Seahurst Project Update - March 17 presentation to City Council

Preview:

DESCRIPTION

This presentation was shared with the Burien City Council on March 17, 2014. It is an update regarding progress on the Seawall Removal and Beach Restoration Project at Seahurst Park. For more information about the project, visit www.burienwa.gov/SeahurstProject

Citation preview

SEAHURST PARKBEACH RESTORATION

PROJECT

Groundbreaking: September 16, 2013

Construction Phase Contractors

• USACE: Project Partner and Construction Management

• CKY Inc. : Prime Contractor (San Pedro, CA)

• SCI Infrastructure: Grading/Earthwork (SeaTac, WA)

• Cadman Inc.: Materials/Gravel/Sand (Redmond, WA)

• Northwest Lining and Geotextiles: (Kent, WA)

• Pacific Pile and Marine: Barge Services (Seattle, WA)

• Dutton Electrico Co.: (Lynwood, WA)

• Cal Portland: Concrete (Seattle, WA)

• Cherry Valley Logging: Wood materials (Duvall, WA)

• Play Creations: Playground (Burien, WA)

Park Closed: October 28, 2013

Project Footprint

Recap of Project Scope

Project Challenges withImpacts on Schedule and

Costs

• Underground cultural resource conditions

• Unknown utility conditions/ locations in specific areas

• New concrete work related to future recreational costs

New Concrete Work

UpdatedProject Schedule and Cost

• Original estimated date: May 17, 2014• Revised completion date: July 11, 2014

• Original estimated cost: $7.7M• Revised construction cost: $8.15M (+5.9%)

Source of Funds

State PSAR and $400,000ESRP Grants

Burien General Fund $50,000(add’l concrete work)

Project Funding Partners

• Army Corps of Engineers

• Washington Department of Fish and Wildlife (ESRP)

• Environmental Protection Agency (EPA)

• Salmon Recovery Funding Board (PSAR)

• King Conservation District

• Green-Duwamish Watershed Forum (WRIA-9)

• City of Burien