View
219
Download
0
Category
Preview:
Citation preview
7/28/2019 Useful Formulas for PMP
1/4
KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX
Effective Learning for Sure Success Page 1
Earn Value FormulasPV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled
EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work Performed)
SV = EVPV (minus is behind schedule)
CV = EVAC (minus is over budget)
SPI = EV/PV (Less than 1 is behind schedule)
CPI = EV/AC (Less than 1 is over budget)
EAC = AC + (BAC-EV) Use when variances are atypical
EAC = AC + [(BAC-EV)/CPI] Use when variances are typical
(Note: This is the same as EAC = BAC/CPI)
VAC = BACEAC
ETC = BACEV Use when variances are atypical
ETC = (BACEV)/CPI Use when variances are typical
ETC = EACAC Use when original estimates were flawed
Network DiagramPrecedence Diagramming Method (PDM)
Also called Activity on Node (AON): Activities are in boxes
Most commonly used today
Has 4 relationships: F-S, S-S, F-F, S-F
No dummies (zero duration dependencies) allowed
Can analyze using either Three-Point Estimates or CPM
Arrow Diagramming Method (ADM)
Also called Activity on Arrow (AOA)
Only 1 relationship: F-S
Can have dummies
Can analyze using either Three-Point Estimates or CPM
Graphical Evaluation and Review Technique (GERT) - Allows loops and repetitive activitiesThree Point Estimates, or PERTPERT = PROGRAM Evaluation and Review Technique
Holds schedule and lets cost float
3 estimates for each task: Optimistic, Pessimistic, and Most Likely
7/28/2019 Useful Formulas for PMP
2/4
KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX
Effective Learning for Sure Success Page 2
Mean Estimate = (O + 4*ML + P)/6
Standard Deviation (s) = (PO)/6
Variance = s2 , or [(PO)/6]2
Standard deviation of tasks on CP = Sum of variances
Standard Deviation Ranges:
If 95% is confidence rating. Range =(2 x ) to + (2 x )
Powers of a Project Manager1. Expert: Best, earned on your own
2. Reward: Next best. Based on PM position
3. Formal: Power, based on PM position
4. Referent: Referring to positions of others
1. 5. Penalty: Worst. Based on PM position
Sources of Conflict (Order of Priority)1. Schedules
2. Priorities
3. Manpower (Resources )
4. Technical Opinions
5. Procedures
6. Personality7. Cost
Channels of CommunicationBetween Team Members = N(N-1)/2
Project Selection Financials
7/28/2019 Useful Formulas for PMP
3/4
KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX
Effective Learning for Sure Success Page 3
NPV (Net Present Value) = FV/(1+r)n
FV= Future Value, r= interest rate, n= no. of time periods
Higher NPV is better
IRR (Internal Rate of Return) = Solve the NPV equation for r
Also called Hurdle Rate
Higher IRR percentage is better
BCR (Benefit/Cost Ratio)
Higher BCR is better.
Beware, exam can call it CBR, where lower is better
ROI (Return on Investment) = Earnings/Investment
Higher ROI is better
Payback Period = Time to recover cost of the project
Lower payback period is better
Cash Flow = Cash InCash Out
Calculating Stack or FloatTotal Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed
without delaying the project finish date.
Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following
activity).
LS ES: Calculates slack with forward pass
LF EF: Calculates slack with backwards passLag Time: Inserted wait time between activities
Lead Time: Overlapping activities, also called paralleling or fast tracking. Lead In; Lag Out
Accuracy of EstimatesOrder of Magnitude:-50% to +50%
Budget Estimate:-10% to +25%
Definitive Estimate:-5% to +10%
Conflict Resolution(Best to Worst)1. Problem Solving: Also called Confronting
2. Compromising: Solutions satisfy both parties
3. Withdrawal: Postponing a decision
4. Smoothing: Emphasis on agreement
5. Forcing: One viewpoint at expense of another.
7/28/2019 Useful Formulas for PMP
4/4
KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX
Effective Learning for Sure Success Page 4
Herzbergs Motivators1. Achievement
2. Recognition
3.
Challenge of the work itself
4. Responsibility
5. Advancement
6. Growth
ClosingProject is closed when administrative closure is complete.
Administrative closure is done at end of each Project Phase and at the end of the Project.
Contract closure: verification that deliverables were acceptable; it is done once at the end of the
contract.
Contract Closure Procedure is produced under Close Project
Recommended