Wellesley Campus Renewal Master Planning: A Better Way?
Since 1972
Jon Alvarez, AIA, NCARB - Capital Program Director, Aramark Engineering SolutionsJames Vermeulen, PQS, LEED AP – Co CEO, Vermeulens
Melissa Chabot, LEED AP – Project Manager, Vermeulens
North America’s Construction Economists Vermeulens.com
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
®
Service Beyond Estimation
2
AIA Continuing Education
Vermeulens is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members are available on request.
This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Wellesley Campus Renewal
3
Learning Objectives
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Wellesley College Campus Renewal Plan
Parallel Estimating and Reconciliation
Implementation Plan
Projecting Escalation
Funding Model
Outcomes 1 9 2 1 – W e l l e s l e y f r o m t h e a i r
Wellesley Campus Renewal
4
Big Picture Comparison to Traditional Master Plan
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Traditional Master Plan A Plan for Campus Renewal
One architect One architect per initiative and a sixth planner for a global look
Building siting and campus linkages Detailed programming with user groups
Possibly site mapping Produced detailed narratives, floor plans, and elevations
One estimator using traditional $/sf for building type
Two independent estimators
No parallel estimating process Produced detailed estimates in parallel with multiple options
Relied only on $/sf for building type Reconciled estimates in parallel
Use traditional project cost multipliers Developed detailed line item project costs
Long term escalation projected using construction trend line
Developed escalation based on the Boston market and experience of CM, CC and Wellesley College
Wellesley Campus Renewal
5
Wellesley College, Wellesley, MA
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Private, independent, four-year, liberal arts college for women founded in 1870
Mission to provide a liberal arts education, “for women who will make a difference in the world”
One of the most academically challenging, and diverse colleges in the country
1 9 3 4 – B e e b e F r e s h m e n
Wellesley Campus Renewal
6
Wellesley College, Wellesley, MA
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
2,300 undergraduate students from all over the world
500-acre bucolic campus, 2.5 million square feet of buildings
Located 12 miles from downtown Boston
1 9 3 1 – S t u d e n t s o n B i c y c l e s
Wellesley Campus Renewal
7
2007 Comprehensive Facilities Plan
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Observations:
Facilities problems resulting from a long-term pattern of underinvestment
60% of facilities hadn’t seen major renovation in more than 50 years
1 9 5 2 – B a t e s H a l l
Wellesley Campus Renewal
8
2007 Comprehensive Facilities Plan
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Observations:
Renewal backlog of $216/sf vs $78/sf average among peer institutions
Estimated construction cost of $370 million - 60% infrastructure and mechanical issues
1 9 6 4 – S t o n e - D a v i s R e c o n s t r u c ti o n
Wellesley Campus Renewal
9
2007 Comprehensive Facilities Plan
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Before spending $370 million on facilities renewal, the need to marry it with program delivery of the future became obvious
Current state of the facilities is impeding educational effectiveness, research, and the quality of campus life
1 9 7 3 – T o w e r C o u r t S u n d i a l
Wellesley Campus Renewal
10
2010 Program Planning Initiative was Born
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
President and Board of Trustees decided to significantly increase the allocation to campus renewal
Program issues to drive planning
Wellesley Campus Renewal
11
Wellesley College Campus Renewal Plan
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Ground up approach required specialists for each planning initiative
Five Planning Initiatives each with separate program planners
Initiative Architect
Student Residential Experience Newman Architects
Arts and Media Gund Partnership
Humanities Kliment Halsband Architects
Science and the Environment Ellenzweig
Wellness and Sports Cannon Design
Wellesley Campus Renewal
12
Wellesley College Campus Renewal Plan
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
“Study Buildings” represented 1.5 million sf of total 2.5 million sf campus
Student Residential Experience initiative comprised half of the 1.5 million sf studied
Wellesley Campus Renewal
13
Wellesley College Campus Renewal Plan
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Organization
This allowed the College to look at each initiative in detail, and on a parallel track within the time constraints specified(spring 2011 to spring 2013)
Trustee Committee
Steering Committee
Working groups and
sub-groups for each planning
initiative
Wellesley Campus Renewal
14
Wellesley College Campus Renewal Plan
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Output Report Conceptual Design Pricing Package including multiple options
Student Residential Experience
3 Dining Option
4 Dining Option
150 Beds/Year
300 Beds/Year
600 Beds/Year
Wellesley Campus Renewal
15
Wellesley College Campus Renewal Plan
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Hired a Sixth Planner to knit together the work of the Five Planning Initiatives
Consolidated Program Plan
(VSBA)
Student Residential Experience
Arts and Media
HumanitiesScience and
the Environment
Sports and Wellness
Wellesley Campus Renewal
16
Conceptual Design Pricing Package
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Substantially more documentation than traditional master plan
Existing Conditions Report
Conceptual Fit Plan Options
Scope of Work
Outline Specification
Building Areas: existing, proposed
Exterior Envelope Repairs
Schedule of Typical Finishes
MEP/FP Systems, Structural, & Code Narratives
Related Construction
FF&E
Wellesley Campus Renewal
17
Detailed Narratives
Approximate space requirement- At steam main service entrance a 20’ x 14’ mechanical room is required to house the steam prv, heat exchangers, pumps, expansion tanks, and appurtenances.- At each wing a 14’ x 24’ mechanical room is required for the residential ventilation AHU’s.- In general proximity of each kitchen, dining room, and program space, air handling unit mechanical rooms of 14’ x 28’ will be required to house the individual units.- Grease exhaust fans will require an 8’ x 8’ room preferably at the attic space or can be located exterior to the building.
Equipment-Preliminary size of instantaneous heating hot water heat exchanger to produce 2400 MBH @ 50 psi steam pressure.
Electrical SystemAdditional scope of work-Provide a single approximately 500 KVA pad mount exterior transformer for Munger.- Provide single interior 75KW generator for Munger Hall.
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Wellesley Campus Renewal
18N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Floor Plans
S c e n a r i o 3 - 1 A - R S M u n g e r ( 3 1 9 S e a t s )
Wellesley Campus Renewal
19
Cost Estimating
Cost Consultant - Vermeulens & Construction Manager - Turner Construction independently create construction estimates
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Wellesley Campus Renewal
20
Parallel Estimating and Reconciliation
Multi-day reconciliation meeting of CC, CM, Space Planner, and Wellesley College PM arrive at final construction cost
01 General Conditions $3,522,971 $3,158,939 ($364,032) -10%02 Site Work $1,263,292 $1,291,482 $28,190 2%03 Concrete $1,432,892 $1,402,290 ($30,602) -2%04 Masonry $734,445 $742,510 $8,065 1%05 Metals $483,451 $481,560 ($1,891) 0%06 Wood/Plastic $883,679 $897,840 $14,161 2%07 Thermal and Moisture Protection $991,247 $1,003,138 $11,891 1%08 Doors/Windows $2,873,880 $2,799,913 ($73,967) -3%09 Finishes $3,001,949 $3,006,860 $4,911 0%10 Specialties $312,565 $312,565 $0 0%11 Equipment $1,617,501 $1,617,501 $0 0%14 Converying Systems $270,000 $275,000 $5,000 2%15 Mechanical $4,679,742 $4,743,827 $64,085 1%16 Electrical $2,069,330 $2,126,564 $57,234 3%
$24,136,944 $23,859,989 ($276,955) -1%17 Permits and Fees $696,156 $613,144 ($83,012) -12%18 Contingencies $2,953,389 $2,623,103 ($330,286) -11%19 Overtime and Out of Hours $0 $0 $0 0%
$3,649,545 $3,236,247 ($413,298) -11%$27,786,489 $27,096,236 ($690,253) -2%
Direct Construction Costs
Total MarkupsTotal Construction Costs
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Wellesley Campus Renewal
21
Developing Detailed Project Costs
Wellesley College PM adds “soft costs” to create the Total Project Control Budget
Hazardous Materials FF&E Fees and Expenses Construction Contingency Program Contingency
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Wellesley Campus Renewal
22
Developing Detailed Project Costs
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Wellesley Campus Renewal
23
Reality Check
Detailed Program and Project Costs for 24 Buildings
Project Costs Range From $905 million to $1.4 billion (in 2012 dollars)
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Wellesley Campus Renewal
24
Reality Check
Timeline
Model to Calculate Escalation
Build a Funding Model/Determine Capacity
What can we afford?
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Wellesley Campus Renewal
25
Escalation
Escalation: relatively high construction escalation rate in the region is expected to persist
Over multiple years, escalation can have a major impact on how much the campus renewal program can accomplish
Delaying a renovation project by a year has the result of making it approximately five percent or more expensive
If project budget is not also increased, a delay reduces the scope that the project can accomplish
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Wellesley Campus Renewal
26
Escalation
The developed escalation model indicates the Base Plan actual expenditure will be $456.1 million
Applied escalation to each of five main components of Total Project Control
Budget over Project lifecycle
Fees & Expenses at time of Architect hire
Related Construction (including Hazmat abatement) one quarter before
construction start
Total Construction Cost at the commencement of construction
FF&E and Expenses at mid-point of construction
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Wellesley Campus Renewal
27
Recommendations
We will gladly organize, an in-depth AIA accredited presentation to the thought leaders in your office so you can find out the:
Contact your local Vermeulens liaison for a Presentation:
Wellesley College Campus Renewal Plan Parallel Estimating and Reconciliation Implementation Planning Projecting Escalation Funding Models and Opportunities
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Wellesley Campus Renewal
28
Why Vermeulens
Track Record
Project Volume & Benchmarking
Consensus Approach in Reconciliation
Market Outlook
Conceptual Estimating
Trusted Advisor
N o r t h A m e r i c a ’ s C o n s t r u c ti o n E c o n o m i s t
Wellesley Campus Renewal
North America’s Construction EconomistVermeulens.com
B o s t o n T o r o n t o D a l l a s D e n v e r L o s A n g e l e s
Thank You
Since 1972
Wellesley Campus Renewal Master Planning: A Better Way?
®