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 750mm and 1000mm dia piles. Residential Tower 44 West Bay (2B + G + 44) project at West Bay for Shk. Abdullah Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of

Page 50: Company profile[1]

SSHHEERR AALLII IISSMMAAIILLYY

Page 5 of 5

Jul 2004 – Sep 2004 May 2004 – Jul 2004 EXPERIENCE PRIOR TO JOINING AMMICO Apr 1996 – Apr 2000 Jun 1986 – Mar 1996

750mm and 1000mm dia piles . Residential Tower (B + G + 40) project at West Bay for Shk. Khalid Bin Naser Abdullah Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 750mm dia piles. Al Dana Office Tower (2B + G + 29) project at West Bay for Shk. Khalid Bin Nasr Abdullah Al Misnad The scope of work for this project included shoring, excavation and dewatering for the two level car park and installation of 750mm and 1000mm dia piles of 18m depth. HBK CONTRACTING COMPANY W.L.L. DOHA Worked as a project manager for marine construction project in Doha. Responsibilities included construction of land development activities, 9.2 km wide beaches, break waters, revetments and installation of navigation aids equipments. DEPARTMENT OF ENVIRONMENTAL MANAGEMENT, COUNTY OF FAIRFAX, VIRGINA, U.S.A Worked as senior civil Engineer. Responsibilities included design review, preparation of project specification, ensuring construction compliance with ASTM & AASTHO specifications and approved county construction codes, project meeting the standard set for siltation and erosion control, monitor the progress of the residential, commercial and highway projects in Fairfax county.

Page 51: Company profile[1]

GGOORRKKEEMM DDOORRAA

Page 1 of 4

Designation : Proposals and Design Manager

Date of Birth : June 23, 1971

Nationality : Turkish

Education : B.Sc. Civil Engineering, 9 September University, Izmir – Turkey, 1993

M.Sc. Geotechnical Engineering, ITU, Istanbul – Turkey, 1996

Years of experience : Eighteen

With Ammico since : July 2011

SUMMARY OF EXPERIENCE

: Mr. Gorkem Dora is a highly experienced manager with eighteen years experience in the field of geotechnical. He has personally managed a medium scale geotechnical contracting company in conjunction with the execution and completion of a number of large and medium scale projects involving installation of concrete and steel shoring systems, diaphragm walls, cast-in-situ concrete piling, soil improvement and jet grouting. In July 2011 he joined the company and is responsible for all the technical issues for ongoing operations. He is also responsible for the technical and commercial proposals for the company.

PRACTICAL EXPERIENCE Jan-2014 to Present Jan-2013 to Present July 2013 – Dec 2013 Jun 2013 – Dec 2013

AMMICO CONTRACTING CO. W.L.L., DOHA Qatar Integrated Railway Project – Major Station –Musheireb Scope of work for the project included:

- Installation of diaphragm wall - Installation of ground anchors

Qatar Integrated Railway project – Metro 1 – Green Line Underground Scope of work for the project included:

‐ Installation of Diaphragm Wall Workas ‐ Installation of Soil Nailing and Shotcrete Work ‐ Installation of Anchoring Works ‐ Piling works

Construction of Lusail Tower, Com-11, Lusail, Qatar Proposals and Design Manager for installation of soldier piles as shoring system for a length of 70lm and a total of 351 nos. working piles with diameters of 600mm to 1200mm. Re-work Package for Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) Proposals and Design Manager for the installation of removable ground anchors for a previously installed diaphragm wall of 550lm in length.

Page 52: Company profile[1]

GGOORRKKEEMM DDOORRAA

Page 2 of 4

Feb 2013 – Aug 2013 Jan 2013 – Present Jan 2013 – Dec 2013 Sep 2012 – Jan 2013 Jan 2012 – Present Nov 2012 – Mar 2013 July 2012 – Jan 2013 June 2012 – Jan 2013

Aug 2011 – Dec 2012

T.J Pearl Mansion, lsola Dana, The Pearl Qatar Proposals and Design Manager for the project. The scope included 80,500m3 excavation, dewatering and installation of 640mm thick and 11m deep cantilever diaphragm for a length of 785lm. It also included 659 nos. of working piles of 400-600mm diameter and 4 -10m depth. Doha Oasis Mixed Use Development, Musheireb, Doha Proposals and Design Manager for the project. The scope includes the installation of 340lm shoring system with removable ground anchors, consisting of contiguous piles of 750mm diameter & a length of 19m at 1.4m centers. In addition 800 nos. of working piles of 800mm diameter & 11m length and 40 nos. of working piles of 1000mm diameter & 17m length. Lookout Restaurant & SPA, Banana Island, Doha, Qatar Proposals and Design Manager for the installation of 80lm sheet piling for the SPA area. Installation of 62 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles. Installation of 28 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Lookout area. Installation of 143 nos. of 16 - 19m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Over water villa area. Qatar Navigation Shipyard, Messaieed, Qatar Proposals and Design Manager for the project involving dredging and silt removal works under floating dock "Al Rufaa II" at Mesaieed Industrial City (MIC). Link Road to Pearl Lusail Expressway Package 1, Doha, Qatar Proposals and Design Manager for the project involving secant piling works, excavation disposal and backfilling for a 49 no. of shafts. Residential Villa at Pearl Qatar for Mr. Omar Alfardan Proposals and Design Manager for the project involving installation of 203 nos. piles of diameter 800mm and length 11m and 56 piles of 1000mm diameter having length 12m. Al-Wahab Tower, For Ezdan Real Estate, Al Dafna, Doha, Qatar Proposals and Design Manager for the project. Scope of work for the project involved installation king post and timber beam shoring works for 2 storey basement. Le Boulevard Project @ Al Saad, Doha, Qatar Design and Proposal Manager for the installation of 277m concrete diaphragm wall 22.5m depth with 17.5m deep excavation for a four basement structure. Gas Sweetening Facilities (GSF) Project, Mesaieed Industrial City. Design and Proposal Manager for the project. This project is situated in live plant facilities of Qatar Petroleum in Mesaieed, Qatar. The scope of work for this project included procurement, fabrication and installation of 43 no., 762mm diameter steel

Page 53: Company profile[1]

GGOORRKKEEMM DDOORRAA

Page 3 of 4

Jun 2011 – April 2013 Sep 2011 – Jun 2012 Jul 2011 – Nov 2012 EXPERIENCE PRIOR TO JOINING AMMICO 2004 – June 2011

tubular piles with 25mm thickness. The fabrication and installation of precast pile caps, beams and slabs as well as cast in situ concrete in various stages. Land reclamation and revetment works and construction of culvert is also included in the project scope.

Doha Land Phase-2 & Phase-3 Project Design and Proposal Manager for the installation of 625m concrete diaphragm wall to 18m & 23m depth, excavation to 13.7m & 17.2m below existing ground level for the 4 & 5 basements respectively, dewatering and installation of 900mm, 1500mm & 1800mm diameter concrete piles. National Library, Education City, Rayyan, Qatar Design and Proposal Manager for the installation of 438 no. 500mm – 1200mm diameter concrete piles. Qatar Faculty of Islamic Studies, Education City, Rayyan, Qatar Proposals and Design Manager for the installation of 698 nos concrete piles of 500mm – 1500mm diameter piles.

GEOMAR GULF LLC , DUBAI – UAE Worked as: General Manager (2009 – June 2011) Technical Manager (2008 – 2009) Operations Manager (2006 – 2008) Project Manager (2004 – 2006). Some of the managed/executed major projects;

- Al Hamidiya Interchange Bridge Piles, Ajman - Armed Forces Al Wathba Camp Piling Works, Abu Dhabi - Police Station & Barrack Piling & Shoring Works, Abu

Dhabi - Al Khaleej Sugar Molasses Pit Shoring Works, Dubai - Dubai Metro Al Quasis Cooling Plant Piling Works,

Dubai - Al Khail / Umm Sequim Intersection Bridge Piles, Dubai - Shafar Tower Piling & Shoring Works, Dubai - Al Khail / Emirates Road Intersection Bridge Piles, Dubai - Emirates Road / Sports City Intersection Bridge Piles,

Dubai - Maze Tower Car Park Piling Works, Dubai - ARY Tower Piling & Shoring Works, Dubai - Dubai Metro Al Rigga Cooling Plant Shoring Works,

Dubai - Dubai Marina Nakheel Bridges Piling Work, Dubai - Platinum Tower Piling & Shoring Works, Dubai - Atlas Telecom Office Building Piling & Shoring Works,

Dubai - Palm Jumeriah Shoreline Apartments & Club Houses Piling

Works, Dubai - Cascades Tower Piling & Shoring Works, Dubai

Page 54: Company profile[1]

GGOORRKKEEMM DDOORRAA

Page 4 of 4

2000 – 2004 1996 – 2000 1995 – 1996

KASKTAS ARABI, JEDDAH - KSA Worked as Deputy General Manager (2003 – 2004) Project Manager (2001 – 2003) Site & Design Engineer (2000 – 2001) Some of the managed/executed major projects;

- Qebla Center Shoring Works, Madinah - Jabal Ka’abe Permanent Rock Anchor Works, Makkah - Development of King Abdul Aziz Permanent Rock Anchor

Works, Makkah - Fakieh Aquarium Piling Works, Jeddah - Hilton Hotel Apartment Phase Piling Works, Jeddah

KASKTAS AS, ISTANBUL - TURKEY Worked as Design Engineer (1999 – 2000) Site Engineer & Design Engineer (1996 – 1999) Some of the executed/designed major projects;

- Tengiz Chevroil Oil Plant Train 5 Sheet Piling Works, Kazakhstan

- Tengiz Chevroil Oil Plant Train 5 Driven Pre-cast Pile Piling Works, Kazakhstan

- Tengiz Chevroil Oil Plant Debottlenecking Mini Piling Works, Kazakhstan

- Beytem Car Park Shoring Works, Istanbul - Alarko Villas Soil Nailing Works, Istanbul

ISTANBUL TECHNICAL UNIVERSITY, ISTANBUL - TURKEY Worked as Research & Teaching Assistant

Page 55: Company profile[1]

P. KUMARESAN

 

 Page 1 of 3 

 

Designation : Projects Manager

Date of Birth : July 28, 1970

Nationality : Indian

Education : B.Sc. Civil Engineering, University of Madras – India, 1991.

Years of Experience : 22 Years

With Ammico since : October 2011

SUMMARY OF EXPERIENCE

: Mr. Kumaresan has 22 years experience in Construction Engineering out of which the last sixteen years (1997 – 2013) has been in the field of Foundation Engineering. During these years, he has been responsible for a number of major projects in Dubai, Singapore and India involving installation of bored piles, secant piles, diaphragm wall, ground anchors, deep excavations and dewatering for high rise buildings, metro railway structures etc.

PRACTICAL EXPERIENCE

AMMICO CONTRACTING CO. W.L.L., Doha, Qatar

Jan‐2013 to Present  July-2013 to Dec 2013 Oct 2011 – June-2013 EXPERIENCE PRIOR TO JOINING AMMICO Apr 2008 – Sep 2011

: : :

Qatar Integrated Railway project – Metro 1 – Green Line UndergroundScope of work for the project included: 

‐ Installation of Diaphragm Wall Workas ‐ Installation of Soil Nailing and Shotcrete Work ‐ Installation of Anchoring Works ‐ Piling works 

Re-work Package for Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) - Rework Managing the project in the capacity of Projects Manager. The scope of work for this project included installation of 550 meter long concrete diaphragm wall to 22m depth, removable ground anchor, excavation up to 20m below existing ground level for five level basement car park, dewatering and installation of 1200mm and 1500mm dia concrete piles for the hundred and five storey tower. Doha Land Phase-2 & Phase-3 Project Projects Manager for the installation of 625m of diaphragm wall to 18m & 23m depth, excavation to 13.7 & 17.2m below existing ground level for the 4 & 5 basements respectively, dewatering and installation of 900 mm, 1500mm & 1800 mm diameter piles. Sharaf Foundations LLC - Dubai As Sr. Project Manager was responsible for execution of piling, earth

Page 56: Company profile[1]

P. KUMARESAN

 

 Page 2 of 3 

 

May 2006 – Mar 2008 Jul 2003 – Apr 2006 Mar 1999 – June 2003 Sep 1998 – Jan 1999 Apr 1997 – Aug 1998

: : : : :

retention (diaphragm wall, secant piles etc.), excavation and dewatering works on following projects in Dubai:

1. Corporate Bay Tower (5B+G+3P+29) at Business Bay 2. Cascade Ville (4B+G+7) at Cultural Village 3. Cascade Manor (5B+G+8) at Cultural Village 4. Yuvi Residence (3B+G+8) at Cultural Village 5. Sanctuary Tower (3B+G+22) at Business Bay 6. The Corner Tower (3B+G+3P+18F) at Business Bay 7. Sharaf Hotel Tower (3B+G+3P+18) at Business Bay 8. Fortune Bay Tower (3B+G+19) at Business Bay 9. DEC Business Tower (3B+G+19) at Business Bay

Arabian Foundation Engineering – Dubai As Project Manager was responsible for piling, earth retention (diaphragm wall, secant piles etc.), excavation and dewatering works on following projects in Dubai:

1. Commercial & Residential Tower (4B+G+25) at Muteena 2. IBIS &Novotel Hotels (2B+G+20) at Deira 3. New City Centre Offices Building (3B+G+20) at Deira 4. Century Properties Building (3B+G+10) at Port Saeed 5. Raffa Tower (4B+G+20) at Al Raffa

Middle East Foundations Group – Dubai Participated in piling, earth retention (diaphragm wall, secant piles etc.), excavation and dewatering works on following projects in Dubai:

1. Dubai Mall - The world’s largest shopping mall (Project Manager) 2. Dubai Sports City Developments Project (Project Manager) 3. Burj Dubai – The world’s tallest tower (QA/QC Manager) 4. Dubai International Airport Expansion Phase II (Project Engineer) 5. Jumeirah Beach Residence Project (As Project Engineer)

Geo Foundations & Structures, Chennai – India As Project Manager was responsible for piling works on following projects in India:

1. Mass Rapid Transport Station Building at Tharamani – Chennai 2. Mass Rapid Transport Station Building at Velacherry – Chennai 3. Vijayawada-Uppalapadu Transmission Line Project in Andra

Pradesh 4. South Eastern Railways Major Bridge No. 343 in Orissa

Falcon Piling Pte Ltd – Singapore Was involved in piling works for following project in the capacity of Civil Engineer:

1. Bored Piling Works for Sengkong Metro Station & Depot Rotary Piling Pte Ltd – Singapore Was involved in piling, secant piles and contiguous piles for following projects in the capacity of Civil Engineer:

1. Hill View Condominium Project – Hill View 2. Primary School Project at Tampaines

Page 57: Company profile[1]

P. KUMARESAN

 

 Page 3 of 3 

 

Sep 1993 – Dec 1996 May 1991 – Aug 1993

:

3. Housing & Development at Toa PayohLorong 8 4. Housing & Development Plot No 851 & 852 at Commonwealth

Avenue Galaxy Consultants Pvt Ltd – Chennai Worked as Civil Engineer responsible for supervision for following projects:

1. Extension of Central Railway Station Main Building – Chennai 2. Construction of Coimbatore Stock Exchange Building

Subhiksha Housing (P) Ltd – Chennai Worked on various building construction projects in the capacity of site engineer.

Page 58: Company profile[1]

UUYYGGAARR KKOOPPRRUUCCUU

Page 1 of 4

Designation : Project Manager - Manager Marine Division

Date of Birth : April 11, 1975

Nationality : Turkish

Education : B.Sc. Construction Civil Engineer, Istanbul University – Turkey, 1997

Years of experience : Seventeen

With Ammico since : April 2012

SUMMARY OF EXPERIENCE

: Mr. Uygar Koprucu is a highly capable manager with seventeen years of experience in the field of offshore and marine engineering construction. He has personally managed the execution of a number of major marine projects involving construction of jetties, driven piles, under water pipe lines, quay wall construction (dredging, trench excavation, foundation preparation, and placing blocks, concrete repair works and general marine maintenance works).

PRACTICAL EXPERIENCE Jan 2013 – Dec 2013 Apr 2012 – Jun-2012 July 2012 – Sep-2012 May 2012 – Jun 2012

AMMICO CONTRACTING CO. W.L.L., DOHAMr. Uygar, in the capacity of Manager – Marine Division, joined Ammico in April, 2012 and is responsible for planning and execution of all projects in the marine environment. Lookout Restaurant & SPA, Banana Island, Doha, Qatar Managing the project in the capacity of Deputy General Manager. Scope of work for the project included 80m sheet pile for SPA area. Installation of 62 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles. Installation of 28 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Lookout area. Installation of 143 nos. of 16 - 19m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Over water villa area. Marine Navigation Beacon @ New Port Project – Doha Overall supervision for the supply and installation of Tidal Beacon Gauge Structure onto 4 driven Ø510/15 piles. Installation and piling includes rock socketing, impact and vibratory driving of piles together with offshore rigging and lifting of the Beacon Structure. Installation was made by partial bolting and on site welding. Dredging Works at Ras Laffan Port Expansion Project – Qatar Overall supervision for the dredging works to remove marine sediment and silt formation by a suction dredger from -13.5 m to -14.5 m for a total of 4200 m3 material. Installation of Marine Piles for Private Jetty, Al Jassasia – Qatar Overall supervision for the supply and Installation of 38 driven

Page 59: Company profile[1]

UUYYGGAARR KKOOPPRRUUCCUU

Page 2 of 4

Apr 2012 – May 2012 EXPERIENCE PRIOR TO JOINING AMMICO May 2011 – Mar 2012 Dec 2006 – May 2011

Ø510/15 Steel Piles. Installation and piling includes rock socketing, impact and vibratory driving of piles. 14 of the projects piles were rock socketed from shore by Auger drilling rigs whereas 24 of them were socketed by floating work vessel by Pile To[ Driller. Banana Island Project – offshore of NDIA, Qatar Overall supervision for the installation of sheet piling and concrete works for two Loading Ramps at Banana Island, Qatar. SIX CONSTRUCT – UAE Project Name: ADGAS IGD Project ( Das Island – UAE ) Worked as Marine Construction Superintendent. Responsibilities included:

Overall supervision of all Marine Construction Works. Communications with Management (PM) in case

problems are encountered. Overall supervision of all DSV / diver installation &

operations and Diving Safety. Responsible for coordinating the Marine Movements of

Working Vessels with Port Authority. Coordination of all required materials, QA/QC related

activities and documentation and surveying issues. NEK OFF SHORE CONSTRUCTION / TARTICILAR A.S. JV Worked as Project Manager. Responsibilities included:

Hands-on construction management for Onshore & Offshore projects.

Oversee all on-site project activities and conduct inspections to ensure projects are completed on schedule, within budget, in accordance with engineering design and in conformance with quality criterias.

Following with tool box safety and progress meetings held on site, attending daily progress meetings with staff and subcontractors, weekly meetings with consultancy and employer.

Leading QA/QC, PMP and Method Statement documentations, tendering and bidding studies, vendor and supplier relations, procurement facilities and staff development programmes.

Implementing design, first applications, stated methods as per contracts and project planning principlas at site, hiring and staffing of employees and subcontractors, developing and enforcing company policies and procedures.

Projects handled during working at NEK OFF SHORE CONSTRUCTION / TARTICILAR A.S. JV are as follows;

Arab Potash Main Pump Station Jetty Construction (Deadsea / Jordan ) 150,000,000 USD budget project, supervising a crew of 420 trades workers, reported by 13 co-workers. Project is formed of 207 offshore & 202 onshore driven piles with sockets varies from 7 to 30 meters. Project is completed 20 days earlier with 2 % budget saving.

Page 60: Company profile[1]

UUYYGGAARR KKOOPPRRUUCCUU

Page 3 of 4

Apr 2005 – Dec 2006 Jun 2002 – Apr 2005

SAVKA Berthing Platform for Fuel Oil Vessels (Mersin / Turkey ) 8,000,000 USD budget project, supervising a crew of 60 trades workers, directly reported by 6 co-workers. Project is 5.5 kilometers away from shoreline and formed of 72 offshore driven piles which are 34 meters and a Subsea pipeline for 15 kilometers. Project completed within deadlines despite high sea conditions and unforeseen subcontractor disputes.

Kibar Holding Container Terminal Construction (İskenderun / Turkey) 25,000,000 USD budget project (only labour, material supplied by Employer), supervising a crew of 95 trades workers, directly reported by 8 co-workers. Project is formed of 752 offshore driven piles which varies from 36 to 53 meters including all constructional concrete repair works for the onshore facilities. Project completed 55 days earlier despite extensive material delays and many design changes with 3 % budget saving.

Marmaray Immersed Project – Construction of Flat Top Diving Barge (Istanbul / Turkey ) 650,000 USD budget project, supervising a crew of 45 trades workers, directly reported by 4 co-workers. Project completed within deadlines despite excessive short construction schedule agreed with the contract within budget limits.

Marmaray Tuzla Construction Yard Temporary Jetty Construction (İstanbul / Turkey ) 2,500,000 USD budget project, supervising a crew of 60 trades workers, directly reported by 4 co-workers. Project completed within deadlines and budget limits.

TAISEI CORPORATION Project Nam: MARMARAY IMMERSED TUNNEL PROJECT – ISTANBUL Worked as Deputy Project Manager for Concrete / Concrete Specialist and Tuzla Construction Site Deputy Site Manager. Responsibilities included:

Hands-on construction management for Tuzla Site construction facilities.

Leading QA/QC and Method Statement documentations, staff development programmes, attending daily progress and site tool box safety and progress meetings.

Creation the design of the required concrete, trial castings and testing all properties. Accreditation and creation of Concrete Laboratory required by the Employer’s Requirement at Istanbul Technical University.

Modeling and reporting of the designed concrete via computer aided modeling softwares, attending quality and progress meeting with the consultant for concrete related works.

LAFARGE TURKEY-AGGREGATE AND CONCRTE GROUP / ISTANBUL Worked as Kurtkoy Batching Plant Manager. Responsibilities included:

Management of Batching Plant for concrete production. Analysing and reporting of market needs, area sales

strategies and special product sales activities. Customers relations management together with

Page 61: Company profile[1]

UUYYGGAARR KKOOPPRRUUCCUU

Page 4 of 4

Dec 1999 – Jun 2002 Aug 1995 – Apr 1999

customer consistency improving studies. Alpsan A.Ş. / Istanbul Worked as Product Manager. Responsibilities included:

Material supply, market analysis and specifying the strategies

Reporting the sales on daily, weekly and monthly base to high management

OZENC CONSTRUCTION LTD. Worked as Site Engineer / Site Chief. Responsibilities included:

Application of the project at construction yard. Complying with the daily, weekly and monthly work

schedules. Keeping the production and quality records.

Page 62: Company profile[1]

TOHEED AHMED

Page 1 of 4  

Designation : QA/QC Manager

Date of Birth : March 26, 1976

Nationality : Pakistani

Education : PGD in Total Quality Management – University of the Punjab, Lahore – Pakistan.

Masters in Environmental Sciences – University of the Punjab, Lahore – Pakistan.

Bachelor in Civil Engineering, UET, Lahore – Pakistan

Years of Experience : Twelve

With Ammico since : August 2008 SUMMARY OF EXPERIENCE

:

Mr. Toheed is a results oriented Civil Engineer with twelve years experience in Quality Assurance & Quality Control. He has been working for the past three years as Ammico’s QA/QC Manager and is responsible for:

Preparation and implementation of Project Quality Plans Periodic QA/QC audits ISO 9001:2008 certification

He was the person who initiated the ISO certification for the company in early 2009 and saw it through in a period of six months.

PRACTICAL EXPERIENCE Jan-2014 to Present  July 2013 – Dec 2013 Jun 2013 – Dec 2013 Feb 2013 – Jun 2013

AMMICO CONTRACTING CO. W.L.L., DOHA Mr. Toheed has developed and implemented QHSE procedures, training schedules and audits for many of Ammico projects. Qatar Integrated Railway Project – Major Station – Scope of work for the project included: 

- Installation of diaphragm wall - Installation of ground anchors 

 Construction of Lusail Tower, Com‐11, Lusail, Qatar. Managing the project in the capacity of QA/QC Manager. Scope of work for the project included; installation of soldier piles as shoring system for a length of 70lm and 351 nos. working piles with diameters of 600mm to 1200mm.  Re‐work Package for Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) Managing the project in the capacity of QA/QC Manager. Scope of work for the project includes design and installation of removable ground anchors for a previously installed diaphragm wall 550lm in length.  T.J Pearl Mansion, Isola Dana, The Pearl Qatar. Managing the project in the capacity of QA/QC Manager.

Page 63: Company profile[1]

TOHEED AHMED

Page 2 of 4  

Jan 2013 – Present Jan 2013 – Dec 2013 Sep 2012 – Jan 2013 Jan 2012 – Present Nov 2012 – Mar 2013 July 2012 – Jan 2013 June 2012 – Jan 2013 Aug 2011 – Dec 2012

Scope of work for the project includes 80,500 m3 excavation, dewatering and installation of 640mm thick and 11m deep cantilever diaphragm for a length of 785lm. It also includes 659 nos. of working piles with 400‐600mm diameter and 4‐10m depth.   Doha Oasis Mixed Use Development, Musheireb, Doha, Qatar. Managing the project in the capacity of QA/QC Manager. Scope of work for the project includes 912,150 m3 excavation, installation of 340 lm shoring system, removable ground anchor, consisting of contiguous piles of diameter 750mm & length 19 meter at a centre to centre distance of 1.4 meters. It also includes 800 nos. of working piles with 800mm diameter & 11m length and 40 nos. of working piles with 1000mm diameter & 17m length. Lookout Restaurant & SPA, Banana Island, Doha, Qatar Managing the project in the capacity of QA/QC Manager. Managing the project in the capacity of Deputy General Manager. Scope of work for the project included 80m sheet pile for SPA area. Installation of 62 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles. Installation of 28 nos. of 12m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Lookout area. Installation of 143 nos. of 16 - 19m length, 11 mm thickness & 475 mm diameter onshore/offshore steel piles in the Over water villa area. Qatar Navigation Shipyard, Messaieed, Qatar Managing the project in the capacity of QA/QC Manager. Scope of work for the project involved dredging and silt removal works under floating dock "Al Rufaa II" at Mesaieed Industrial City (MIC). Link Road to Pearl Lusail Expressway Package 1, Doha, Qatar. Managing the project in the capacity of QA/QC Manager. Scope of work for the project involved secant piling works, excavation disposal and backfilling for 49 no. of shafts.  Residential Villa at Pearl Qatar for Mr. Omar Alfardan Managing the project in the capacity of QA/QC Manager. Scope of work for the project involved installation of 203 nos. piles of diameter 800mm and length 11m and 56 piles of 1000mm diameter having length 12m. Al-Wahab Tower, for Ezdan Real Estate, Al Dafna, Doha, Qatar Managing the project in the capacity of QA/QC Manager. Scope of work for the project involved installation king post and timber beam shoring works for 2 storey basement. Le Boulevard Project @ Al Saad, Doha, Qatar. Managing the project in the capacity of QA/QC Manager. Scope of work for the project involved the installation of 277lm concrete diaphragm wall 22.5m depth with a 17.5m deep excavation for four basement structure. Gas Sweetening Facilities (GSF) Project, Mesaieed Industrial City, Messaieed, Qatar. Managing the project in the capacity of QA/QC Manager. This project is situated in live plant facilities of Qatar Petroleum in

Page 64: Company profile[1]

TOHEED AHMED

Page 3 of 4  

Jun 2011 – Mar 2013 Sep 2011 – Jun 2012 Jul 2011 – Nov 2011 Dec 2010 – Jun 2011 July 2010 – Aug 2011 Aug 2010 – Oct 2010 June 2010 – Oct 2010 Feb 2010 – Oct 2010

Mesaieed, Qatar. The scope of work for this project included procurement, fabrication and installation of 43 no., 762mm diameter steel tubular piles with 25mm thickness. The fabrication and installation of precast pile caps, beams and slabs as well as cast in situ concrete in various stages. Land reclamation and revetment works and construction of culvert is also included in the project scope. Doha Land Phase-2 & Phase-3 Project, Doha, Qatar. Managing the project in the capacity of QA/QC Manager. The scope of work included the installation of 625lm concrete diaphragm wall to 18m & 23m depth, removable anchors, excavation to 13.7m & 17.2m below existing ground level for the 4 & 5 basements respectively, dewatering and installation of 900mm, installation of 1500mm & 1800mm diameter concrete piles. The project had a total of 3500 number piles. National Library, Education City, Al Rayyan, Qatar. Managing the project in the capacity of QA/QC Manager. The scope of works includes the installation of 438 no. of 500mm – 1200mm diameter concrete piles. Qatar Faculty of Islamic Studies, Education City, Al Rayyan, Qatar. Managing the project in the capacity of QA/QC Manager. The scope of work for this project includes the installation of 698 concrete piles of 500mm – 1500mm diameter piles. Earthworks, Shoring, Anchors & Soil Nailing Works at Sheraton Park Project, West Bay Doha. Managing the project in the capacity of QA/QC Manager. The scope of work for this project included; excavation of approximately 1,100,000 m3, backfilling of approximately 250,000 m3, installation of 605 lm concrete secant pile wall, 241 Lm of concrete contiguous pile wall, 380 no. anchors and installation of 1700 no. soil nails. Jetty Boil-Off Gas Recovery Project, Ras Laffan Industrial City Managing the project in the capacity of QA/QC Manager. The scope of work for this project included the installation of 1036 concrete piles of 600mm diameter and 8m long below cut off level. Lusail Development Sewage Treatment Works, Lusail, Qatar. Managing the project in the capacity of QA/QC Manager. The scope of work for this project included installation of concrete secant piles for shafts, excavation & De-watering for shafts. Construction of Temporary Berth at Marsa Arabia Project, The Pearl Qatar. Managing the project in the capacity of QA/QC Manager. The scope of work for this project was the installation of steel offshore piles 900mm dia and the design & construction of temporary berth at Marsarabia, The Pearl Qatar, including associated concrete works, marine grade painting and miscellaneous metal works and accessories. Ras Laffan Port Expansion Project, Ras Laffan, Qatar. Managing the project in the capacity of QA/QC Manager. The scope of work for this project was the installation of concrete

Page 65: Company profile[1]

TOHEED AHMED

Page 4 of 4  

July 2010 – Sep 2010 Apr 2009 – Jan 2010 Aug 2008 – June 2010 Aug 2008 – May 2010 EXPERIENCE PRIOR TO JOINING AMMICO Sep 2001 – Aug 2008

piles dia 900mm and depth up to 27m for coast guard, liquid petroleum berth and container berth. 12 New Departure Gates Project at Doha International Airport Managing the project in the capacity of QA/QC Manager. The scope of work for this project included installation of 600mm dia bored piles 101 number and 750mm dia concrete bored piles 39 number. Lusail Transit System / CP 13 – Phase ESE for QDVC Managing the project in the capacity of QA/QC Manager. he scope of works for this project included reinforced earth wall using geotextile membrane upto 7m depth, excavation upto 14m depth below ground level. Shell GTL Project – CB&I Condensate Tanks Foundations Phase II Common off plot project at Ras Laffan, Qatar. Managing the project in the capacity of QA/QC Manager. The scope of work for this project included site preparation, earthworks for thirty eight tank forms of world’s largest GTL plant project.   Shell GTL Project –CB&I Civil works at Ras Laffan, Qatar. Managing the project in the capacity of QA/QC Manager. The scope of work for this project included on-site and off-site civil works. Before joining AMMICO in Qatar, Mr. Toheed Ahmad worked on following projects in Pakistan as QA/QC engineer:

MOL Gas Project – field development, site facilities, tank foundations, MCCR buildings, pipe racks, main control rooms, residential blocks (US$140 million).

Mangla Dam Upraising Project – earthworks, earth retentions systems, upstream blanket worsk, RCC works, emergency spillway, dredging, mass filling (US$400 million)

1B+G+4 Storey Descon World Headquarter Construction Project – Worked as Site Incharge

He also worked with Presson Descon International Ltd, Descon Engineering Ltd. and MSC Textile Mills in Pakistan.

Page 66: Company profile[1]

HHAAMMMMAADD HHAAKKEEEEMM

Page 1 of 5

Designation : HSE Manager

Date of Birth : January 15, 1976

Nationality : Pakistani

Education : B.Sc Professional Engineer

Years of experience : Twelve

With Ammico since

Certification

:

:

:

:

:

:

August 2012

NEBOSH International General Certificate in Occupational Health and Safety

An Overview of the WISHA Rules 1-2

WISHA Fall Protection Systems-Overview.

WISHA Fall Protection Systems and Methods.

WISHA Fall Arrest System

SUMMARY OF EXPERIENCE

: Mr. Hammad Hakeem is highly motivated HSE Manager with ten years experience. He is dedicated to ensure the correct HSE practices are followed on Ammico sites. Before joining Ammico, he worked with world class organization like Descon Engineering.

PRACTICAL EXPERIENCE

AMMICO CONTRACTING CO. W.L.L., DOHA Working as a Manager Construction Safety having the following responsibilities

- Design safety training programs for employee and ensure response to all specific requirements and maintain knowledge of all company safety programs.

- Prepare all HSE training program according to required regulations and prepare schedule of all training programs and ensure all employees receive appropriate training and participate in various committee meetings for site.

- Develop and recommend improvements to all Safety Systems and develop and implement efficient global operations emergency response plans and ensure adherence to all federal and state regulations.

- Provide support to execution of all global operation emergency response plans and manage all emergency situations and design solutions to all issues and design required business tools and execute all HSE procedures and policies.

- Monitor all HSE procedures and recommend strategies to avoid all accidents and implement all health and safety hazards for all sites.

- Monitor all conservation and protection programs and maintain hygiene at facility at all times and prepare required status reports.

Page 67: Company profile[1]

HHAAMMMMAADD HHAAKKEEEEMM

Page 2 of 5

Jan-2014 to Present Jan-2013 to Present July 2013 – Dec 2013 Jun 2013 – Dec 2013 Feb 2013 – Jun 2013 Jan 2013 – Present Jan 2013 – Present Sep 2012 – Jan 2013 Jan 2012 – Present Nov 2012 – Mar 2013 July 2012 – Jan 2013

Qatar Integrated Railway Project – Major Station – Scope of work for the project included:

- Installation of diaphragm wall - Installation of ground anchors

Qatar Integrated Railway project – Metro 1 – Green Line Underground Scope of work for the project included:

‐ Installation of Diaphragm Wall Workas ‐ Installation of Soil Nailing and Shotcrete Work ‐ Installation of Anchoring Works ‐ Piling works

Construction of Lusail Tower, Com-11, Lusail, Qatar.

- HSE Manager for the project including installation of soldier piles as shoring system for a length of 70lm and 351 nos. working piles with diameters of 600mm to 1200mm.

Re-work Package for Qatar National Bank Head Quarters HSE Manager for the project including design and installation of removable ground anchors for a previously installed diaphragm wall 550lm in length.

T.J Pearl Mansion, Isola Dana, The Pearl Qatar.

- HSE Manager for the project including 80,500 m3 excavation, dewatering and installation of 640mm thick and 11m deep cantilever diaphragm for a length of 785lm. It also includes 659 nos. of working piles with 400-600mm diameter and 4-10m depth. Doha Oasis Mixed Use Development, Musheireb

- HSE Manager for the project involving shoring system, piling and excavation. Lookout Restaurant & SPA, Banana Island

- HSE Manager for the project involving offshore piling and sheet piling at Banana Island Qatar Navigation Shipyard

- HSE Manager for the project involving dredging works under floating dock "Al Rufaa II" at Mesaieed Industrial City (MIC).

Link Road to Pearl Lusail Expressway Package 1

- HSE Manager for the project involving secant piling works, excavation disposal and backfilling for a no. of shafts.

Residential Villa at Pearl Qatar for Mr. Omar Alfardan

- HSE Manager for the project involving installation of 203 nos. piles of diameter 800mm and length 11m and 56 piles of 1000mm diameter having length 12m.

Al-Wahab Tower

- HSE Manager for the project involving installation and testing of preliminary test piles, installation of working piles, tests on working piles, shoring and excavation works.

Page 68: Company profile[1]

HHAAMMMMAADD HHAAKKEEEEMM

Page 3 of 5

June 2012 – Jan 2013 Aug 2012 – Dec 2012 EXPERIENCE PRIOR TO JOINING AMMICO Sep 2011 – Aug 2012

Apr 2011 – Sep 2011

Le Boulevard Project @ Al Saad- HSE Manager for the installation of 277m concrete diaphragm

wall 22.5m depth having 17.5m deep excavation for four basement structure. Gas Sweetening Facilities (GSF) Project, Mesaieed Industrial City.

- Responsible for the implementation of the correct HSE practices for the installation of 43 no. of 712 mm diameter of concrete piles, and jetty marine works, including precast concrete decking, fabrication and installation.

49.5MW Wind Power, Jamhpir, Sind, Pakistan Worked as a Deputy Manager Construction Safety having the following responsibilities:

- To recommend and implement improvement in the construction work practices and procedure through mandatory and job specific training for project workforce.

- Development of training plan, monthly training schedule and training reports.

- Supervision and auditing on the contractor and sub-contractors In-House safety training.

- Development and conducting weekly TBT for management and contractor staff.

- Supervision of contractors weekly TBT - Develop safety statistics for bi-weekly safety committee and

senior management safety reviews. - Approve material supplies of necessary HSE material and

First-Aid equipment to sites and workforce. - Monthly & Weekly departmental safety & HSE NC reporting. - Develop and share HSE awareness materials and

Procedures. Installation of Styrene Pipe Line At Al-Jubail KSA Worked as a HSE Engineer Construction Safety having the following responsibilities

- Develop & Implement Project HSE Management System (e.g.; HSE Plan, Supporting Procedures, Risk Assessments, Training programs and Communication media such as HSE Alerts, Bulletins etc.

- Establish and Manage onsite and offsite HSE team roles and responsibilities.

- Review Sub-Contractor’s documentation such as HSE Plans, Procedures & Risk Assessments.

- Supervising & conducting various training courses (e.g. HSE Inductions, Crisis and Emergency Management (Including Drills), Risk Analysis & Assessments, Hazardous materials, Confined Space etc.)

- Reviewing and monitoring sub-contractor’s HSE Management system.

- Maintain a record of all accidents reported from site. - To ensure that investigation reports of serious accidents are

Page 69: Company profile[1]

HHAAMMMMAADD HHAAKKEEEEMM

Page 4 of 5

Sep 2010 – Apr 2011 Sep 2008 – Sep 2010

prepared and forwarded to the management. - Arrange regular meetings PM/SM/PE and others to discuss

Safety Policy, accident prevention, training requirements, future works etc. Make sure follow-up action has been carried out.

- Advise management on the preparation, promotion review of the company’s HSE policy.

- Carry out investigations of serious accidents and prepare and provide HSE statics on weekly and monthly basis.

- Approve material supplies of necessary HSE material and First-Aid equipment to sites and workforce.

- Implementation and co-ordination of the project safety organization.

- Arrange and provide necessary literature for use and display at sites and workplaces.

- Scheduling and conducting regular safety meetings with management, supervisory staff and various craft groups and maintaining broad safety awareness on the project. Food & Utility Plant At Karachi, Pakistan Worked as a HSE Engineer Construction Safety having the following responsibilities

- To recommend and implement improvement in the construction work practices and procedures through mandatory and job specific training for project workforce.

- Responsible for developing training programs to cover construction activities, plant shut down, tie-in, pre-mechanical commissioning and commissioning activities.

- Training of managers, supervisors and work force from construction and pre-mechanical commissioning and commissioning groups.

- Development of training plan, monthly training schedule and training reports.

- Supervision and auditing on the contractor and sub-contractors In-House safety training.

- Development and conducting weekly TBT for management and contractor staff.

- Supervision of contractors weekly TBT. - Develop safety statistics for bi-weekly safety committee and

senior management safety reviews. - Develop and managing BBS (Behavior Based Safety)

programme in collaboration with client and owner. - Participate in SIMOPS safety assessments. - Implement & review safety procedures such as, STOP, SOP,

and "Supervisors as Safety Advisors" and Training to the front line supervision.

- Training on Risk Assessment and Hazard Identification programme (HIP).

- Conduct regular site visits for to ensure the hygiene standard of welfare facility is maintained to the required standard.

Port Qasim Karachi Foundry Project, Pakistan Worked as a Manager Construction Safety having the following responsibilities:

- Support EHS Manager in the practical implementation of the company EHS Policy and procedures.

- Implement company’s and client’s Environmental, Health and

Page 70: Company profile[1]

HHAAMMMMAADD HHAAKKEEEEMM

Page 5 of 5

Nov 2006 – Sep 2008

Feb 2002 – Oct 2006

Safety Program which includes pollution control, waste management

- Monitor that the proper barricades and safety signs are in place and to educate the workers to respect and follow the signs and barricades

- Giving training to the workers how to use fire extinguishers and tackle.

- Conduct site inspections and walk through to monitor the safety of personnel and property by identifying work and property hazards and to make appropriate corrections.

- Monitor the implementation of the Job Hazard Analysis (JHA) safety precautions.

- Conducts the Daily Tool Box meetings periodically and assist supervisors/ foramens to conduct tool box meetings prior to start the job. .

- Equipments inspections, to ensure that safety equipment and facilities are in best working order prior to use.

- Keep all safety records (Tool Box Meetings, Competent personnel list and certificates, Heavy equipment list and certificates). Investigate and prepare the incident and/or accident reports and keep record of it. Assure work permits are in place prior to start of work in Permit To Work (PTW) or Restricted areas Shell Pearl GTL (Gas to Liquids) 2. Dolphin Onshore Gas Facilities At Ras Laffan Qatar Worked as a HSE Field Incharge having the following responsibilities:

- Carrying out site supervision, site surveys, Hazard Assessments, Accident/ Incident Investigations.

- Checking & Inspection of confined spaces, Hot jobs, Crane operations, Heavy lifts and field fire fighting equipments.

- Implementing color coding of tools & equipments, lifting gears, cranes and earth moving equipments.

- Preparation of HSE reports, JSA, Flyers and other HSE documentation.

- Conducting tool box talk and attending meetings with client and sub-contractors.

- Identify and facilitate implementation of Qatar’s regulatory health, safety and environmental requirements and other international HSE standards in accordance with project objectives.

Haroon Oils Limited Karachi, Pakistan Worked as a Safety Engineer having the following responsibilities

- Monthly & Weekly Departmental Safety & HSE NC Reporting - Develop and share HSE awareness materials and Procedures - Analyze and monitoring Operation & Maintenance Safety

Data & Procedures - Coordinate and train workmen for Safety Requirement - Review and comments on safe work Procedure and Method

of Statement (MOS) - Carryout Risk Assessment and control PTW system - Assists in HSE meetings, bulletins and publications

Page 71: Company profile[1]

HHAAMMMMAADD HHAAKKEEEEMM

Page 6 of 5

- Implement and Monitor effectiveness of SOPs - Carry out HSE Audits and Inspection and closing out of

corrective actions. - To conduct “Job Specific” Trainings - Coordinate for the collection and proper disposal of waste as

per regulatory requirements. - Create awareness among workforce regarding WMP

implementation

Page 72: Company profile[1]

MMUUHHAAMMMMAADD IIMMRRAANN CCHH..

Page 1 of 4

Designation : In-charge Plant and Equipment

Date of Birth : April 1, 1979

Nationality : Pakistani

Education : B.Tech(Hons) Mechanical Power/Equal B.Sc. Mechanical Engineering, University of Engineering and Technology, Lahore – Pakistan, 2003

B.Tech(Pass) Mechanical Power, University of Engineering and Technology, Lahore – Pakistan, 2001

Diploma of Associate Engineer: Mechanical Power, Lahore – Pakistan, 1997

Years of experience : Twelve

With Ammico since : January 2011

SUMMARY OF EXPERIENCE

: Mr. Muhammad Imran is a highly capable In-charge Plant & Equipment. He has twelve (12) years experience in the field of managing the plant & equipment on completion of a number of large and medium scale projects involving installation of concrete diaphragm walls, concrete secant piles, cast-in-situ concrete piling, deep excavations and dewatering.

PRACTICAL EXPERIENCE

Jan-2014 to Present July 2013 – Dec 2013 Jun 2013 – Dec 2013 Feb 2013 – Jun 2013

AMMICO CONTRACTING CO. W.L.L., DOHA Qatar Integrated Railway Project – Major Station – Scope of work for the project included:

- Installation of diaphragm wall - Installation of ground anchors

Construction of Lusail Tower, Com-11, Lusail, Qatar. In-charge Plant & Equipment for the project. Scope of work for the project included; installation of soldier piles as shoring system for a length of 70lm and 351 nos. working piles with diameters of 600mm to 1200mm. Re-work Package for Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) In-charge Plant & Equipment for the project. Scope of work for the project includes design and installation of removable ground anchors for a previously installed diaphragm wall 550lm in length. T.J Pearl Mansion, Isola Dana, The Pearl Qatar. In-charge Plant & Equipment for the project. Scope of work for the project includes 80,500 m3 excavation, dewatering and installation of 640mm thick and 11m deep cantilever diaphragm for a length of 785lm. It also includes 659 nos. of working piles with 400-600mm diameter and 4-10m depth.

Page 73: Company profile[1]

MMUUHHAAMMMMAADD IIMMRRAANN CCHH..

Page 2 of 4

Jan 2013 – Present

Jan 2013 – Present

Sep 2012 – Jan 2013 Jan 2012 – Present Nov 2012 – Mar 2013 July 2012 – Jan 2013 June 2012 – Jan 2013

Aug 2011 – Dec 2012

Jul 2011 – Mar 2013 Dec 2010 – Jun 2011 EXPERIENCE PRIOR TO JOINING AMMICO Aug 2008 – Dec 2010

Doha Oasis Mixed Use Development, Musheireb In-charge Plant & Equipment for the project involving shoring system, piling and excavation. Lookout Restaurant & SPA, Banana Island In-charge Plant & Equipment for the project involving offshore piling and sheet piling at Banana Island. Qatar Navigation Shipyard In-charge Plant & Equipment project involving dredging works under floating dock "Al Rufaa II" at Mesaieed Industrial City (MIC). Link Road to Pearl Lusail Expressway Package 1 In-charge Plant & Equipment project involving secant piling works, excavation disposal and backfilling for a no. of shafts. Residential Villa at Pearl Qatar for Mr. Omar Alfardan In-charge Plant & Equipment project involving installation of 203 nos. piles of diameter 800mm and length 11m and 56 piles of 1000mm diameter having length 12m. Al-Wahab Tower In-charge Plant & Equipment project involving installation and testing of preliminary test piles, installation of working piles, tests on working piles, shoring and excavation works. Le Boulevard Project @ Al Saad In-charge Plant & Equipment for the installation of 277m concrete diaphragm wall 22.5m depth having 17.5m deep excavation for four basement structure. Gas Sweetening Facilities (GSF) Project, Mesaieed Industrial City. In-charge Plant & Equipment for the installation of 43 no. 712 mm diameters of concrete piles, and a jetty marine works, including precast concrete decking, fabrication and installation. Doha Land Phase-2 & Phase-3 Project In-charge Plant & Equipment for the installation of 625m of concrete diaphragm wall to 18m & 23m depth, excavation to 13.7 & 17.2m below existing ground level for the 4 & 5 basements respectively, dewatering and installation of 900 mm, 1500mm & 1800 mm diameter piles. Earthworks, Shoring, Anchors & Soil Nailing Works at Sheraton Park Project, West Bay Doha. Incharge Plant & Equipment for the excavation of aprox. 1,100,000cum soil, backfilling of aprox. 250,000cum, installation of 605 Lm of secant pile wall, 241 Lm of Contiguous Pile wall, 380 no. of anchors and installation of 1700 no. soil nails. Al Jar Cranes & Equipment L.L Doha Qatar (CCIC) Engineer Heavy Machinery Work Shop. PMV (Plant,

Page 74: Company profile[1]

MMUUHHAAMMMMAADD IIMMRRAANN CCHH..

Page 3 of 4

Mar 2006 – Aug 2007 May 2005 – Mar 2006 Jun 2004 – May 2005 Apr 2003 – Apr 2004

Machinery & Vehicle)In-charge Plant & Equipment for the workshop department for day to day activities, providing various projects with cranes and heavy equipment & plant and tools. Co-ordinate the work of subordinate staff and work effectively with the order executive and departmental manager, to ensure effective completion of work and achievement of departmental objectives and targets. Monitor cost effectiveness of all plant operations following consultation with subordinates, analysis of information and make approval, changes to achieve performance. Descon Engineering Limited Project description: Kachhi canal Project KC-03 5009, &50 km Road Contrcution. Engineer Heavy Machinery Work Shop. PMV (Plant, Machinery & Vehivle)(I/C E&P): Management of all types of Construction equipment such as Earth moving equipment (Dozers, Excavator, Loader, Dumper, Compaction Roller) Management of all type of power producing equipmants. Management of all type of Batch Plant and Crush Plant. Ms. Volvo Pakistan Limited Service Engineer. PMV (Plant, Motor, Vehicle) Fast running repair. Implementation of plan and preventive program. Ensuring daily checking Handling the warranty cases. Ms. Imperial Electrical Company Assistant Service Engineer Handling the field service and overhauling team for timely repair and maintenance of different types of generators set like Duets, Puma, caterpillar, Cummins of different rating (25KVA TO 1250 KVA). Worked on installation and commission of different type of generator at many sites also in Govt. Departments. To prepare and implementation of annual plan and preventive maintenance for annual maintenance contract sets. To prepare estimation cost of major top overhauling of diesel engines also include top over hauling, intermediate overhauling. To prepare and control the store inventory of spare. Ms. Japan Power Generation Limited (135 MW) Trainee Engineer To test and trial of different types of Furnace/Diesel Genset. To manage the mechanical maintenance team to rectify the problem in engine and also make strategic regarding preventive maintenance.

Page 75: Company profile[1]

MMUUHHAAMMMMAADD IIMMRRAANN CCHH..

Page 4 of 4

Mar 1998 – Jul 1999 Aug 1999 – Feb 2000 Feb 2000 – Jun 2000

Ms. US Apparel and Garments (Pvt) Ltd Plant In charge To install all necessary connection and parameter before operation of Genset. To plan, repair and maintenance according to the manufacturer recommendation. To arrange timely fast running and overhauling parts. To coordinate the technical staff regarding maintenance issues. To Supervision of stitching/mechanical/electrical staff. To provide feedback to the technical Chief Manager. Ms. Pakistan Railway Supervise Industrial Training To get supervised training on different shops. Locomotive carriage and wagon shop. Testing and analysis of Fluid and material shop. Ms. Adamjee Diesel Engineering (pvt) Limited Supervise Industrial Training To perform job as Assistant Engineering Services. Training to handle parts & repair department.

Page 76: Company profile[1]

BBAALLAAJJII PPAATTTTAABBHHIIRRAAMMAANN

Page 1 of 5

Designation : Admin & Commercial Manager

Date of Birth : June 21, 1968

Nationality : Indian

Education : M. Com., University of Madras – India, 1991

B. Com., University of Madras – India, 1989

Years of experience : Twenty Four

With Ammico since : December 2005

SUMMARY OF EXPERIENCE

: Mr. Balaji is an outstanding manager with twenty four years experience in procurement, accounts, administration & Commercial. He has managed administration & Commercial for a number of large and medium scale projects involving installation of concrete diaphragm walls, concrete secant piles, cast-in-situ concrete piling, deep excavations and dewatering.

PRACTICAL EXPERIENCE Jan-2014 to Present Jan-2013 to Present July 2013 – Dec 2013 Jun 2013 – Dec 2013 Feb 2013 – Jun 2013

AMMICO CONTRACTING CO. W.L.L., DOHA Qatar Integrated Railway Project – Major Station –Musheireb Scope of work for the project included:

- Installation of diaphragm wall - Installation of ground anchors

Qatar Integrated Railway project – Metro 1 – Green Line Underground Scope of work for the project included:

‐ Installation of Diaphragm Wall Workas ‐ Installation of Soil Nailing and Shotcrete Work ‐ Installation of Anchoring Works ‐ Piling works ‐

Construction of Lusail Tower, Com-11, Lusail, Qatar. Administering the project in the capacity of Admin and Commercial Manager. Scope of work for the project included; installation of soldier piles as shoring system for a length of 70lm and 351 nos. working piles with diameters of 600mm to 1200mm. Re-work Package for Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) Administering the project in the capacity of Admin and Commercial Manager. Scope of work for the project includes design and installation of removable ground anchors for a previously installed diaphragm wall 550lm in length. T.J Pearl Mansion, Isola Dana, The Pearl Qatar. Administering the project in the capacity of Admin and Commercial Manager. Scope of work for the project includes 80,500 m3 excavation,

Page 77: Company profile[1]

BBAALLAAJJII PPAATTTTAABBHHIIRRAAMMAANN

Page 2 of 5

Jan 2013 – Present Jan 2013 – Present Aug 2011 – Dec 2012 Dec 2010 – Jun 2011 Jul 2009 – Feb 2010 Nov 2008 – Jul 2009 Jul 2008 – Jul 2009 Nov 2007 – Mar 2008

dewatering and installation of 640mm thick and 11m deep cantilever diaphragm for a length of 785lm. It also includes 659 nos. of working piles with 400-600mm diameter and 4-10m depth. Doha Oasis Mixed Use Development, Musheireb In the role of Administration & Commercial Manager for the project involving shoring system, piling and excavation. Lookout Restaurant & SPA, Banana Island. In the role of Administration & Commercial Manager for the project involving offshore piling and sheet piling. Gas Sweetening Facilities (GSF) Project, Mesaieed Industrial City. In the role of administration & Purchase Manager associated with the material purchasing for the installation of 43 no. of 712mm diameter concrete piles, and a jetty marine works. Earthworks, Shoring, Anchors & Soil Nailing Works at Sheraton Park Project, West Bay Doha. In the role of administration & Purchase Manager associated with the responsible for the excavation of aprox. 1,100,000 cum soil, backfilling of aprox. 250,000 cum, installation of 605 Lm of concrete secant pile wall, 241 Lm of Contiguous Pile wall, 380 no. of anchors and installation of 1700 no. soil nails. Al Quds Tower Project, West Bay, Doha (5B + G + 100) In the role of administration & Purchase Manager associated with the responsible for the installation of 670m of concrete diaphragm wall to 30m depth, excavation to 24m below existing ground level for the five level basement car park, dewatering and installation of 1200mm and 1500mm dia concrete piles for the hundred storey tower. Headquarters for The Energy City Qatar, Lusail (2B+G+M+2) In the role of administration & Purchase Manager associated with the responsible for the installation of 561m concrete diaphragm wall with 16m depth, excavation to 11m below existing ground level for the three level basement car park, dewatering and installation of 600mm, 900mm & 1200mm dia concrete piles for the building structure. Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) In the role of administration & Purchase Manager associated with the responsible for the installation of 550 meter concrete diaphragm wall to 22m depth, excavation up to 20m below existing ground level for five level basement car park, dewatering and installation of 1200mm and 1500mm dia concrete piles for the hundred and five storey tower. Woqod Tower Project, West Bay, Doha (4B + G + M + 30)

Page 78: Company profile[1]

BBAALLAAJJII PPAATTTTAABBHHIIRRAAMMAANN

Page 3 of 5

Nov 2007 – Feb 2008 Jul 2007 – Nov 2007 May 2007 – Nov 2008 Oct 2006 – Jun 2007 Jul 2006 – Oct 2006 Jul 2006 – Oct 2006 May 2006 – Jun 2006

In the role of administration & Purchase Manager associated with the responsible for the installation of 238m concrete diaphragm wall to 24m depth, excavation up to 21m below existing ground level for the four level basement car park, dewatering and installation of 900mm and 1200mm dia concrete piles for the thirty storey tower. The Pearl, Qatar, VB 11 & 17 – Viva Bahriya, for Dorrat Al Doha In the role of administration & Purchase Manager associated with the responsible for the installation of 600mm, 900mm and 1200mm dia concrete piles with 8m to 38m depth. 2000MW CCPP Project at Mesaieed “A” for Iberdrolla Engg In the role of administration & Purchase Manager associated with the responsible for the (a) installation of 545 nos 600mm and 415 nos 1000mm dia concrete piles of 22m depth for the main plant (b) installation of 135 m of concrete diaphragm of 19.5m depth for the pump house (c) excavation to 15.5m depth for the pump house (c) construction of the pump house structure. Doha Convention Center & Tower Project, West Bay, Doha (3B + G + 114) In the role of administration & Purchase Manager associated with the installation of 1600 meter concrete diaphragm wall up to 17m depth, excavation up to 21m under the tower footprint, excavation for the triple and double level basement car parks, dewatering, installation of 1500mm dia concrete piles for the hundred and fourteen storey tower and 900mm piles for the convention center. The Gate Development Project, West Bay, Doha (3B + G + 17) In the role of administration & Purchase Manager associated with the installation of 700m concrete diaphragm wall of 20m depth, excavation to 13m below existing ground level for three level basement car park, dewatering and installation of 900mm and 1200mm dia concrete piles. The Pearl, Qatar, Parcel 7A project at Porto Arabia for Al Darwish United Real Estate & Investment Co. W.L.L. In the role of administration & Purchase Manager associated with the installation of 500mm and 1200mm dia concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 13A & 13B projects at Porto Arabia for General Retirement and Pension Authority In the role of administration & Purchase Manager associated with the installation of 500mm and 1200mm dia concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 2A project at Porto Arabia for M/s.

Page 79: Company profile[1]

BBAALLAAJJII PPAATTTTAABBHHIIRRAAMMAANN

Page 4 of 5

May 2006 – Jun 2006 Jan 2006 – Dec 2006 Jan 2006 – Jun 2006 Dec 2005 – Feb 2006 EXPERIENCE PRIOR TO JOINING AMMICO 2004-2005 1997-2003 1993-1996

Ali AlfardanIn the role of administration & Purchase Manager associated with the installation of 500mm and 1200mm dia concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 8A project at Porto Arabia for M.s, Ali Alfardan and M/s. Jamil Mattar This project involved installation of 500mm and 1200mm dia concrete piles of 16m and 22m depth respectively. The Pearl, Qatar, Parcel 1, 2, 3, 4, 5, 10C, 14 and 18 projects for United Development Co. In the role of administration & Purchase Manager associated with the installation of 500mm, 600mm, 900mm and 1200mm dia concrete piles with depth between 12 to 28m for a large number of high rise towers and low rise structures at The Pearl Qatar. The Pearl, Qatar, Parcel 6 project at Porto Arabia for M/s. Sabban Property Investments In the role of administration & Purchase Manager associated with the installation of 500mm, 1000mm and 1200mm concrete piles with depths of 18m, 24m and 28m respectively. Dukhan Apartment Tower (B + G + 32) project at West Bay for H.E. Sheikh Meshal Al Thani This project involved installation of 600mm and 900mm dia concrete piles with depth of 10m and 12m respectively. Powerchip Technologies Chennai India Worked as Manager Administration and Accounts, was responsible to handle the entire accounts & administration, finance, sales & services of this global technical support company. Cromwell Tools India & Miranda Tools - Division of Nicholas Piramal India Ltd Chennai India Worked as Manager Administration and Accounts responsible for handling the regional accounts, administration and sales / marketing i.e. complete dealer network for Tamilnadu, Pondicherry & Kerala states. Reported to Head of Marketing at Mumbai. Miranda Tools - Division of Nicholas Piramal India Ltd., Bangalore, India Worked as Area Manager responsible for handling complete branch accounts including state Taxation. Implemented ISO 9001 and statutory requirements for Joint Venture with Cromwell Tools India. Reported to the Head of Finance & Accounts at Mumbai.

Page 80: Company profile[1]

BBAALLAAJJII PPAATTTTAABBHHIIRRAAMMAANN

Page 5 of 5

1990-1993 1987-1990 1986-1987

L M Van Moppes Diamond Tools (India) Ltd., Chennai, IndiaWorked as accounts officer responsible to coordinate marketing with production, planning, finance & accounts departments, debtors control and central excise. Reported to Head of Marketing. Karnataka Planters Coffee Curing Works India (Pvt) Ltd. Karnataka - India Worked as accountant responsible for curing works accounts and audit, wages disbursement, implementation of provident fund, ESIC and coffee board pool account maintenance. Reported to Chief Auditor / Executive Director. Kedia (India) Ltd Chennai - India Worked as accounts assistant responsible for branch accounts, invoicing and inventory control. Reported to Accountant/Branch Manager.

Page 81: Company profile[1]

SHEHZAD AKMAL

Page 1 of 3

Designation : Contracts Manager

Date of Birth : October 21, 1971

Nationality : Pakistani

Education : B-Tech Civil Engineering (Honors) - GOVT. COLLEGE OF TECHNOLOGI MULTAN

Diploma of associate Engineering civil

Years of experience : Nineteen Years

With Ammico since : Mar-2014

SUMMARY OF EXPERIENCE

: Mr.Shehzad Akmal is a highly capable Contracts Manager and has nineteen years experience in the field of civil engineering, building and fit out environment. Mr.Shehzad has joined Ammico in March 2014 as Contracts Manager and is responsible for all the contractual issues of the projects at tendering and execution stages.

PRACTICAL EXPERIENCE Jan-2014 to Present Jan-2013 to Present EXPERIENCE PRIOR TO JOINING AMMICO July-2004 to March -2014

AMMICO CONTRACTING CO. W.L.L., DOHA Mr.Shehzad in the capacity of Contracts Manager is responsible for contractual matters for the following projects: Qatar Integrated Railway Project – Major Station – Scope of work for the project included:

- Installation of diaphragm wall - Installation of ground anchors

Qatar Integrated Railway project – Metro 1 – Green Line Underground Scope of work for the project included:

‐ Installation of Diaphragm Wall Workas ‐ Installation of Soil Nailing and Shotcrete Work ‐ Installation of Anchoring Works ‐ Piling works

Descon Engineering Ltd. Position- Sr. Estimator (Civil, Mechanical & Elect.) Cost Control Engineer/In charge commercial

Projects Rehabilitation/Modernization of Jihan Barrage Distt.

Mianwali

Page 82: Company profile[1]

SHEHZAD AKMAL

Page 2 of 3

July-2000 to July-2004 June-1995 to June-2000

Asphalt Blowing Unit 15000TPD Distt. Muzaffer Garh. 2194 MTPD Ammonia and 3835 MTPD Prilled Urea at

Engro City Daharki. Maple Leaf Cement Factory Phase II, 6700 TPD Distt.

Mianwali. Rehmat Gas Field Project Distt Ghottki. Lukky Cement Factory at Pezzo. 2*210Mw Thermal Power Station Muzaffar Garh.

Hyundai Engineering & Construction Co. Position- Sr. Quantity Surveyor (Civil, Mechanical & Elect.)

23 X 8MW Chashma Hydropower Project Distt. Mianwali.

Head Office at Lahore. Habib Rafiq (Pvt.) Ltd.

Position- Quantity Surveyor D-Point Car Parking Plazza Shah-alam Market Lahore.

CICL-Polyacrylic Fiber Plant at Karachi. 2*364Mw Thermal Power Station Muzaffargarh.

RESPONSIBILITIES

Fully understanding the Contract documents and

Projects specification. Solve the Contractual matters with consultant and contractor.

Working in Proposal department and made bids for different Project specially by bidding software.

Responsible for development of method statements for the calculating quantities (Civil Mechanical & Electrical) and proposal for rectification and create an atmosphere of communication between client, Engineer and contractor. Attending meetings with consultant and contractor for technical matters relating to IPC.

Monthly Project analytical study Report. Responsible to accurately determine BOQ and Prepare

monthly interim payment certificate (Civil Mechanical & Electrical) and have to check it from consultant and client.

Responsible for direct/Consumable material requirement for the project from the Project drawings and compare it with the project budget.

Monthly basis update the project budget with the actual cost.

Verify quantities achieved by the sub-contractors. (Fully responsible total project sub-contracting.)

Calculate the Earthwork Volume by Eagle Point Road Cal.

Page 83: Company profile[1]

SHEHZAD AKMAL

Page 3 of 3

Calculate the piping dia inches according to pipe

specification including insulation and painting. Preparation Bar Bending Schedule from Reinforcement

drawing. Compare Construction Drawings with Tender Drawings. Prepare realistic plans (P3) for execution, to critically

monitor execution and to suggest appropriate and timely corrective action for achieving of project objectives.

To prepare base plane at P3 of different project from basic information (Tender drawings, BOQ, Mechanical delivery status) of initial stage of project only quantity and man-hours base.

Responsible for Procurement of all type of material of total project.

Negotiate the rate with sub-contractor/suppliers

Page 84: Company profile[1]

MUHAMMAD RAMZAN SAQIB

 

 Page 1 of 4 

 

Designation : Asst. General Manager

Date of Birth : January 7, 1967

Nationality : Pakistani

Education : M.Com - University of the Punjab, Lahore – Pakistan

Years of Experience : 23 Years

With Ammico since : June 2008

SUMMARY OF EXPERIENCE

: Mr. Ramzan is finance & accounts professional with over 22 years experience at different levels of a large organization. Currently heading HR and Admin division of Ammico Contracting. Core responsibilities include the financial management of the Ammico Contracting Co W.L.L.

PRACTICAL EXPERIENCE

AMMICO CONTRACTING CO. W.L.L., Doha, Qatar

Jan‐2014 to Present     Jan‐2013 to Present       July 2013 – Dec 2013       Jun 2013 – Dec 2013    Feb 2013 – Jun 2013  

: : : : :

Qatar Integrated Railway Project – Major Station –Scope of work for the project included: 

- Installation of diaphragm wall - Installation of ground anchors 

 Qatar Integrated Railway project – Metro 1 – Green Line Underground Scope of work for the project included: 

‐ Installation of Diaphragm Wall Workas ‐ Installation of Soil Nailing and Shotcrete Work ‐ Installation of Anchoring Works ‐ Piling works 

 Construction of Lusail Tower, Com‐11, Lusail, Qatar. Asst. General  Manager Scope of work for the project included; installation of soldier piles as shoring system for a length of 70lm and 351 nos. working piles with diameters of 600mm to 1200mm.  Re‐work Package for Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) Managing the project in the capacity of Asst. General Manager. Scope of work for the project includes design and installation of removable ground anchors for a previously installed diaphragm wall 550lm in length. T.J Pearl Mansion, The Pearl Qatar Responsible for the finance and accounts for the project inolving shoring works (diaphragm wall), excavation works down to formation level & disposal of excavates materials, dewatering, piling works & pile head

Page 85: Company profile[1]

MUHAMMAD RAMZAN SAQIB

 

 Page 2 of 4 

 

Jan 2013 – Dec 2013 Jan 2013 – Dec 2013 Nov 2012 – Jan 2013 Sep 2012 – Jan 2013    Jan 2012 – Dec‐2013  July 2012 – Jan 2013   June 2012 – Nov 2012 Sep 2011 – Jun 2012 Aug 2011 – Nov 2012 Jul 2011 – Nov 2012

: : : : : : : : : : :

breaking to foundation level and testing of piles. Doha Oasis Mixed Use Development, Musheireb Responsible for the finance and accounts for the project involving shoring system, piling and excavation. Lookout Restaurant & SPA, Banana Island Responsible for the finance and accounts for the project involving offshore piling and sheet piling at Banana Island. Residential Villa at Pearl Qatar for Mr. Omar Alfardan Responsible for the finance and accounts for the project involving installation of 203 nos. piles of diameter 800mm and length 11m and 56 piles of 1000mm diameter having length 12m. Qatar Navigation Shipyard Responsible for the finance and accounts for the project involving dredging works under floating dock "Al Rufaa II" at Mesaieed Industrial City (MIC). Link Road to Pearl Lusail Expressway Package 1 Responsible for the finance and accounts for the project involving execution of secant piling works, excavation, disposal and backfilling for a no. of shafts. Al-Wahab Tower Responsible for the finance and accounts for the project involving installation and testing of preliminary test piles, installation of working piles, tests on working piles, shoring and excavation works. Le Boulevard Project @ Al Saad Contracts Manager for the installation of 277m concrete diaphragm wall 22.5m depth having 17.5m deep excavation for four basement structure. National Library, Education City Responsible for the finance and accounts for the installation of 438 no. of 500mm – 1200mm diameter of piles. Gas Sweetening Facilities (GSF) Project, Mesaieed Industrial City. Responsible for the finance and accounts for the installation of 43 no. of 712mm diameter of piles, and a jetty marine works. Qatar Faculty of Islamic Studies Responsible for the finance and accounts for the project which involves installation of 698 piles of 500mm – 1500mm diameter piles. Doha Land Phase-2 & Phase-3 Project

Page 86: Company profile[1]

MUHAMMAD RAMZAN SAQIB

 

 Page 3 of 4 

 

Jun 2011 – Mar 2013  Dec 2010 – Jun 2011 July 2010 – Aug 2011 Jul 2010 – Oct 2010 Jul 2010 – Oct 2010 Jun 2010 – Oct 2010 Jul 2009 – Feb 2010 Jul 2008 – Jul 2009 Jun 2007 – Nov 2008

: : : : : : : :

Responsible for the finance and accounts for the installation of 625m of diaphragm wall to 18m & 23m depth, excavation to 13.7 & 17.2m below existing ground level for the 4 & 5 basements respectively, dewatering and installation of 900 mm, 1500mm & 1800 mm diameter piles. Earthworks, Shoring, Anchors & Soil Nailing Works at Sheraton Park Project, West Bay Doha. Responsible for the finance and accounts for the excavation of aprox. 1,100,000 cum soil, backfilling of aprox. 250,000 cum, installation of 605 Lm of secant pile wall, 241 Lm of Contiguous Pile wall, 380 no. of anchors and installation of 1700 no. soil nails. Jetty Boil off Gas Recovery Project ( Qatar Gas) Responsible for the finance and accounts for the installation of piles dia. 600mm depth up to 8m. Lusail Development Sewage Treatment Works Responsible for the finance and accounts for the installation of secant piles, excavation & De-watering for shafts. 12 New Departure Gates Project at DIA Responsible for the finance and accounts for the installation of piles dia. 600mm and 750mm depth up to 8m. The Temporary Bearth at Marsa Arabia- The Pearl Qatar Responsible for the finance and accounts for the installation of temporary jetty at Marsa Arabia inside the Pearl Qatar. Al Quds Tower Project, West Bay, Doha (5B + G + 100) Responsible for the finance and accounts for the installation of 670m of concrete diaphragm wall to 30m depth, excavation to 24m below existing ground level for the five level basement car park, dewatering and installation of 1200mm and 1500mm dia concrete piles for the hundred storey tower. Qatar National Bank Head Quarters Building Project, West Bay, Doha (5B + G + 105) Responsible for the finance and accounts for the installation of 550 meter concrete diaphragm wall to 22m depth, excavation up to 20m below existing ground level for five level basement car park, dewatering and installation of 1200mm and 1500mm dia concrete piles for the hundred and five storey tower.. Doha Convention Center & Tower Project, West Bay, Doha (3B + G + 114) Responsible for the finance and accounts for the Installation of 1600 meter concrete diaphragm wall up to 17m depth, excavation up to 21m under the tower footprint, excavation for the triple and double level basement car parks, dewatering, installation of 1500mm dia concrete piles for the hundred and fourteen storey tower and 900mm concrete piles for the convention center.

Page 87: Company profile[1]

MUHAMMAD RAMZAN SAQIB

 

 Page 4 of 4 

 

Nov 2008 – Jul 2009 Oct 2008 – Mar 2009 Jun 2008 – Nov 2008 EXPERIENCE PRIOR TO JOINING AMMICO 1993 – 2008 1991 - 1993

:

Headquarters for The Energy City Qatar, Lusail (2B+G+M+2) Responsible for the finance and accounts for the installation of 561m concrete diaphragm wall with 16m depth, excavation to 11m below existing ground level for the three level basement car park, dewatering and installation of 600mm, 900mm & 1200mm dia concrete piles for the building structure. The Pearl, Qatar, VB-09 at Viva Bahriya, for Hamad Al Mana Responsible for the finance and accounts for the installation of 600mm, 900mm and 1200mm dia concrete piles for the tower structure. Cultural Village Commercial Plaza Car Park project at West Bay Responsible for the finance and accounts for the installation of 173m of concrete diaphragm wall and 600mm, 900mm and 1200mm dia concrete piles. Deputy General Manager Finance QARSHI Industries (Ltd) Lahore Pakistan Worked as Deputy Manager Finance. Was responsible for supervising the accounts, product costing & MIS. Also responsible for the administrative matters of the Finance Division, which is centrally located at Qarshi Head Office. Chief Accountant Sadoon Textile Industries Ltd. Lahore Pakistan Was responsible for Quarterly & annually Profit & loss accounts and balance sheet. Supervised accounts receivable & payables and bank reconciliation statement. Final approval of vouchers and checking & verification of salaries of the Staff.

Page 88: Company profile[1]

AMMICO COMPANY PROFILE  

10

Copies of Various Trade Licenses

Page 89: Company profile[1]
Page 90: Company profile[1]
Page 91: Company profile[1]
Page 92: Company profile[1]

•-\y•\

**1...*,..

I!J,..,....•""""""~"""""""..•"""

·J••+•••

-S-

0

I•

I

•..-

.-<

••..

--

•I

•I

I

Jj

Page 93: Company profile[1]
Page 94: Company profile[1]
Page 95: Company profile[1]

AMMICO COMPANY PROFILE  

11

Photo Gallery

Page 96: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

PILING WORKS FOR DOHA LAND PHASE 2 & 3, DOHA, QATAR

Page 97: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  INSTALLATION OF DIAPHRAGM WALL TO A DEPTH OF 26M AT DOHA LAND PHASE 2 & 3, DOHA, QATAR 

Page 98: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  INSTALLATION OF DIAPHRAGM WALL TO A DEPTH OF 26M AT DOHA LAND PHASE 2 & 3, DOHA, QATAR 

Page 99: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  BULK EXCAVATION FOR DOHA LAND PHASE 2 & 3, DOHA, QATAR

Page 100: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  PILING WORKS AT QATALUM PROJECT, MESAIEED, QATAR 

Page 101: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  DIAPHRAGM WALL & EXCAVATION TO A DEPTH OF 17M FOR DOHA CONVENTION CENTRE & TOWER PROJECT, DOHA, QATAR 

Page 102: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  ENABLING WORKS FOR DOHA CONVENTION CENTRE & TOWER PROJECT, DOHA, QATAR 

Page 103: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  ENABLING WORKS FOR QNB HEADQUARTERS, THE CORNICHE, DOHA, QATAR 

Page 104: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  ENABLING WORKS PACKAGE FOR AL‐QUDS TOWER, DOHA, QATAR 

Page 105: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  ENABLING WORKS PACKAGE FOR AL‐QUDS TOWER, DOHA, QATAR

Page 106: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  ENABLING WORKS PACKAGE FOR WOQOD TOWER PROJECT, DOHA, QATAR 

Page 107: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  ENABLING WORKS PACKAGE FOR WOQOD TOWER PROJECT, DOHA, QATAR 

Page 108: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  EXCAVATION WORKS AT DOHA FESTIVAL CITY, DOHA, QATAR

Page 109: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  EXCAVATION WORKS WITH DRUM CUTTER MACHINE AT QSTEC PROJECT, RAS LAFFAN, QATAR 

Page 110: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  EXCAVATION WORKS INSIDE DIAPHRAGM WALL TO A DEPTH OF 11M AT ENERGY CITY, LUSAIL, QATAR 

Page 111: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  DIAPHRAGM WALL WORKS TO A DEPTH OF 20M FOR THE GATE PROJECT, DOHA, QATAR 

Page 112: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  DIAPHRAGM WALL WORKS TO A DEPTH OF 20M FOR THE GATE PROJECT, DOHA, QATAR 

Page 113: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  INSTALLATION OF DIAPHRAGM WALL TO A DEPTH OF 77M AT NORTH JEDDAH PUMPING STATION, K.S.A. 

Page 114: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  EXCAVATION WORKS INSIDE DIAPHRAGM WALL TO A DEPTH OF 65M AT NORTH JEDDAH PUMPING STATION, K.S.A. 

Page 115: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  EXCAVATION WORKS INSIDE DIAPHRAGM WALL TO A DEPTH OF 65M AT NORTH JEDDAH PUMPING STATION, K.S.A. 

Page 116: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  EXCAVATION AND CIVIL WORKS FOR TANK FARM AREA, SHELL GTL PROJECT, RAS LAFFAN, QATAR 

Page 117: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  MARINE WORKS FOR MARSA ARABIA AT THE PEARL, QATAR

Page 118: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  INSTALLATION OF STEEL PILES FOR MARINE JETTY AT MESAIEED, QATAR

Page 119: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  DESIGN AND INSTALLATION OF SECANT PILE SHORING TO A DEPTH OF 20M SHAFT AT LUSAIL, QATAR 

Page 120: Company profile[1]

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  DESIGN AND INSTALLATION OF SECANT PILE SHORING TO A DEPTH OF 20M SHAFT AT LUSAIL, QATAR 

Page 121: Company profile[1]

AMMICO COMPANY PROFILE  

12

ISO & OHSAS Certificates

and Company Policies

Page 122: Company profile[1]
Page 123: Company profile[1]
Page 124: Company profile[1]
Page 125: Company profile[1]
Page 126: Company profile[1]

AMMICO COMPANY PROFILE  

13

Safety Awards

Page 127: Company profile[1]
Page 128: Company profile[1]
Page 129: Company profile[1]
Page 130: Company profile[1]
Page 131: Company profile[1]
Page 132: Company profile[1]
Page 133: Company profile[1]