Boston college

Preview:

Citation preview

BOSTON COLLEGEHIGGINS HALL

Physics & Biology LabsAnimal Facility & Rooftop Greenhouse

2001

5 phase construction completed with the building fully occupied during all phases

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics, design development, construction documents , bid and award, construction and

closeout documentation.

BOSTON COLLEGEHIGGINS STAIR

2000

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics, design development, construction documents , bid and award, construction and

closeout documentation.

BOSTON COLLEGESports Complex Study

1996

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics, design development.

Unbuilt

BOSTON COLLEGEStudent Center Study

1996

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics and design development.

Unbuilt

BOSTON COLLEGELaw School Library

199684,450 Sq Ft

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics, design development, construction documents , bid and award, construction and

closeout documentation.

BOSTON COLLEGEFULTON HALL

Carroll School of ManagementComputer Labs

1995134,790 Sq Ft

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics, design development, construction documents , bid and award, construction and

closeout documentation.

BOSTON COLLEGEFULTON HALL

Carroll School of ManagementComputer Labs

1995134,790 Sq Ft

BOSTON COLLEGEALUMNI STADIUM

54,500 Seat Stadium1994

487,835 Sq Ft.

Demolition started in February and construction was complete for first game on September 14,

1994

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics, design development, construction documents , bid and award, construction and

closeout documentation.

BOSTON COLLEGEDEVLIN HALL

Geology LabsArt Department & Admissions

199392,618 Sq. Ft.

OwnerBoston College

Owner’s Project Manager during feasibility study, schematics, design development, construction documents , bid and award, construction and

closeout documentation.

BOSTON COLLEGEDEVLIN HALL

Geology LabsArt Department & Admissions

199392,618 Sq. Ft.

BOSTON COLLEGEMERKERT HALL

Chemistry Labs

1991117,791 Sq. Ft.