View
219
Download
4
Category
Preview:
Citation preview
AFFORDABLE GROUP HOUSING COLONY(5 ACRES) LOCATED AT SECTOR 104,GURGAON, HARYANA By M/s. PERFECT BUILDWELL PVT. LTD.
(A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO.SEIAA/HR/2015/280 DATED 09.03.2015FORCONSTRUCTION OF
Sl. No. Conditions Status of Compliance
PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE:
1 “Consent to Establish” shall be obtained
from Haryana State Pollution Control
Board under Air and Water act and a
copy shall be submitted to the SEIAA
Haryana before the start of any
construction work at the site.
Agreed. Consent to Establish” has been
obtained from Haryana State Pollution
Control Board under Air and Water Act
Annexure 1.
2 A First Aid room as proposed in the
project report will be provided in both
during construction and operation of the
project.
Agreed. Construction work has just started
at site. Site pics have been attached as
Annexure 16. First Aid room has been
provided at the project site during the
construction phase and will be provided in
the operational phase , its picture has been
attached as Annexure 19.
3 Adequate drinking water and sanitary
facilities shall be provided for
construction workers at the site.
Provision should be made for the mobile
toilets. Open defecation by the laborers is
strictly prohibited. The safe disposal of
waste water and solid wastes generated
during the construction phase should be
ensured.
Agreed. It is assured that adequate drinking
water and sanitation will be provided for
workers at the site. In addition to it, mobile
toilets will be provided along with the
provision of septic tank & soak pit for the
disposal of wastewater.
1
4 All the top soil excavated during
construction activities should be stored
for use in horticulture/landscape
development within the project site.
Agreed. The excavated material will be used
for leveling, refilling and in horticulture/
landscape development within the project
site& surplus will be disposed off outside the
premises with consent to mixing department.
5 The project proponent shall ensure that
the building material required during
construction phase is properly stored
within the project area and disposal of
construction waste should not create any
adverse effect on the neighboring
communities and should be disposed off
after taking the necessary precautions for
general safety and health aspects of
people, only in approved sites with the
approval of competent authority.
Agreed. It will be ensured that the building
materials will be properly stored within the
project area and disposal of construction
waste will not create any adverse effect on
the neighboring communities. It will be
disposed off after taking the necessary
precautions for general safety and health
aspects of people, only in approved sites with
the approval of competent authority.
6 Construction spoils, including
bituminous material and other hazardous
materials, must not be allowed to
contaminate watercourses and the dump
sites for such material must be secured so
that they should not leach into the ground
water and any hazardous waste generated
during construction phase, should be
disposed off as per applicable rules and
norms with necessary approval of the
Haryana State Pollution Control Board.
Agreed. Construction spoils including
bituminous material and other hazardous
material will not be allowed to contaminate
the water courses. No dumping of such
materials will be allowed at project site.
Waste lubricating oil generated from
maintenance of DG sets falls under
hazardous waste category. Such wastes will
be disposed off with the help of waste
recycler with necessary approval from
Haryana State Pollution Control Board.
7 The Diesel generator sets to be used
during construction phase should be of
ultra-low sulphur diesel type and should
conform to Environment (Protection)
Agreed. Ultra-low sulphur diesel will be used
to run the Diesel generator sets to be used
during construction phase with Provisions of
Air and Noise Emissions Standards as per
2
Rulesprescribed for air and noise
emission standards.
EPA Rules, 1986.
8 The diesel required for operating DG sets
shall be stored in underground tanks and
if required, clearance from Chief
Controller of Explosives shall be taken.
Agreed. Used oil from DG sets will be stored
in HDPE drums in isolated covered facility.
This used oil will be sold to authorized
recyclers. Suitable care will be taken to avoid
spills/leaks of used oil from storage. Separate
log books will be maintained for
accountability.
9 Ambient noise levels should conform to
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be
closely monitored during construction
phase. Adequate measures should be
taken to reduce ambient air and noise
level during construction phase, so as to
conform to the stipulated residential
standards.
Agreed. Ambient noise level is within the
standard level prescribed by MoEF.
Incremental pollution loads on the ambient
air and noise quality are being closely
monitored. Laboratory data of the
environmental monitoring of air, noise and
soil carried out at the site are enclosed as
Annexure 17.
Similarly, Ambient air quality is also closely
monitored so as to conform to the stipulated
standards.
10 Fly ash should be used as building
material in the construction as per the
provisions of Fly Ash Notification of
September, 1999 and amended as on 27th
August, 2003.
Agreed. Fly ash Bricks will be used as
building material in the construction as per
the provisions of Fly Ash Notification of
September, 1999 and amended as on 27th
August, 2003.
11 Storm water control and its re use as per
CGWB and BIS standards for various
applications should be ensured.
Agreed. Storm water control and its re use
(for various applications) will be ensured as
per BIS and Central Ground Water Board
(CGWB) standards. Adequate number of
harvesting pits will be provided for control of
3
storm water.
12 Water demand during construction
should be reduced by use of pre-mixed
concrete, curing agents and other best
practices.
Agreed. Water demand during construction
will be reduced by the practice of using pre-
mixed concrete, curing agents and other
best practices.
13 In view of the severe constrains in water
supply augmentation in the region and
sustainability of water resources, the
developer will submit the NOC from
CGWA specifying water extraction
quantities and assurances from
HUDA/utility provider indicating source
of water supply and quantity of water
with details of intended use of water –
potable and non-potable. Assurance is
required for both construction and
operation stages separately. It shall be
submitted to the SEIAA and RO, MoEF,
Chandigarh before the start of
construction.
Agreed. Water Assurance for Construction as
well as for operation phase is attached as
Annexure 2&3.
14 Roof must meet prescriptive requirement
as per Energy Conservation Building
Code by using appropriate thermal
insulation material.
Agreed. Roof will be constructed as per
Energy Conservation Building Code.
15 Opaque wall should meet prescriptive
requirement as per Energy Conservation
Building Code which is proposed to be
mandatory for all air conditioned spaces
while it is desirable for non-air-
conditioned spaces by use of appropriate
thermal insulation material to fulfill
Agreed. Opaque wall will meet prescribed
requirement as per Energy Conservation
Building Code (ECBC).
4
requirement.
16 The approval of the competent authority
shall be obtained for structural safety of
the building on account of earthquake,
adequacy of firefighting equipment’s,
etc. as per National Building Code
including protection measures from
lightening etc. If any forest land is
involved in the proposed site, clearance
under The Forest Conservation Act shall
be taken from the competent Authority.
Agreed. The approval of the competent
authority will be obtained in due course of
time for structural safety of the buildings due
to earthquake, adequacy of firefighting
equipment, etc. as per National Building
Code including protection measure from
lightening etc. No forest land is involved in
the project site. NOC from Forest
Department has been obtained from Dy.
Conservator of Forest, Gurgaon vide letter
No. 2065-G dated 18.09.2014 and copy of
the same is enclosed as Annexure 4.
17 Overexploited groundwater and
impending severe shortage of water
supply in the region requires the
developer to redraw the water and energy
conservation plan. Developer shall
reduce the overall footprint of the
proposed development. Project
proponent shall incorporate water
efficiency / saving measures as well as
water reuse/ recycling within 3 months
and before start of construction to the
SEIAA, Haryana and RO, MoEF, GOI,
Chandigarh.
Agreed. Overexploited groundwater and
impending severe shortage of water supply in
the region requires the developer to redraw
the water and energy conservation plan.
Developer will reduce the overall footprint of
the proposed development. Project proponent
will incorporate water efficiency / saving
measures as well as water reuse/ recycling
within 3 months and before start of
construction to the SEIAA, Haryana and RO,
MoEF, GOI, Chandigarh.
18. The project proponents as stated in
proposal shall constructed 05 nos. rain
water harvesting pits shall be designed to
make provision for silting chamber and
removal of floating matter before
Agreed.5 numbers of RWH pits will be
provided with adequate design with silting
chamber after finishing the civil construction
work. RWH plan is attached as Annexure
9.
5
entering harvesting pit. Maintenance
budget and persons responsible for
maintenance must be provided. Care
shall also be taken that contaminated
water do not enter any RWH pit.
19 The project proponent shall provide for
adequate fire safety measures and
equipment’s as required by Haryana Fire
Service Act, 2009 and instructions issued
by the local authority/Directorate of fire
from time to time. Further the project
proponent shall take necessary
permission regarding fire safety
scheme/NOC from competent Authority
as required.
Agreed. Adequate Fire Safety measures and
equipment’s as per Haryana Fire Service Act,
2009 and instructions issued by the local
Authority/ Directorate of fire will be
provided. Necessary permission regarding
fire safety scheme/NOC from competent
authority is attached as Annexure 21.
20. The project proponent shall obtain
assurance from the DHBVN for supply
of 3500 KVA of power supply before the
start of construction. In no case project
will be operational solely on generators
without any power supply from any
external power utility.
Agreed. The project proponent has obtained
assurance from the DHBVN for supply of
electricity. Copy of the same is enclosed as
Annexure 5.
21 Detail calculation of power load and
ultimate power load of the project shall
be submitted to DHBVN under
intimation to SEIAA Haryana before the
start of construction. Provision shall be
made for electrical infrastructure in the
project area.
Agreed. Total power requirement is 3500
kVA. Calculation of power load is enclosed
as Annexure 6.
22. The Project proponent shall not raise any
construction in the natural land
There is no natural land depression/ Nallah/
Water course passing through the project site.
6
depression/Nallah/ Water course and
shall ensure that the natural flow from
the Nallah/ Water course is not
obstructed.
23. The project proponent shall keep the
plinth level of the building blocks
sufficiently above the level of the
approach road to the Project as per
prescribed bye-laws. Levels of the other
areas in the Projects shall also be kept
suitably so as to avoid flooding.
Agreed. The plinth level of the building
blocks will be sufficiently above the level of
the approach road to the project as per
prescribed by-laws. Levels of the other areas
in the projects will also be kept suitably so as
to avoid flooding.
24. Construction shall be carried out so that
density of population does not exceed
norms approved by Director General
Town and Country Department Haryana.
Agreed. Construction will be carried out so
that density of population does not exceed
norms approved by Director General Town
and Country Planning Department Haryana.
25. The Project proponent shall submit an
affidavit with the declaration that ground
water will not be used for construction
and only treated water should be used for
construction.
Agreed. Affidavit regarding no abstraction of
ground water is already submitted to SEIAA,
Haryana.
26. The project proponent shall not cut any
existing tree and project landscaping plan
should be modified to include those trees
in green area.
Agreed. Since the project site is a vacant
land; only small clearing of bushes will be
required.
7
27 The project proponent shall provide 3
meter high barricade around the project
area, dust screen for every floor above
the ground, proper sprinkling and
covering of stored material to restrict
dust and air pollution during
construction.
Agreed. The project proponent will provide 3
meter high barricade around the project area,
dust screen for every floor above the ground,
proper sprinkling and covering of stored
material to restrict dust and air pollution
during construction.
28 The project proponent shall construct a
sedimentation basin in the lower level of
the project site to trap pollutant and other
wastes during rains.
Agreed. Sedimentation basin will be
constructed in the lower level of the project
site to trap pollutant and other wastes during
rains.
29 The Project Proponent shall provide
proper Rasta of proper width and proper
strength for each project before the start
of construction.
Agreed. Proper Rasta of proper width and
proper strength for this project will be
provided before the start of construction.
30 The Project Proponent shall ensure that
the U-value of the glass is less than 3.177
and maximum solar heat gain co-
efficient is 0.25 for vertical fenestration.
Agreed. It will be ensured that the U-value of
the glass is less than 3.177 and maximum
solar heat gain co-efficient is 0.25 for vertical
fenestration.
31 The project proponent shall adequately
control dusts like silica dust, non-silica
and wood dust. Such dust shall not
spread outside project proponent shall
provide respiratory protective equipment
to all construction workers.
Agreed. There will be adequate provision to
control silica dust, non-silica and wood dust.
Such kind of dust will not be spread outside
the project. Respiratory protective
equipments will be provided to all the
construction workers.
32. The project proponent shall develop
complete civic infrastructure of the group
Housing colony including internal roads,
green belt development, sewerage line,
Rain water Harvesting arrangements,
storm water drainage system, solid waste
Agreed.
8
management site and provision for
treatment of biodegradable waste, STP,
water supply line, dual plumbing line,
electric supply line etc. and shall offer
possessions of the units/ flats thereafter.
33. The project proponent shall provide one
refuge area till 24 meter, one till 39
meter and one after 15 meter each, as per
National Building Code. The project
proponent shall not convert any refuse
area in the habitable space and it should
not be sold out/commercialized.
Since , it is an affordable group housing
project , providing refuge area is not
mandatory.
34. The project proponent shall provide fire
control room and fire officer for building
avobe 30 meter as per National Building
Code
Agreed. Fire control room and fire officer
will be provided for building above 30meter
as per National Building Code.
35. The project proponent shall obtain
permission of Mines and Geology
Department for excavation of soil before
the start of construction.
Agreed. Permission from mines and Geology
Department for excavation of soil has been
taken and a copy of it is attached as
Annexure 18.
36. The project proponent shall seek specific
prior approval from concerned local
authority/HUDA regarding provision of
storm drainage and sewerage system
including their integration with external
services of HUDA/ Local authorities
beside other required services of
HUDA /Local authorities beside other
required services before taking up any
construction activity.
Agreed. The project proponent has obtained
permission from HUDA for taking up
construction activity; copy of the same is
enclosed as Annexure 2.
37. The site for solid waste management Agreed. There is solid waste management
9
plant be earmarked on the layout plan
and the detailed project for setting up the
solid waste management plant shall be
submitted to the authority within one
month.
area earmarked on the layout plan and the
detailed project for setting up the solid waste
management plant will be submitted to the
authority in due course of time.
38. The project proponent shall submit the
copy of fire safety plan duly approved
by fire Department before the start of
construction.
Agreed. The approved fire safety scheme has
been attached as Annexure 21.
39. The project proponent shall discharge
excess of treated waste water/storm
water in the public drainage system and
shall seek permission of HUDA before
the start of construction.
Agreed. Permission from competent
authority to discharge sewage into public
sewer will be taken.
40. The project proponent shall maintain the
distance between STP and water supply
line.
Agreed. Suitable difference between STP and
water supply line will be maintained.
41. The project proponent shall ensure that
the stack height is 6 meter more than the
highest tower.
Agreed. Stack height will be provided as per
the CPCB norms.
42. The project proponent shall ensure that
structural stability to withstand
earthquake of magnitude 8.5 on Richter
scale.
Agreed. It is ensured that structural stability
of the building is such that it can withstand
earthquake of magnitude 8.5 on Richter
scale.
43. The project proponent shall implement
the revised site plan marked “A-8/81st”
showing Aaganwadi of 380 sqmt (G+1)
and community center of 380 sqmt
(G+1).
Since , it’s an affordable group housing
project, in Approved Drawing it is only
188.352sqmt & 192.54sqmt
44. The project proponent shall ensure that
no construction activity is undertaken
Agreed. No encroachment of the revenue
rasta will be done while carrying out the
10
either on surface or below or above
surface of revenue rasta passing through
the project area.
construction activities.
45. The project proponent shall indicate the
width and length of revenue rasta passing
through the project area on sign board
and shall display the same at both the
ends of revenue rasta stretch, for
awareness of public. Sign board shall
also display the message that this is a
public rasta/road and any citizen can use
it. There shall not be any gate with or
without guards on revenue rasta further
project proponent shall not encroach
revenue rasta and shall not cross internal
roads over revenue rasta.
Agreed. The width and length of revenue
rasta passing through the project area on sign
board will be displayed on the both the ends
of revenue rasta stretch, for awareness of
public. Sign board will also display the
message that this is a public rasta/road and
any citizen can use it. There will not be any
gate with or without guards on revenue rasta
further, project proponent shall not encroach
revenue rasta and shall not cross internal
roads over revenue rasta.
46. The project proponent shall ensure that
the plinth level of the building block to
be 1.5 meter above 100 years flood level
of the said Najafgarh jheel.
Agreed. The plinth level of the building
block will be kept 1.5 meter above 100 years
flood level of the said Najafgarh Jheel.
47. The project proponent shall obtain NOC
from HUDA as well as Irrigation
Department before the start of
construction, regarding possible adverse
effect of project proposal on the said
Najafgarh Jheel.
Agreed. The required NOC from the
concerned department will be taken in due
course of time.
PART A- SPECIFIC CONDITIONS : Operation Phase
a “Consent to Operate” shall be obtained
from Haryana State Pollution Control
Board under Air and Water Act and a
copy shall be submitted to the SEIAA,
Agreed. “Consent to Operate” will be
obtained from Haryana State Pollution
Control Board under Air and Water Act and a
copy will be submitted to the SEIAA,
11
Haryana. Haryana.
b The STP shall be installed for the
treatment of the sewage to the prescribed
standards including odor and treated
effluent will be recycled. The installation
of STP should be certified by an
independent expert and a report in this
regard should be submitted to the
SEIAA, Haryana before the project is
commissioned for operation. Tertiary
treatment of waste water is mandatory.
Discharge of treated sewage shall
confirm to norms and standards of
HSPCB, Panchkula. Project Proponent
shall implement such STP technology
which does not require filter backwash.
The project proponent shall essentially
provide two number of STP preferably
equipment to 50% of total capacity or
depending upon the initial occupancy as
the case may be.
Agreed. The STP will be installed for the
treatment of the sewage to the prescribed
standards including odor and treated effluent
will be recycled. The installation of STP will
be certified by an independent expert and a
report in this regard will be submitted to the
SEIAA, Haryana before the project is
commissioned for operation. Tertiary
treatment of wastewater is mandatory.
Discharge of treated sewage shall confirm to
norms and standards of HSPCB, Panchkula.
STP technology which does not require filter
backwash will be deployed. Keeping in mind,
the initial occupancy; modular STP will be
provided.
c Separation of the grey and black water
should be done by the use of dual
plumbing line. Treatment of 100% grey
water by decentralized treatment should
be done ensuring that the re-circulated
water should have BOD level less than
5mg/litre and the recycled water will be
used for flushing, gardening and DG set
cooling etc. to achieve zero discharge.
Separation of the grey and black water will
be done by the use of dual plumbing line.
Treatment of 100% grey water by
decentralized treatment will be done ensuring
that the re-circulated water will have BOD
level less than 5mg/litreand the recycled
water will be reused for flushing, gardening,
DG set cooling to achieve zero exit
discharge. Water Balance Diagram showing
Zero Discharge is enclosed as Annexure-7.
12
d For disinfection of the treated waste
water Ultra violet radiation or
ozonization process should be used.
Agreed. For disinfection of the treated
wastewater, UV Disinfection process will be
used.
e Diesel power generating sets proposed as
source of back-up power for lifts,
common area illumination and for
domestic use should be enclosed type
and conform to rules made under the
Environmental (Protection) Act, 1986.
The location of the DG sets should be in
the basement as promised by the project
proponent with appropriate stack height
i.e. above the roof level as per the CPCB
norms. The diesel used for DG sets
should be ultra-low sulphur diesel (35
ppm sulphur) instead of low sulphur
diesel.
Agreed. Diesel power generating sets
proposed as source of back-up power for
lifts, common area illumination and for
domestic use will be of enclosed type and
will conform to the rules made under the
Environmental (Protection) Act, 1986. The
diesel used for DG sets will be ultra-low
sulphur diesel (35 ppm sulphur) instead of
low sulphur diesel. There is no basement in
this project. Picture of D.G. sets is attached
as Annexure 20.
f Ambient noise level should be controlled
to ensure that it does not exceed the
prescribed standards both within and at
the boundary of the proposed Affordable
Group Housing Project.
Agreed. Ambient noise level will be
controlled within and at the boundaries of the
project ensuring compliance to regulatory
norms that is in accordance to Schedule-III of
The Noise Pollution (Regulation and
Control) Rules, 2000. This could be attained
through:
1) Development and maintenance of at
least 20% of the total land area for
tree plantation all around the project.
2) Providing acoustic enclosures to DG
sets.
3) Better traffic management.
4) Regular surveillance monitoring.
13
g The project proponent as stated in the
proposal should maintain at least 18.1%
as green cover area for tree plantation
especially all around the periphery of the
project and on the road sides preferably
with local species so as to provide
protection against noise and suspended
particulate matter. The open spaces
inside the project should be preferably
landscaped and covered with
vegetation/grass, herbs & shrubs. Only
locally available plant species shall be
used.
15.776% of the total project area ( as it is an
affordable group housing project) will be
maintained as used for tree plantation all
around the periphery and the road sides.
Species shall be endemic and chosen to
provide protection from dust and noise. In
addition open spaces within the boundaries
shall be landscaped whenever possible and to
the maximum extent. Landscape Plan is
enclosed as Annexure 8.
h The project proponent shall strive to
minimize water in irrigation of landscape
by minimizing grass area, using native
variety, xeriscaping and mulching,
utilizing efficient irrigation system,
scheduling irrigation only after checking
evapo-transpiration data.
Agreed. Minimum water will be used for
irrigation of landscape by minimizing grass
area, using native variety, xeriscaping and
mulching, utilizing efficient irrigation
system, scheduling irrigation only after
checking evapo-transpiration data.
i Rain water harvesting for roof run-off
and surface, as per plan submitted should
be implemented. Before recharging the
surface run-off, pre-treatment through
sedimentation tanks must be done to
remove suspended matter, oil and grease.
The bore well for rainwater recharging
should be kept at least 5m. Above the
highest ground water table. Care shall be
taken that contaminated water do not
enter any RWH pit. The project
Agreed. Rain water harvesting for roof run-
off and surface, as per plan submitted will be
implemented. Before recharging the surface
run-off, pre-treatment through sedimentation
tanks will be done to remove suspended
matter, oil and grease. The bore well for
rainwater recharging will be kept at least 5m
above the highest ground water table. Rain
water harvesting plan is enclosed as
Annexure 9.
14
proponent shall avoid RWH of first 10
minutes of rain fall. Roof top of the
building shall be without any toxic
material or paint which can contaminate
rain water. Wire mess and filters should
be used wherever required.
j The ground water level and its quality
should be monitored regularly in
consultation with Central Ground Water
Authority.
Agreed. The ground water level and its
quality will be monitored regularly in
consultation with Central Ground Water
Authority.
k A report on the energy conservation
norms finalized by Bureau of energy
efficiency should be prepared
incorporating details about building
material & technology, R & U Factors
etc. and submitted to the SEIAA,
Haryana in three month time.
Agreed. Report on energy conservation
measures conforming to energy conservation
norms finalized by BEE will be submitted in
due course of time. Energy conservation
measures are enclosed as Annexure 10.
l Energy conservation measures like
installation of LED for lighting the-areas
outside the building should be integral
part of the project design and should be
in place before project commissioning.
Use of solar panels must be adapted to
the maximum energy conservation.
Agreed. Energy conservation measures like
installation of LED for lighting the areas
outside the building will be integral part of
the project design and will be in place before
project commissioning. Solar panels will be
adapted for the maximum energy
conservation.
m The project proponent shall use zero
ozone depleting potential material in
insulation, refrigeration, air-conditioning
and adhesive. Project proponent shall
also provide Halon free fire suppression
system.
Agreed. Zero ozone depleting potential
material in insulation, refrigeration, air-
conditioning and adhesive will be used.
Halon free fire suppression will be provided.
15
n The solid waste generated should be
properly collected and segregated as per
the requirement of the MSW Rules, 2000
and as amended from time to time. The
bio-degradable waste should be
composed by vermin-composting at the
site war marked within the project area
and dry/inert solid waste should be
disposed-off to the approved sites for
land-filling after recovering material.
Agreed. The solid waste generated will be
properly collected and segregated as per the
requirement of the MSW Rules, 2000. The
bio-degradable waste will be composed by
the use of organic waste converter at the site
earmarked within the project area and
dry/inert solid waste will be disposed-off to
the approved sites for land-filling after
recovering material. Solid Waste
Management plan is enclosed as Annexure-
11.
o Provision of the solar water heating
systems shall be as per norms specified
by HAREDA & shall be made
operational in each building block
Agreed. The provision of the solar water
heating system will be as per the norms
specified by HAREDA and will be made
operational in each building block.
p The traffic plan and the parking plan
proposed by the project proponent should
be adhered to meticulously with further
scope of additional parking for future
requirement. There should be no traffic
congestion near the entry and exit points
from the roads adjoining the proposed
project site. Parking should be fully
internalized and no public space should
be used.
Agreed. Proposed parking plan will be
adhering to meticulously with further scope
of additional parking for future requirement.
There will be no traffic congestion near the
entry and exit points from the roads adjoining
the proposed project site. Parking will be
fully internalized and no public space should
be used. Parking cum traffic circulation plan
is enclosed as Annexure 12.
q The Project shall be operationalized only
when HUDA/local authority will provide
domestic water supply system in the
area.
Agreed. The Project will be operationalized
only when HUDA/local authority will
provide domestic water supply system in the
area.
r Operation and maintenance of STP, solid
waste management and electrical
Agreed. Operation and maintenance of STP,
solid waste management and electrical
16
Infrastructure, pollution control measures
shall be ensured even after the
completion of project.
Infrastructure, pollution control measures
will be ensured even after the completion of
sale.
s Different type of waste should be
disposed-off as per provisions of
municipal solid waste, biomedical waste,
hazardous waste, e-waste, batteries &
plastic rules made under Environment
Protection Act, 1986. Particularly E-
Waste and Battery waste shall be
disposed of as per existing E-waste
Management Rules 2011 and Batteries
Management Rules 2001. The project
proponent should maintain a collection
center for E-Waste and it should be
disposed of to only registered and
authorized dismantler/recycler.
Agreed. Different type of waste will be
disposed-off as per provisions of municipal
solid waste, biomedical waste, hazardous
waste, e-waste, batteries & plastic rules made
under Environment Protection Act, 1986.
Particularly E-Waste and Battery waste will
be disposed of as per existing E-waste
Management Rules, 2011 and Batteries
Management Rules, 2001. Collection center
for E-Waste will be maintained and it will be
disposed of to only registered and authorized
dismantler/recycler.
t Standards for discharge of environmental
pollutants as enshrined in various
schedules of rules 3 of Environment
Protection Rules 1986 shall be strictly
complied with.
Agreed. Standards for discharge of
environmental pollutants as enshrined in
various schedules of rules 3 of Environment
Protection Rules, 1986 will be strictly
complied with.
u Water supply shall be metered to
different residential units and different
utilities.
Agreed. Water supply will be metered to
different residential units and different
utilities.
v The project proponent shall ensure that
the stack height of DG sets is as per the
CPCB guide lines and also ensure that
the emission standards of noise and air
are within the CPCB prescribed limits.
Noise and Emission level of DG sets are
Agreed. It is ensured that the stack height of
DG sets is as per the CPCB guidelines and
also that the emission standards of noise and
air are within the CPCB prescribed limits.
Noise and Emission level of DG sets greater
than 800KVA will be maintained as per
17
greater than 800KVA shall be as per
CBCB latest standards for high capacity
DG sets.
CBCB latest standards for high capacity DG
sets.
w All electric supply exceeding 100amp, 3-
phase shall maintain the power factor
between 0.98 lag to 1 at the point of
connection.
Agreed. All electric supply exceeding
100amp, 3-phase will maintain the power
factor between 0.98 lag to 1 at the point of
connection.
x The project proponent shall use only
treated water instead of fresh water for
HVAC and DG cooling. The project
proponent shall use evaporative cooling
technology and double stage cooling
system for HVAC in order to reduce
water consumption. Further temperature,
relative humidity during summer and
winter session should be kept at optimal
level. Variable speed drive, best co-
efficient of performance, as well as
optimal integrated point load value and
minimum outside fresh air supply may
be resorted for conservation of power
and water. Coil type cooling DG sets
shall be used for saving cooling water
consumption for water cooled DG sets.
Agreed. It is ensured that treated water
instead of fresh water will be used for
horticulture, flushing and DG cooling. As it
is affordable housing project; so, HVAC will
not be provided. Further temperature, relative
humidity during summer and winter session
will be kept at optimal level. Variable speed
drive, best co-efficient of performance, as
well as optimal integrated point load value
and minimum outside fresh air supply will be
resorted for conservation of power and water.
y The PP shall ensure that the transformer
is constructed with high quality grain
oriented, low loss silicon steel and virgin
electrolyte grade copper. The PP shall
obtain manufacturer’s certificate also for
that.
Agreed. We will ensure that the transformer
is constructed with high quality grain
oriented, low loss silicon steel and virgin
electrolyte grade copper and manufacturer’s
certificate will be obtained.
z The project proponent shall ensure that Agreed. We will ensure that exit velocity
18
exit velocity from the stack should be
sufficiently high. Stack shall be designed
in such a way that there is no stack
down-wash under any meteorological
conditions.
from the stack will be sufficiently high.
Stack will be designed in such a way that
there is no stack down-wash under any
meteorological conditions.
aa The project proponent shall provide
water sprinkling system in the project
area to suppress the dust in addition to
the already suggested mitigation
measures in the Air Environment
Chapter of EMP.
Agreed. Water sprinkling will be carried out
by the labour.
ab The project proponent shall ensure
proper Air Ventilation and light system
in the basement area for comfortable
living of human being and shall ensure
that number of Air Changes per
hour/(ACH) in basement never fall
below 15.In case of emergency capacity
for increasing ACH to the extent of 30
must be provided by the project
proponent.
Agreed. The project proponent will ensure
proper air ventilation and lighting.
ac The project proponent shall ensure
drinking/ domestic water supply as per
prescribed standards till treated water
supply is made available by HUDA.
Agreed. We will ensure drinking/domestic
water supply as per prescribed standards till
treated water supply is made available by
HUDA.
ad The project proponent shall provide
addition green area on terrace and roof
top.
Agreed. The project proponent will provide
additional green area on terrace and roof top.
ae The project proponent shall install solar
panel for energy conservation.
Agreed. The project proponent will install
solar panel for energy conservation
19
PART-B GENERAL CONDITION:
I. The project proponent should ensure the
commitments made in Form-1, Form-1A,
EIA/EMP and other documents
submitted to the SEIAA for protection of
environment and proposed
environmental safeguards are complied
with in letter and spirit. In case of
contradiction between two or more
documents on any point, the most
environmentally friendly commitment on
the point shall be taken as commitment
by project proponent.
Agreed. It will be ensured that commitments
made in Form-1, Form-1A, EIA/EMP and
other documents submitted to the SEIAA for
protection of environment and proposed
environmental safeguards are complied with
in letter and spirit. In case of contradiction
between two or more documents on any
point, the most environmentally friendly
commitment on the point will be taken as
priority.
II. The project proponent shall also submit
six monthly compliance of the reports
on the status of compliance of the
stipulated EC conditions including result
of monitored data (both in hard copy as
well as by e-mail)to the northern regional
Office, MoEF, the respective Zonal
office of CPCB, HSPCB and SEIAA ,
Haryana.
Agreed. This is first compliance. Six monthly
monitoring reports will be submitted to the
northern regional Office, MoEF, the
respective Zonal office of CPCB, HSPCB
and SEIAA, Haryana.
III. STP outlet after stabilization and stack
emission shall be monitored monthly.
Other environmental parameters and
green belt shall be monitored on
quarterly basis. After every 3 months, the
project proponent shall conduct
environmental audit and shall take
corrective measure, if required, without
delay.
Agreed. STP outlet after stabilization and
stack emission will be monitored monthly.
Other environmental parameters and green
belt will be monitored on quarterly basis.
After every 3 months, the project proponent
will conduct environmental audit and will
take corrective measure, if required, without
delay.
20
IV. The SEIAA, Haryana reserves the right
to add additional safeguard measures
subsequently, if found necessary.
Environmental Clearance granted will be
revoked if it is found that false
information has been given for getting
approval of this project. SEIAA reserves
the right to revoke the clearance if
conditions stipulated are not
implemented to the satisfaction of
SEIAA/MOEF.
Agreed.
V. The project proponent shall not violate
any judicial orders/ pronouncements
issued by the Court/ Tribunal.
Agreed.
VI. All other statutory clearances such as the
approvals for storage of diesel from
Chief Controller of Explosives, Fire
Department, Civil Aviation Department,
Forest Conservation Act, 1980 and
Wildlife (Protection) Act, 1972, Forest
Act, 1927, PLPA 1900 etc. shall be
obtained, as applicable by the project
proponents from the respective
authorities prior to construction of the
project.
Agreed. AAI NOC receiving from Civil
Aviation Department for Height clearance
and Aravalli clearance from D.C. has already
been granted and are enclosed as Annexure
– 13& 14respectively. For forest NOC please
refer Annexure 4.
VII. The project proponent should inform the
public that the project has been accorded
Environment Clearance by the SEIAA
and copies of the clearance letter are
available with the Haryana State
Pollution Control Board & SEIAA. This
Agreed. Advertisement copy of notice in
Newspaper will be submitted in the next
compliance report.
21
should be advertised within 7 days from
the date of issue of clearance letter at
least in two local newspapers that are
widely circulated in the region and the
copy of the same be forwarded to SEIAA
Haryana. A copy of Environment
Clearance collections shall also be put on
project proponent’s website for public
awareness.
VIII. Under the provisions of Environment
(Protection) Act, 1986, legal action shall
be initiated against the project proponent
if it was found that construction of the
project has been started without
obtaining Prior Environmental
Clearance.
Agreed. Environmental clearance has been
obtained vide letter no. SEIAA/HR/2014/882
dated 30.06.2014from SEIAA. EC Letter is
attached as Annexure - 15.
IX. Any appeal against this Environmental
Clearance shall lie with the National
Green Tribunal, if preferred within a
period of 30 days as prescribed under
Section 16 of the National Green
Tribunal Act, 2010.
Agreed.
X. The project proponent shall put in place
Corporate Environment Policy as
mentioned in MOEF, GOI, ON No. J-
11013/41/2006-IA II (I) dated 26.04.12
within 3 months period. Latest Corporate
Environment Policy should be submitted
to SEIAA within 3 months of issuance of
this letter.
Agreed. CESR Plan will be submitted to
SEIAA.
XI. The fund ear-marked for environment Agreed.
22
protection measures should be kept in
separate account and should not be
diverted for other purposes and year wise
expenditure shall be reported to the
SEIAA/RO MoEF GOI under rules
prescribed for Environment Audit.
XII. The PP shall ensure the compliance of
Forest Department, Haryana Notification
no. S.O.121/PA2/1900/S.4/97 dated
28.11.1997.
Agreed. The compliance of Forest
Department, Haryana Notification no.
S.O.121/PA2/1900/S.4/97 dated 28.11.1997
will be done.
XIII. The project proponent shall ensure that
no vehicle during construction/operation
phase enter the project premises without
valid ‘Pollution Under Control’
certificate from competent Authority.
Agreed. It will be ensured that no vehicle
during construction/operation phase enters
the project premises without valid ‘Pollution
Under Control’ certificate from competent
Authority.
XIV. The PP is responsible for compliance of
all conditions in Environmental
Clearance letter and project proponent
can not absolve himself/herself of the
responsibility by shifting it to any
contractor engaged by project proponent.
Agreed. We will be responsible for
compliance of all conditions in
Environmental Clearance letter and project
proponent cannot absolve himself/herself of
the responsibility by shifting it to any
contractor engaged by project proponent.
XV. The Project proponent shall seek fresh
Environmental Clearance if at any stage
there is change in the planning of the
proposed project.
Agreed. Fresh Environmental Clearance will
be sought if at any stage there is change in
the planning of the project.
XVI. Besides the developer/ applicant, he
responsibility to ensure the compliance
of Environmental clearance if at any
stage there is change in the planning of
the proposed project.
Agreed. Besides the developer/ applicant, the
responsibility to ensure the compliance of
Environmental clearance if at any stage there
is change in the planning of the project.
XVII. The proponent shall upload the status of Agreed.
23
compliance of the stipulated EC
conditions, including results of
monitored data on their website and shall
update the same periodically. It shall
simultaneously be sent to the regional
office of levels namely: PM2.5, PM10,
SOx, NOx, Ozone, Lead, CO, Benzene,
Ammonia, Benzopyrine, arsenic and
Nickel, (Ambient levels as well as stack
emissions) or critical sectoral parameters,
indicated for the project shall be
monitored and displayed at convenient
location near the main gate of the
company in the public domain.
XVIII. The environmental statement for each
financial year ending 31st March in
form-V as is mandated to be submitted
by the project proponent to the HSPCB
Panchkula subsequently, shall also be
sent to the respective Regional Office of
MoEF by e-mail.
Agreed. The environmental statement for
each financial year ending 31stMarch in
form-V as is mandated to be submitted by the
project proponent to the HSPCB Panchkula
subsequently, will also be sent to the
respective Regional Office of MoEF by e-
mail.
XIX. The project proponent shall conduct
environment audit at every three months
interval and thereafter corrected measure
shall be tken without any delay. Details
of environment audit and corrective
measures shall be submitted in the
monitoring report.
Agreed. We will conduct environment audit
at every three months interval and thereafter
corrected measure shall be taken without any
delay. Details of environment audit and
corrective measures will be submitted in the
monitoring report.
XX. Corporate Environment and Social
Responsibility (CESR) shall be laid
down by the project proponent (2% shall
Agreed. CESR will be carried out during the
construction of the project.
24
be earmarked) as per guidelines of
MoEF, GOI Office Memorandum No. J-
11013/41/2006-IA.II (I) dated
18.05.2012 and ministry of Corporate
Affairs, GOI Notification Dated
27.02.2014. A separate audit statement
shall be submitted in the compliance.
Environment related work proposed to be
executed under this responsibility shall
be undertaken simultaneously. The
project proponent shall select and
prepare the list of the work for
implementation of CESR of its own
choice and shall submit the same before
the start of construction.
(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF
SI.
No.Points as per EIA Guidance Manual Status of Compliance
A. Air Environment
1. Wind erosion is a serious problem in
areas where the ground is virtually bare
and devoid of vegetation. Vegetation
methods are found to be most effective
in the form of windbreaks and
shelterbelts.
The site will be enclosed with sufficiently high
barricade wall around the project boundary
which will act as a wind breaker.
Vegetation will be developed during the
operation phase of the project.
25
SI.
No.Points as per EIA Guidance Manual Status of Compliance
2. Sprinkling of water and fine spray from
nozzles to suppress the dust.
Water sprinkling will be carried out through
tanker water regularly at site for dust
suppression and logbook will be maintained.
3. On-Road-Inspection should be done for
black smoke generating machinery.
All the machineries deployed at site will be of
good standard and of reputed make and
comply with emission & noise standards.
Inspections and maintenance of construction
machineries and vehicles will be carried out
periodically.
4. Promotion of use of cleaner fuel should
be done.
Ultra low sulphur diesel (ULSD) (sulphur
content less than 50ppm) will be used for
running of DG sets, vehicles and construction
machineries.
5. All DG sets should comply emission
norms notified by MoEF.
The DG sets will be acoustically enclosed
which will conform to the permissible air
emission and noise standards notified by
MoEF. DG sets will be fitted with stack of
sufficient height as prescribed in emission
norms notified by MoEF. Monitoring of
emissions of DG sets will be carried out
periodically.
6. Vehicles having pollution under control
certificate may be allowed to ply.
Only PUC certified vehicles will be allowed to
enter the project site. The vehicles without
valid Pollution under Check (PUC) certificate
are not permitted at project site.
26
SI.
No.Points as per EIA Guidance Manual Status of Compliance
7. Use of covering sheet to prevent dust
dispersion at buildings and
infrastructure sites, which are being
constructed.
Sheets will be used to prevent dust dispersion.
8. Use of covering sheets should be done
for trucks to prevent dust dispersion
from the trucks, implemented by district
offices.
The trucks carrying construction materials and
debris will be covered by tarpaulin and plastic
sheets.
9. Paving is a more permanent solution to
dust control, suitable for longer duration
projects. High cost is the major
drawback to paving.
During construction, access roads will be
covered with gravels to prevent dust emission.
(At the completion stage of the project, all
permanent internal roads & walkway will be
paved and greeneries will be developed)
10. Reducing the speed of a vehicle to 20
kmph can reduce emissions by a large
extent. Speed bumps are commonly
used to ensure speed reduction. In cases
where speed reduction cannot
effectively reduce fugitive dust, it may
be necessary to divert traffic to nearby
paved areas.
Speed of the vehicles will be restricted by
erecting speed bumps at regular intervals at
project site and proper signage will be
provided for guided vehicular movement and
speed restrictions.
27
SI.
No.Points as per EIA Guidance Manual Status of Compliance
11. Material storages/ warehouses-Care
should be taken to keep all material
storages adequately covered and
contained so that they are not exposed to
situations where winds on site could
lead to dust/ particulate emissions.
Fabrics and plastics for covering piles of
soils and debris is an effective means to
reduce fugitive dust.
We are making concrete at site through Batch
Mix Plant.
B. Noise Environment
1. Setting up the barriers: National
Building Code 2005 suggests that
design solutions such as barrier blocks
should be used to reduce external LA10
noise levels to at least 60-70dB(A) at
any point 1.0 m from any inward
looking façade.
The site will be enclosed with sufficiently high
barricade wall around the project boundary to
control propagation.
The DG sets will be installed in acoustic
enclosure which conforms to the permissible
noise standards notified by MOEF. DG sets
will be new and certified by manufacturers.
C. Water Environment
1. Curing water should be sprayed on
concrete structures; free flow of water
should not be allowed for curing.
Curing water will be sprayed on concrete
structures.
2. After liberal curing on the first day, all
concrete structures should be painted
with curing chemical to save water. This
will stop daily water curing hence save
water.
Curing compounds will be used to save water
for curing.
28
SI.
No.Points as per EIA Guidance Manual Status of Compliance
3. Concrete structures should be covered
with thick cloth/gunny bags and then
water should be sprayed on them. This
would avoid water rebound and will
ensure sustained and complete curing.
Concrete structures will be covered with thick
clothes/ gunny bags and water spraying will be
taken into practice to prevent water loss.
4. Ponds should be made using cement and
sand mortar to avoid water flowing
away from the flat surface while curing
No water will be used for curing hence, ponds
are not proposed in the site.
5. Water ponding should be done on all
sunken slabs; this would also highlight
the importance of having an impervious
formwork.
No water will be used for curing.
(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO CONSTRUCTION
29
SI.
No.NGT Order dated 10.04.2015 Status of Compliance
1. Every builder or owner shall put tarpaulin on
scaffolding around the area of construction
and the building. No person including
builder, owner can be permitted to store any
construction material particularly sand on
any part of the street, roads in any colony.
Tarpaulin covers will be provided around the area
of construction wherever required. No construction
materials such as cement, sand and aggregates will
be stored at site. Ready-mixed concrete will be used
for concrete work at project site which will be
transported from the off-site batching plant.
2. The construction material of any kind that is
stored in the site will be fully covered in all
respects so that it does not disperse in the Air
in any form.
Tarpaulin covers will be provided around the area
of construction wherever required.
3. All the construction material and debris shall
be carried in the trucks or other vehicles
which are fully covered and protected so as
to ensure that the construction debris or the
construction material does not get dispersed
into the air or atmosphere, in any form
whatsoever.
The trucks carrying construction materials and
debris will be covered by tarpaulin and plastic
sheets.
4. The dust emissions from the construction site
should be completely controlled and all
precautions taken in that behalf.
All necessary precautions will be adopted to control
the dust emissions. Water sprinkling at site will be
carried out through tanker water regularly at site for
dust suppression and logbook will be maintained.
5. The vehicles carrying construction material
and construction debris of any kind should be
cleaned before it is permitted to ply on the
road after unloading of such material.
“Wheel Washing Bay” has been provided at main
entry road and Batching Plant sites. Wheels of
construction equipment/ vehicles and trucks will be
washed before allowing it to ply on the road.
30
SI.
No.NGT Order dated 10.04.2015 Status of Compliance
6. Every worker working on the construction
site and involved in loading, unloading and
carriage of construction material and
construction debris shall be provided with
mask to prevent inhalation of dust particles.
All safety measures will be taken. Construction
workers has been provided with personal protective
equipment (PPE) as required under the health &
safety norms. The pictures of construction workers
using PPE is attached as Annexure 16.
7. Every owner and or builder shall be under
obligation to provide all medical help,
investigation and treatment to the workers
involved in the construction of building and
carry of construction material and debris
relatable to dust emission.
Fully fledged first aid facility has been provided at
the construction site and regular medical check-ups
by Doctor will be conducted for construction
workers. Logbook will be maintained with medical
treatment details of the workers.
8. It shall be the responsibility of every builder
to transport construction material and debris
waste to construction site, dumping site or
any other place in accordance with rules and
in terms of this order.
When debris will be generated, it will be disposed
off at Government Authorized landfills.
9. All to take appropriate measures and to
ensure that the terms and conditions of the
earlier order and these orders should strictly
comply with by fixing sprinklers, creations
of green air barriers.
Regular sprinkling of water will be carried out at
site through tanker.
10. Compulsory use of wet jet in grinding and
stone cutting.
All necessary precautions will be taken in the stone
cutting and grinding area which will be done at later
stage of construction.
11. Wind breaking walls around construction
site.
The site will be enclosed with sufficiently high
barricade wall around the project boundary which
acts as a wind breaker.
31
SI.
No.NGT Order dated 10.04.2015 Status of Compliance
12. All the builders who are building
commercial, residential complexes which are
covered under the EIA Notification of 2006
shall provide green belt around the building
that they construct. All Authorities shall
ensure that such green belts are in existence
prior to issuance of occupancy certificate.
Green area will be developed at the end of
construction stage as per approved building plan.
32
Recommended