Preparing for yourS/4HANA Migration
John Appleby
GM, Bluefin Solutions Inc.
Brian S. Freed, CFA
VP, In Memory Architecture, SGI
• S/4HANA Introduction Differences between Suite on HANA and S/4HANA
Deployment Options
• Preparing for your S/4HANA Migration Building an integrated schedule
Sandboxing and prototypying
Housekeeping & Solution Manager
Change Management & Test Management
Sizing, Architecture, HA, DR, Backup & Recovery
What you will learn today
2
• The next version of SAP Business Suite
• New SKU and Code Fork Only supported with the SAP HANA DB
• S/4HANA themes: Renewed interface with Fiori UX
Simplified structure with SAP HANA
Cloud deployment first
What is S/4HANA
4
S/4HANA Deployment Options
5
Public Cloud
• Shared HANA multi-tenant DB
• HANA Cloud Platform Extensions
• Quarterly Release Schedule
• 100% Managed by SAP
• Automatic Updates
Managed Cloud
• Managed HANA DB and network
• HANA Cloud Platform Extensions
• ABAP Customization
• Quarterly Release Schedule
• 100% Managed by SAP
• Scheduled Updates
On-Premises
• On-Premises or Hosted
• ABAP Customization
• Yearly Release Schedule
• Managed by Customer/Partner
• Update schedule defined by customer
SAP S/4HANA Roadmap
6
http://www.sap.com/bin/sapcom/en_us/downloadasset.2015-03-mar-02-23.sap-s-4hana-frequently-asked-questions-pdf.bypassReg.html
SAP S/4HANA Customer Journey
7
http://www.sap.com/bin/sapcom/en_us/downloadasset.2015-03-mar-02-23.sap-s-4hana-frequently-asked-questions-pdf.bypassReg.html
• Most Customers look for a technical migration first To S/4HANA or Suite on HANA
• Out of Scope: HANA Live / Analytics
Simple Finance (i.e. S/4HANA)
• Suite on HANA is the stepping stone to S/4HANA Then perform code changes, activate S/4HANA extensions
• S/4HANA direct migration expected late 2015 N.B. Migrating to SoH is a great first step to S/4HANA!
Project Scope
9
• Cover all Technical Migration activities Upgrade to ECC 6.0 EhP7 (if necessary)
Unicode Conversion (if necessary)
HANA Migration
• Restitution “As fast, faster, or much faster”
ABAP code optimization (some things will be slower)
Technical Scope
10
ECC EHP 7 Upgrade
ECC to HANA MIgration
Future Projects
ECC on HANA
• Build one Integrated Schedule Weekly goals
• Include all teams above And partners!
Assign ownership
• Agree schedule with all teams Takes time (1-2 weeks)
Aligns with project prep phase
The Integrated Schedule
11
Who is involved?
12
Functional
PMOBasis
ReleaseManagement
BW/Analytics
Integration
ChangeManagement
TestManagement
Business Owners
Sponsors
ABAP
Infrastructure
EnterpriseSecurity
SAPSecurity
• Build first sandbox immediately Recent production copy
Production sized!
Include integration environment (if possible)
• Include test cycle Unit testing
Integration testing
Performance/Stress testing
Sandboxes & Prototyping
13
• Production-sized hardware Loan hardware
Try & Buy programs
• Use the hardware vendor you plan Plan to keep the hardware
Hardware Options for Sandbox
14
• Business Suite systems often venerable Housekeeping is not always done
A clean system is #1 way to de-risk your project!
• DRAM is expensive! Basis tables alone cost ~150GB of DRAM below
Multiplied by N production sized systems! TB!
• Run HANA sizing guide SAP Note 1736976 (BW)
SAP Note 1793345 (ECC)
Look for Big Basis Tables
SAP Note 706478
• Include in Schedule
Housekeeping
15
• Disk Databases are inexpensive Data Reduction rarely considered
• Top 100 tables usually 90% of DB space Run HANA sizing guide
SAP Note 1736976 (BW)
SAP Note 1793345 (ECC)
• Analyze Top 100 tables Create action plan
PSA, DSO Change Log deletion (BW)
IDOC, Old Functional Areas, Data Archiving (ECC)
• Remember every GB saved is 10-20GB stored!
Data Reduction
16
• Test Management is critical Some customers have a mature strategy
Some do not
• Revise your test management strategy Test Automation
Test Coverage
Test Prioritization
• Reduce your time to complete testing! How long does it take to complete regression test?
Change Management & Test Management
• Make sure you are on the latest latest SP! http://scn.sap.com/community/abap/custom-code-management
• Custom Code Management Tools (CCMT) Custom Code Management Cockpit (CDMC)
Usage & Procedure Logging (UPL)
CloneFinder
• Use these tools in combination with: Testing
Process prioritization by business users
Solution Manager is your friend!
18
TestStrategy
Priority
Testing
Clones CDMCUPL
• Complete Sizing Sandbox system is a great way to size accurately
Sizing tools are good alternative
• Consider technical architecture HANA supports database multi-tenancy
Architecting for S/4HANA
• HANA supports system replication Active/Passive Synchronous (HA)
Multi-tier Asynchronous (DR)
SUSE Linux supports automated host failover
• Very low cost to implement As compares to e.g. RAC
Most HANA systems are HA
• Even lower cost options Share QA & DR
Architect for HA/DR
Seamless Single-Node Scalability
21
4 Socket (3TB)*Available Today!
4-Socket Units
8 Socket (6TB)*Available Today!
16 Socket (12TB)*Controlled Availability
Planned Q2:15
32 Socket (24TB)*Co-Innovation Effort with SAP
on-going
Backup Storage+ *timing is subject to change+Scale Kit
+Scale Kit
UV for SAP HANA Scales as ONE and the same Single Node*
• SGI supports in-place upgrades
• CPU Ivy Bridge-EX (today)
Haswell (expected H2 2015)
Broadwell (future)
• DRAM DDR-3 (today)
DDR-4 (future)
Most HANA systems are HA
• Preserve Customer Capex
Architect for the future
Architect for resilience
System Data path checking (including single bit
correct)
Firmware provisioning
Redundant chassis controllers
FRU failure analysis
Online diagnostics
Uptime management
Interconnect LLP, CRC and retry support
Hot connect / disconnect
Lane failover and redundant routing
Dynamic reconfigurations
Alpha immune latches
Processors Dynamic and boot time isolation
Memory DRAM failure analysis
Page migration
Boot time disable
Tiered failure containment
Power and
Cooling
Redundant, hot-swappable power
supplies and cooling fans.
Redundant line cords
Online fault detection and ACPI support
Extending Intel® Xeon® RAS, SGI UVTM also provides the following :
• Enabling customer adoption in partnership Customer looking to build the business case for SAP HANA
SAP providing the trial product
SGI providing loan hardware
Bluefin providing migration services
• Quickly complete a SAP HANA migration Benchmark before and answer and show success
Identify critical analytic processes which can be improved
Ensure any product concerns are alleviated
• Build the business case to move ahead Accelerate adoption
S/4 Try & Buy Program
25
Recommended