Vilas Park Pedestrian Bridges Replacement Project

Mike Sturm, City of Madison Parks Division, Project Manager

Meeting Agenda• Project Location• Existing Conditions• Proposed Replacement Bridges and Approach Improvements• Next Steps

Vilas Park Pedestrian Bridges Replacement Project

Project Location

Lagoon

Vilas Park

Henry Vilas Zoo

Lake Wingra

Existing Shelter

Island

ExistingPlayground

ExistingTennis Courts

Project Location

Lagoon

Vilas Park

Henry Vilas Zoo

Lake Wingra

Existing Shelter

Island

ExistingPlayground

ExistingTennis Courts

North Bridge

Project Location

Lagoon

Vilas Park

Henry Vilas Zoo

Lake Wingra

Existing Shelter

Island

ExistingPlayground

ExistingTennis Courts

North Bridge

South Bridge

North Bridge – Existing Conditions

North Bridge – Existing Conditions

North Bridge – Existing Conditions

North Bridge – Existing Conditions

North Bridge – Existing Conditions

South Bridge – Existing Conditions

South Bridge – Existing Conditions

South Bridge – Existing Conditions

South Bridge – Existing Conditions

South Bridge – Existing Conditions

South Bridge – Existing Conditions

Replacement Bridge Design Criteria• Piling System• Abutment Design• Operational Standards• Load Requirements• Life Cycle Requirements• Accessibility

Vilas Park Pedestrian Bridges Replacement Project

Driven Pile Foundation System

Helical Pier Foundation System

Abutment Design

Operation Standards and Load Requirements

12 ft. Width

Accessibility Standards

North Bridge – Existing Path Approach

8% Slope

6.5% Slope

North Bridge – Proposed Bridge Alignment and Path Approach

North Bridge – Proposed Bridge Alignment and Path Approach

5% Slope

2% Slope

North Bridge – Proposed Angle‐Braced Bridge Structure

Pending

North Bridge – Proposed Angle‐Braced Bridge Structure

Pending

North Bridge – Proposed Angle‐Braced Bridge Structure

North Bridge – Proposed Cross‐Braced Structure

Pending

North Bridge – Proposed Cross‐Braced Structure

Pending

North Bridge – Proposed Cross‐Braced Structure

South Bridge – Proposed Bridge Alignment and Path Approach

13% Slope

8% Slope

South Bridge – Proposed Bridge Alignment and Path Approach

South Bridge – Proposed Bridge Alignment and Path Approach

5% Slope

5% Slope

South Bridge – Proposed Angle‐Braced Structure

Pending

South Bridge – Proposed Angle‐Braced Structure

Pending

South Bridge – Proposed Angle‐Braced Structure

South Bridge – Proposed Cross‐Braced Structure

Pending

South Bridge – Proposed Cross‐Braced Structure

Pending

South Bridge – Proposed Cross‐Braced Structure

Next Steps• Landmarks Commission Review• DNR Permitting• Construction Project Bidding• Construction and Site Restoration