Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT November 20, 2013

Preview:

Citation preview

Work Plan Development

Aschalew AberraHighway Utility Engineer, INDOT

November 20, 2013

2

Outline Learning objectives –why work

plan? Top five reasons why a work plan is

important What are the recent updates?

Target date, signing first or second page, emergency contact, pre-construction & post construction activity, etc.

Work plan development (Process): preparation, review, revision & approval.

Practical exercise

It is the Law! 105 IAC 13-3-3 (b) (1): A work plan shall be

submitted whether or not any facility relocations are required.

It is not a matter of opinion or an option, it is the LAW.

Utilities are obligated to submit their work plans in order to accommodate a highway improvement project.

Focus on deliverables Target out of conflict date.

Pre-construction schedule.

Construction schedule.

Relocation drawing.

Cost estimate & proof of property interest.

A signed commitment/contract

A work plan is a signed commitment by a utility to accurately relocate its facilities on schedule.

Projects are let based on information obtained from utility work plans.

A utility shall be held accountable, for utility related delay claims.

No surprises!

Work plan is a major tool to avoid surprises during construction.

The utility team shall demonstrate due diligence in reviewing & approving work plans.

Last chance before construction stage!

Use of work plan as an input Utility risk management report.

Gantt chart.

Utility special provision.

Utility coordination certificate.

A tool for resolution of scheduling and location conflicts

Preamble 105 IAC-13-2-9: Work plan is defined as a

plan of the utility to carry out facility relocation to accommodate an improvement project.

Use preliminary final project plan (Stage 3/90%).

Prepare and send letter Request Work Plan.

Use the most recent work plan template. Go to the INDOT website.

When is a work plan due? Sixty (60) days for a minor project; and

One hundred twenty (120) days for a major project.

An additional thirty (30) days will be allowed to furnish the work plan if coordination is required with another utility or utilities.

If a work plan is not received on time: contact the authorized representative and notify the oversight agent.

11

Work plan revision Non compatible work plans shall be returned

to the utility immediately.

The utility shall submit a revised work plan within 30 days.

If the revised work plan is not compatible, the UC will prepare an alternate work plan.

The utility shall accept/make changes to the alternate plan within 30 days.

12

Section 1: General Information

13

General info……cont’d

14

Section 2: Location info.

15

Section 3 & 4 Property interest & Work in

contract

16

Section 5: Pre-construction

17

Section 6: Construction

18

Section 7, 8, & 9: Attachments

$500,000.00 (Not Reimbursable)

19

Work Plan Review Ensure each work plan is

compatible with: INDOT permit requirements The project plans The construction schedule Other utility relocation work plans

Ensure the relocation scheme and cost for compensable work is reasonable

20

Section 10 & 11: Approval

21

Work plan addendums: Addendums can either be INDOT initiated or

utility initiated.

A utility shall submit a revised work plan with a new cost estimate (if reimbursable).

The utility coordinator shall review the addendum; and send it to the approval of the oversight agent.

If an addendum is issued during construction, a copy shall be sent to the construction engineer.

22Questions?

Questions?

Practical Exercise Group exercise

Identify 3 or 4 items that need to be corrected.

Recommended