Power plant Siddhirganj 2x120 MW Peaking Power Plant

Electricity Generation Company Of Bangladesh Limited An enterprise of Bangladesh power

development board (BPDB)23.11.1996 registration Name was Meghnahat Power Company Ltd

(Private Limitrd )16.02.2004, Remaned: EGCB Ltd 15.01.2009: Public Limited Company

Vision “Generation of quality electricity for the

betterment of the nation”‘Fitness of use’1. Frequency2. Voltage 3. Reliability 4. Availability

Mission ‘to excel in electricity business by generation

efficient, reliability and cost effective electricity in an environmentally responsible manner to satisfy our customers’.

Plants Siddhirganj 2x120 MW PPPHaripur 412 MW CCPPSiddhirganj 335 MW CCPP

Siddhirganj 2x120 MW PPP

MD FAZLUI RHAMN(CE)124563 Lac TakaADB & GOB25 YEARS LIFE Bharat Heavy Electricals Limited (BHEL), IndiaSub contractor: Bengal Electric Limited (BEL) COD: 05.02.20122 GT, SIMPLE cycle Natural gas 4.17 acres 31%209.54 MW

Power Plant Gas Coal Oil WindSun Air/H2(fuel cell)Potential energy of water /hydro Tidal Geothermal Ocean wave Nuclear energy (natural or uranium dioxide enriched 3.2%

U235 )

Power plant Gas turbine Steam turbine Combine cycle power plant Solar plant Wind turbine Atomic power plant Cole power plant Hydro power plant /mini hydro

Gas turbine/open cycle

Advantages Quick start and synchronize to grid O&M easy Less manpower Operating cost low

Disadvantages Starting unit means starting motor, 1305 kw1800 rpm stop, self sustaining speed Compressor power requires Low output efficiency, exhaust high

temperature Combating chamber tem high, so life time

short

Component SMCOMPRESSOR GENERATOR GAS TURBINE TRANSFORMER

Maintenance CI=combustion inspection (flow slip, liner,

transition pitch), after 12000h HGPI= hot gas path inspection (flow slip,

liner, transition pitch, turbine blade, nozzle change generator bearing, turbine bearing, all sensor(tem, vibration) after 24000h )

MI= major inspection (Generator rotor decoupling , retaining ring, generator inspection with HGPI work )

Blade Nozzle

VID_20160830_103108.3gp

Siddhirgang 2X120 MW PPPGBC;2020KW, Induction motor 19-22=50MW Above 22 kg/cm2 require above 50-110MW Compressor 3 stage

One line diagram of Sid 2x120MW PPP

Generator turbine shaft

Transformer 2 GT(102/136/170MVA)2 MVUAT(10/12MVA)2 UAT (1.6MVA)2 SAT (2.5MVA)

Motors Induction (star/delta)(6.6KV, 415V, 230V)6.6KV(GBC, SM)De shunt motor (125V DC)

IA/PAPlant air(for cleaning)Instrument air (control pneumatic valve )Nitrogen (sealing, inert gas , purging )

Chiller Cooling purpose Administrative building Center control room

Switch gear Air CB Vacuum CB SF6 GCBFuse Relay

Switchyard CT PT Isolator

Safety Fire protection system Heat detector Smoke detector UV detector Water system

Water treatment system Input : river water Port able water DM water

employeesEngineers Finance Acc.HRStaffsTechnicalSecurity