1 Texas Nodal
Texas Nodal
Program Implementation
TPTF June 26, 2006
Agenda
2 Texas Nodal
Agenda
• Rational Unified Process training: 10 mins – Status …….request for action
• Nodal Market Implementation Status Report: 15 mins– Information– Qs and As
• TPTF Submission Schedule (Gantt): 15 mins – Information– Timeline negotiation, principles identified
• Key Dates for Planning: 30 mins – Information– Discussion
3 Texas Nodal
Texas Nodal
Market Participant RUP Training
June 26, 2006
4 Texas Nodal
TPTF RUP Training Overview
Summary – 10 attendees confirmed to date
• Provide overview of RUP (Rational Unified Process)
• Basics to writing Use Cases
• Two 16-person classes
• One day in length
• All classes at IBM Austin – downtown
– July 12th (Wednesday)
– August 9th (Wednesday)
– Email: raldridge@ercot.com to register
5 Texas Nodal
Status Report
• Nodal Market Implementation Status Report: 15 mins
– Information
– Qs and As
6 Texas Nodal
Texas Nodal Market Implementation
ERCOT Board of Directors MeetingProgram status briefing - June 20,2006
TPTF June 26, 2006
7 Texas Nodal
Overall Status
Overall program status remains redThe size, complexity and risk of the program is not yet contained: The common network model and CRR are subject to significant uncertainty Expectations for extensive fork-lifting must be tempered by the fact of unique Texas Nodal Protocols Budgetary implications are not firmEnlisting TPTF to expedite resolution of key issuesScenario analyses will inform options for substantial de-risking “green” software and integrationERCOT will confirm the budget – and its risk-based contingencies – on September 1 (to coincide with the go-live date determination)
Low confidence in the feasibility of 1/1/09 (<5%):ERCOT and the Market Participants will confirm the go-live date by September 1 (Results delivered at the 9/13/06 BOARD meeting)
Staffing is not yet fixed: Mobilization and productivity levels are behind expectations Resources for business requirements are the priority
A comprehensive staffing model is now being deployed, utilizing ERCOT staff, short-term staff augmentation, contractors and consultants
Business requirements are the short-term critical path challenge: The scale of effort required to achieve the necessary quality and approval is not yet understood Mobilization and productivity levels are behind expectations NPRRs have not been impacted through the Nodal Change Control
The combined NODAL team is driving to complete business requirements by October 30
8 Texas Nodal
Texas Nodal Team achieved a major milestone:- selected preferred vendors (RFP’s issued April 14)
Vendor selection completed on schedule: ERCOT selected preferred vendors for the critical Nodal systems Rigorous selection criteria have been applied, consistent with the Nodal Charter:
- No “green” software – code in production will have fewer bugs, more robust, with proven integration- Consistent with ERCOT’s technology roadmap/footprint – to minimize total cost of ownership- Risk mitigation – minimized integration risks having schedule and cost implications- Proven track record of delivery – client references have been leveraged to validate predicted performance- Strength of vendor team – demonstrate adequate commitment of skills and experience, particularly project management
The results of selection are strictly confidential, pending explicit advice to the contrary
Preferred Vendor Other comments
Credit Monitoring ROME Corporation
CRRNexant, Inc.
Energy Solutions Division
EMS AREVA T&D, Inc. (current vendor)
Financial transfer None To be developed internally
Load Forecast AREVA T&D, Inc. (current vendor)Improvements to the zonal application currently underway will be migrated to Nodal. The application will be supplemented by a forecasting service for reference/assurance
Market OperationsABB, Inc.
PSN/Power Systems Division
Network Modeling & TelemetryNexant, Inc.
Energy Solutions DivisionAssessment and improvement of model and SE – short- and long-term
NMMSSiemens Power Transmission & Distribution, Inc.
Energy Management & Automation Division
Outage SchedulerABB, Inc.
PSN/Power Systems DivisionVendor governed by MMS selection
RPP forecast AWS Truewind, LLC
Note - Commercial Systems (including Billing and Settlement) to be developed internally).
9 Texas Nodal
A strategy for integration has been established – requiring additional procurements
The strategy – messaging through web services with specialized solutions e.g. for real time and bulk data: Focus on information architecture – applications need common definitions to communicate Applications are loosely coupled through web services – insulating each application from changes in other applications.
Changes center on messages, not the implementation of messages Applications need not be “aware” of the web services, transforming interfaces into messages Adhere to widely adopted open standards (i.e. xml, soap, wsdl, uddi) to reduce the technology implementation issues Preferred vendors can all support this strategy
The strategy for integrating information addresses a number of risks: Applications must communicate with each other, an EDW and presentation layer Avoids the risk of point solutions without incurring the cost and effort of a major EAI implementation
ERCOT will issue an RFP to specialist IT integration vendors
10 Texas Nodal
Spending year to date
O&M Internal labor $ 1452K Equipment, tools, supplies $ 19K Outside services $ 878K Facilities and Utilities $ 91K Employee expenses $ 19K Interest and fees $ 21K Total O&M: $2,480K
Capital Total Capital $ 473K
Total spending through May $2,953K 83% since April
11 Texas Nodal
TPTF Submission Schedule
• TPTF Submission Schedule (Gantt): 15 mins
– Information
– Timeline negotiation, principles identified
12 Texas Nodal
Integrated timeline to September – as of 6/22/06
Week ending dates (Friday) Jul 14 Sep 15Jul 28Jul 21Jun 16Jun 9Jun 2 Jun 30Jun 23 Jul 7May 26 Sep 8Aug 4 Aug 11 Sep 1Aug 25Aug 18Jul 14 Sep 15Jul 28Jul 21Jun 16Jun 9Jun 2 Jun 30Jun 23 Jul 7May 26 Sep 8Aug 4 Aug 11 Sep 1Aug 25Aug 18
NMMS NMMS Vendor T&M Contract Mobilize
CSD TPTF approval
NMMS – Requirements, DSOW, Use Case, Conceptual Design Development
CSD TPTF submission
Conceptual System DesignNMMS NMMS Vendor T&M Contract Mobilize
CSD TPTF approval
NMMS – Requirements, DSOW, Use Case, Conceptual Design Development
CSD TPTF submission
Conceptual System Design
EMS Proposal Refinement
TPTF approval
EMS – Requirements, DSOW, Use Case, Conceptual Design Development
TPTF submission
Contract MobilizeEMS Proposal Refinement
TPTF approval
EMS – Requirements, DSOW, Use Case, Conceptual Design Development
TPTF submission
Contract Mobilize
IDA
Vendors on board 7/5
RUP Training Delivery
Vendor demos
RUP standards definition
Bus process validation
Configuration Mg Plan
Vendors selected
6/7
Overall architecture
6/7
CSD & Interface doc templates
ERCOT Readiness & Transition
As-is Org Analysis Org Vision & Principles
EDS Release Strategy – V0.9
Org Options Org Design
EDS Release Strategy – Socialization EDS Release Strategy – V1 EDS 3 Release Plan
People Strategy Capabilities Planning
Testing StrategyProject
Staffing & startup
Nodal Resourcing Template Nodal Resourcing Template – V1 ERCOT Readiness Criteria RC link to MPERP Organization Readiness Plan V1
Draft EDS Release Strategy
Testing Strategy
EDS Release Strategy TPTF submission
EDS3 Release Plan
People Transition plans
EDW EDW – Architecture definition EDW – Roadmap definitionEDW EDW – Architecture definition EDW – Roadmap definition
MMS
Reqts TPTF submission
MMS – Requirements, DSOW, Use Case DevelopmentMMS Vendor T&M Contract MobilizeMMS
Reqts TPTF submission
MMS – Requirements, DSOW, Use Case DevelopmentMMS Vendor T&M Contract Mobilize
Infrastructure
Business Implementation plans
Commercial Systems
CM - Contract
FT - Assessment
Reqts TPTF approval
Reqts TPTF submission
Mobilize Credit Monitoring - Requirements, Use Case Development
Financial Transfer - Requirements, Use Case Development
Disputes
Registration - Conceptual System DesignRegistration - Requirements, Use Case Development
Reqts TPTF approval
Reqts TPTF submission
Settlements & Billing - Requirements, Use Case Development (multiple drops)
Commercial Systems
CM - Contract
FT - Assessment
Reqts TPTF approval
Reqts TPTF submission
Mobilize Credit Monitoring - Requirements, Use Case Development
Financial Transfer - Requirements, Use Case Development
Disputes
Registration - Conceptual System DesignRegistration - Requirements, Use Case Development
Reqts TPTF approval
Reqts TPTF submission
Settlements & Billing - Requirements, Use Case Development (multiple drops)
Resourcing
Test Lab DefinitionIntegrated Testing Test Case Template; Procedures Early Test Cases (EMS/MMS)
Test Script template
Test Case template
Test lab configuration
SAT CriteriaDetailed Planning Test Lab DefinitionIntegrated Testing Test Case Template; Procedures Early Test Cases (EMS/MMS)
Test Script template
Test Case template
Test lab configuration
SAT CriteriaDetailed Planning
CRRRequirements, Use Case, DSOW DevelopmentCRR Vendor T&M Contract
ResourcingReqts TPTF submission
Clarification Questions to TPTF
CRRRequirements, Use Case, DSOW DevelopmentCRR Vendor T&M Contract
ResourcingReqts TPTF submission
Clarification Questions to TPTF
MP Engagement & Readiness
TPTF Review/Approve Nodal PRRs TPTF – Review/Approve Business Requirements & Conceptual Systems Designs
Discuss Readiness Criteria with TPTFMP Engagement & Readiness
TPTF Review/Approve Nodal PRRs TPTF – Review/Approve Business Requirements & Conceptual Systems Designs
Discuss Readiness Criteria with TPTF
Use Cases
EMMS H/W vendor selection
MISMIS-Posting/Reports/Extracts - Requirements
MIS Strategy definition MIS Roadmap definition MIS –UI Requirements from applications identified
Integration Strategy definition Integration RoadmapIntegration
Existing data center rationalization
Changes/additions in blue
13 Texas Nodal
Planning Dates
• Key Dates for Planning: 30 mins
– Information
– Discussion
14 Texas Nodal
Preliminary Key Dates
• 6/7/06 Preferred vendors selected• 7/5/06 Start joint requirements, use cases, test cases was 6/30/06
• 7/6/06 EDW Roadmap complete• 7/10/06 Market Participant readiness activities list• 7/30/06 MIS & Integration Roadmap complete
» Scenario Development and Choices 6/7-9/1
• 9/13/06 ERCOT Board of Directors meeting (commitment: date and dollars)
• 10/30/06 Rqmts complete and approved *requires TPTF approval
• 3/31/07 Market Participant interface specs complete• 4/1/07 EMS FAT begins
• 1/1/08 Market Participant SCED offers begin (EDS3)• 7/1/08 Market systems, Market Participant offers (EDS4)