Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Jennifer Thompson, District 4 CommissionerStone Lakes Elementary School

March 3, 2011

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Planning, Design & Right-of-Way

Identified in Comprehensive Plan

Public/Private Partnership Agreement Approved by BCC

– Avalon & Associates: Design

– Morgran: Up-Fronted Cash & Ponds

Construction Plans Finalized 2009

Right-of-Way Acquisition Completed August 2010

Project History

Design Elements

10 Stormwater Ponds

4 Travel Lanes

Raised Grass Median

12,000 Feet of Retaining Wall

Project History

Utility Work

– Wastewater, Reuse, Water Mains

(Pipe Size Varies from 24” to 36”)

Design Elements

3 Signalized Intersections (One New)

No Landscaping or Lighting Due to Budgetary Constraints

Project History

Existing

Signal

Upgrade

Golfway Bv.

Existing

Signal

Upgrade

Innovation Way

New

Signal

Stoneybrook Bv.

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Construction

Bid Recommendation Approved – January 25, 2011

Contract Executed – February 11, 2011

Pre-Construction Conference – February 23, 2011

Notice to Begin – Effective March 21, 2011

Procurement and Construction

Construction

Construction Duration 2-1/2 Years

(September 2013)

County’s $19.6 Million Roadway Estimate: $11.1 Million Utilities

$30.7 Million Total

Procurement and Construction

Construction Bids:

Company Estimated Bid Amount

Jr. Davis $30,203,373

Halifax $31,042,574

Prince $33,359,946

Ranger $34,610,030

County’s $30,700,000

Estimate

Procurement and Construction

Alafaya Trail Project Update

Avalon Park Boulevard to Mark Twain Boulevard

Project History

Procurement and Construction

What to Expect

Mark Twain Boulevard

Avalon Park Boulevard

& Innovation Way

Alafaya Trail

3.8 Miles

Construction Phases

During the First 7-8 Months:

– Installation of Water Main, Force Main & Reuse Main

– Clearing and Stormwater Pond Excavation

– Temporary Lanes Constructed on the North Side for Utility Work & Stormwater Piping

• During the Next 6-7 Months

– Southbound Travel Lanes Begin Construction

– Two-way Traffic Moves from Temporary Lanes to Southbound Lanes When Complete

What to Expect

Construction Phases

During the Next 5-6 Months:

– Remaining Stormwater Piping Installed

– Northbound Travel Lanes Begin Construction

• During the Final Phase

– Structural Asphalt, Friction Course & Temporary/Final Pavement Markings Installed

What to Expect

Orange County Highway Construction

William Totten

Senior Engineering Inspector

407-836-7911

321-354-7330

Steven Stokes

Engineering Inspector

321-354-7395