Waste Splitting - Differentiating ENERGY for profitability30 September 2014
WealthUnearthed
Roadmap
Geographical Location
Bambanani
Kopaneng
Simunye
K6
Kwezi
7mt/annum
475k oz
Background
PGM Prices
Production costs
Objective
• To optimise the blast design through effective ENERGY
distribution which will result in reef and waste separation during
blasting operations.
• To derive specific blast designs for specific reef conditions across
the 5 operating shafts and their sections.
• To maintain the ounce production of 475k oz for BP 15.
0g/t
Main Top 12.39g/t
Main Seam 4.56g/t
Main Bot 7.62g/t
Footwall 0 g//t
Leader 2.42g/t
Internal Waste
Methodology and Process
• Reef/Waste splitting was successfully trialled - March to May 2014.
• Safely blasted and loaded waste and reef separately during the trial
and waste packed in swept back areas.
• Logging of panels blasted (both reef & waste) completed – drilling
pattern, cast blasting, start & end time of loading, number of
buckets loaded etc. were recorded.
• A sampling & assay programme was conducted from the inception
of the trial to measure efficacy and results.
• On 30 April the K1 plant milled 8000 tons of only Kopaneng ore.
Blast Design
NOT TO SCALE
Drill Rig 10m x 2.1 & 2.5 (61 holes)
15 cm
50 cm
40 cm
1,3m
80 cm
75 cm
NOT TO SCALE
Drill Rig 10m x 2.1 & 2.5 (56 holes)
ENERGY Distribution
PF by 25% to 1.54kg/m³
PF by 100% to 1.10kg/m³
PF by 57% to 0.77kg/m³
Less is More !!!!
Proposed Typical Cycle
Rig 1
Rig 1
M/S
Drill panel & blast waste
Drill panel & blast waste
Cycle – 1st Shift - Drill Face & Blast Waste
Cast Blasting
Proposed Typical Cycle
Clean waste & blast reef
Clean waste & blast reef
A/S
Rig 1
Rig 1
M/S
Drill panel & blast waste
Drill panel & blast waste
Cycle – 2nd shift – Clean Waste & Blast Reef
“Drop & Pop”
Proposed Typical Cycle
Clean waste & blast reef
Clean waste & blast reef
A/S
Clean reef & Support panel
Clean reef & Support panel
N/S
Rig 1
Rig 1
M/S
Drill panel & blast waste
Drill panel & blast waste
Cycle – 3rd shift - Clean Reef & Support Face
Proposed Typical Cycle
Clean waste & blast reef
Clean waste & blast reef
A/S
Clean reef & Support panel
Clean reef & Support panel
N/S
Rig 1
Rig 1
M/S
Drill panel & blast waste
Drill panel & blast waste
Rig 2
Rig 2
Rig 3
Rig 3
Drill panel & blast waste
waste
Drill panel & blast waste
Clean waste & blast reef
Clean waste & blast reef
Clean reef & Support panel
Clean reef & Support panel
Drill panel & blast waste
Drill panel & blast waste
Clean waste & blast reef
Clean waste & blast reef
Clean reef & Support panel
Clean reef & Support panel
24 Hours
waste
Drill panel & blast waste
Drill panel & blast waste
Clean waste
blast reef
Clean waste & blast reef
Drill panel & blast waste
Drill panel & blast waste
Clean reef & Support panel
Clean reef & Support panel
Clean waste & blast reef
Clean waste & blast reef
Drill panel & blast waste
waste
Drill panel & blast waste
N/SA/SM/S
24 Hours
A Marked Blastface
Hangingwall Parting
Bottom Reef/Waste Parting Exposed
Benefits
Improved excavation integrity due to less ENERGY tr ansmitted into H/W
Improved excavation integrity due to less ENERGY tr ansmitted into H/W
Reef Fragmentation
Waste to be discarded in swept areas
Waste Packing Discipline
Base grade Proposed Head
Grade
Kopaneng
project gradesamples
Silo grade
samples
Strike belt
samples
Plant Recovery Tail grade
2.23
2.9
3.413.57
3.88
>80% 0.77
0.47
Grade Improvement
Reduced drilling costs and time per panelAllows for 2 additional panels to be drilled
Reduced explosives costs – R1.5m
Reduced hoisting costsLess pressure on maintenance
Reduced tramming costs
Reduced Plant costs – R45mImproved Grade
Reduced Tail grade Improved maintenance Scheduling
Benefits
• Original BP15 ore flow per shaft was used as base.• U/G waste packing was recalculated according to blast design
and ore flow was recalculated using BP15 parameters.
BP 20157,137,795 Tonnes Blasted
475,244 ounces
BP 2015 revised6,353,438 Tonnes Blasted
485,696 ounces
10% Less Waste Tonnes sent to the plant………..
10 450 More Ounces……….
R150m
Acknowledgement
Wessel PumoGM Kroondal Operations
Jan StrydomManager Projects Kopaneng
Brent ParkerManager Projects
Dave StarleyGM Projects
Team
Thank You
Wealth flows from ENERGY and ideas.William Feather