Pune Ring Road• To avoid traffic congestion in the city it is necessary to have a ring road for Pune.

•Decision taken in the meeting conducted by Hon’ble Chief Minister on 12/06/2007.

•Pune and Pimpri – Chinchwad Municipal Corporation to make necessary provision in their Development Plan.

•PWD to implement the project on BOT basis.

Page 3: 04. Ring Road Proposal

Ring road alignment• Survey of following stretches of ring road

undertaken.• Part I – Theurphata NH9, Kesnand, Wagholi, Bhavdi,Tulapur, Alandi,

Kelgaon, Chimbli, NH50.

• Part II – NH50, Chimbli Moi, Nighoje, Sangurde, Shelarwadi, Chandkhed, Pachne, Pimploli, Rihe, Ghotawde, Pirangutphata.

• Part III – Pirangutphata, Bhugaon, Chandni Chowk, Ambegaon, Katraj.

• Part IV – Ambegaon, Katraj, Mangdewadi, Wadachiwadi, Holkarwadi, Wadkinaka, Ramdara, Theurphata, NH9

Page 4: 04. Ring Road Proposal

Proposed Ring road - Map

Page 5: 04. Ring Road Proposal

• Detail survey of Part I , II and IV completed.

• Presentation was made on 19.04.2008. As Part III and IV are very close to the city limits considering rapid growth of city

• Revised Alignment based on toposheets and google earth images for Part III & IV is considered.

Page 6: 04. Ring Road Proposal

Alignment DetailsPart I Theurphata NH9, Kesnand, Wagholi,

Bhavdi,Tulapur, Alandi, Kelgaon, Chimbli, NH50.

39.89 km

Part II Chimboli phata to Nighoje to Sangurde, Shelarwadi, NH4, Shirgaon, Chandkhed, Rihe, Ghotawde, Pirangut

46.40 km

Part III

Pirangut, Urwade, Mutha Bahuli, Sangrun, Nigde, Khamgaon, Ghera Sinhgad, Kalyan, Kondanpur, Shriramnagar

51.20 km

Part IV

NH4 , Gogalwadi, Patharwadi, Bhivri, Kanifnath, New Mula – Mutha canal, Theurphata, NH9

32.24 km

After the alignment of Part III & IV is finalised detail survey work will be undertaken.

Page 7: 04. Ring Road Proposal

Acquisition Proposed

• Ring road length 169.73km

• Land Acquisition cost Rs. 2374.00 crores

• Construction cost Rs. 6065.00 crores

• Total cost Rs. 8439.00 crores.

• Satelite townships in 38.38km stretch in balance width of 200m (expected area 8,25,93,760 sq.ft) – by giving FSI of 1.0 + additional 1.0 = 2.0 the expected revenue Rs. 9228.00 crores.

Page 8: 04. Ring Road Proposal

Approx. estimates• Acquisition is proposed for 38.38km length – 300m width, 121.12km

length – 100m width and 10.44km length – 45 to 60m.

• Acquisition cost - Rs. 2374 crores.

• Construction cost – Rs. 6065 crores.

• For the stretch of 38.38km road length acquisition is proposed for 300m width and the width balance after that required for road i.e. 200m will be developed with additional FSI of 1.0 over and above existing 1.0 FSI to make the project financially viable.

• State Govt. to approve the project on a PPP model without toll alongwith concession of extra FSI.

Page 9: 04. Ring Road Proposal

Details of Ring roadName of the Road Length

in mFlyovers Majo

r bridges length in m

Minor bridges length in m

Viaducts bridges length in m

Under pass length

Tunnels length in m

Elevated road

Land Acquisition

Road Length in m

Railway length in m

100 m width area in hectares

300m width road area in hectares

1 2 3 4 5 6 7 8 9 10 11 12 13 14

1 ¦Part I – Theurphata, NH9, Kesnand, Wagholi, Bhavdi, Tulapur, Alandi, Kelgaon, Chimbli, NH50

39.89 650 300 490 450 1260 2750 355 132

2 ¦Part II – Chimboliphata to Nighoje to Sangurde, Shelarwadi, NH4, Shirgaon, Chandkhed, Rihe, Ghotawde, Pirangut.

46.400 160 200 850 300 630 120 650 3490 242.6 695.8

3 Part III – Pirangut, Urwade, Mutha Bahuli, Sangrun, Nigde, Khamgaon, Ghera Sinhgad, Kalyan, Kondanpur, Shriramnagar.

51.200 1850 1520 300 3070 90 2928 425 255.00

4 Part IV – NH4, Gogalwadi, Patharwadi, Bhivri, Kanifnath, New Mula – Mutha canal, Theurphata, NH9

32.240 500 150 150 2250 980 8050 1200 203.0055.70

45.00

169.940 3160 650 2860 1200 5320 2960 120 11628 7440 1281.4 1116.8