Timberlane School Field Restoration Project Middle School Freshman JV

Preview:

Citation preview

T imber lane Schoo lF ie ld Res to ra t i on P ro jec t

Middle School Freshman

JV

Tonight

• To review JV/ Middle School Baseball Field proposed renovation donation:• Dugouts• Batting cages• General Field Improvements• Long term Goals

• Proposed value

• Phase one: $19,369.25• Phase two: $20,366.00

Quick update

What we’ve accomplished so far!

Where We Started

Day 1 irrigation

Shine on me!

Phase 1

Two 9’ x 50’ dugouts

Construction to be supervised by Jim Hughes and Angelo Fantasia

Construction•Reinforced Concrete Pads•8’ CMU three courses high•2 X 6 stick Construction

Proposed Cost $19,369.25

Phase 2 Batting CagesTwo 70’ X 16’ x12’ Batting Cages

Internal Net to fit inside cages

Increased value at practices

Saves on existing infrastructure

Access from dug out directly into batting cage

Proposed Cost $20,366.00

Batting Cage

T

Dugout

Dugou

tSeat

s

Seats

Battin

g Cage

310’

350’

Design Advantages

Batting Cages:

Extensions of backstop

Used as on deck circle

and bullpen

Increase efficiency of

practice time

Dugouts:

Provides a dry and

sheltered area for players

Adds separation

from students and fans

Field Needs

Long Term Project

•Bleachers•Outfield fence•Lights

Proposed Screening

Serves three purposesPrivacy from Batting cages and other

fields.Mode of corporate donationsTeam logo

Proposed Value

JV FIELD RESTORATIONItem Materials Total cost Alt Extension

Dug outs 2 x 50' x 12' 2x6x8 with 4x8 siding 1,259.65$ 2,519.30$ 8" CMU 375.00$ 750.00$ Paint/ nials/ rental 925.00$ 925.00$

roof 1,857.00$ 3,714.00$ Timbertech benches 1,885.95$

Pad 1,250.00$ 2,500.00$ Labor 3,537.50$ 7,075.00$

Footings and foundation Total Dug out 19,369.25$

Fence /Poles batting cages 9,585.00$ 19,166.00$ 19,166.00$

Netting 1,200.00$

20,366.00$

Master Plan

Parent Participation

• Communications• Participation• Fund Raising• Team Building

projects• Short Term Field Plan• Long Term Plan

Donations

• Corporate Sponsorships

• Donation acknowledgement

• Sign of recognition• Corporate

involvement• Fund raising

activities

Value vs. Cost

• Batting cages– Cost to contract = $20,366.00–Material Cost:• Fence $ 1000.00• Misc. $ 200.00• Net $ 650.00• Labor $ 0.00 ____________Total cost $1850.00

Recommended