THE ISRAEL ELECTRIC CORPORATION LTD. ENGINEERING PROJECTS GROUP ENGINEERING DIVISION
STANDARD No. 01-1E
STANDARD SPECIFICATION FOR
CONTRACTOR'S DDOCUMENTS, DATA FILES AND TRANSMITTALS
01 May 2017 Dr. A. Livshits; B. Meiri; J. Ipenberg; P. Soloveichik; N. Buchbut; E. Reznitzky
T. Romano Z. Steg
00 May 2004 M. Ronen J. Weinstock
J. Habuba Z. Eyal First issue
Rev. Date Prepared Checked Approved Description
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 2 of 34
STANDARD SPECIFICATION 01-1E
CONTRACTOR’S DOCUMENTS, DATA FILES AND TRANSMITTALS
TABLE OF CONTENTS
SECTION PAGE No.
1. General …………………………………………………………… 2
2. Quality Requirements …………………………………………… 4
3. Data Files and Transmittals………………………………………... 4
4. Mailing of Documents…………………………………… ………. 10
5. Attachments………………………………………………………. 10
Attachment # 1: Document Transmittal Notice………………… 11
Attachment # 2: Approval Notice Stamp………………………. 12
Attachment # 3: Instructions for AUTOCAD
Drawings Submitted to IEC……………………… 13
Attachment # 4: Requirements for PDMS Model
and Items to be Agreed Upon………………….. 15
Attachment # 5: Requirements for Technical Data
and Commercial Lists …………………………… 16
Attachment # 6: Upload files service - Web Site home page… 31
Attachment # 7: Instruction for IEC SFE use…………………. 32
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 3 of 34
STANDARD 01-1E
CONTRACTOR’S DOCUMENTS, DATA FILES AND TRANSMITTALS
1. GENERAL
Document control is an essential key to the project success. It allows both IEC and
the Contractor to keep track of all the documents and drawings which are
submitted for approval / information and submittals of documents and comments
from IEC to the contractor or backwards.
In accordance with the provisions of the General Conditions and the Schedule in
accordance with Annexure "J" – Documentation Submission Schedule; and not
derogating from the generalities thereof, Contractor’s documents, such as:
Drawings, Manuals and Instructions (data, certificates, reports, calculations), Lists
and Procedures, etc., shall be submitted to the Purchaser in accordance with this
Standard, except as supplemented in or modified by the Technical Specification
(Annexure “B”).
1.1 Transmittal Notice
A transmittal notice (see paragraph 3 below for detailed information) must
accompany all Contractor's documents. Transmittals submitted without a
transmittal notice containing necessary information will be returned to the
Contractor.
1.2 Design Information
Design information shall be included on correctly identified documents (see
paragraph 3 below for required identifying information). The fact that such design
information may later be included in instruction and/or operating manuals does not
relieve the Contractor from compliance with this requirement.
1.3 Instructions Manuals
Instruction Manuals (Installation, commissioning, Operation and Maintenance
Instructions, Erection and Execution of Work Directive and Assembly Instructions,
Storage, Preservation and Shipment Instructions), shall be submitted in
accordance with the requirements of the Technical Specification (Annexure "B")
and the general Conditions (Annexure "A").
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 4 of 34
1.4 Document Review and Approval
All documents shall be submitted, as required in the Technical Specification
(Annexure "B") and Documents Submittal Schedule (Annexure "J"), to the
Purchaser for Approval or for Information.
1.4.1 The Purchaser will review the documents for compliance with Contract Technical
Specifications. If changes or corrections are necessary the documents, with such
changes or corrections noted, will be returned to the Contractor.
1.4.2 Submittals requiring the Purchaser’s approval will be reviewed by Purchaser,
submittals will be marked and stamped same to indicate changes or corrections,
as required (as detailed in 1.4.3).
1.4.3 The Contractor shall prepare the APPROVAL NOTICE, as shown in Attachment # 2,
and stamp it on each drawing and document that requires an approval by the
Purchaser according to the Contract. The Purchaser will provide (by request) the
APPROVAL NOTICE stamp on digital media. The size and measures of the
APPROVAL NOTICE stamp should be kept without change.
Submittals requiring the Purchaser’s approval will be returned to the Contractor,
marked as follows:
STATUS 1
NO EXCEPTION TAKEN, THE CONTRACTOR MAY
PROCEED WITH FABRICATION OR CONSTRUCTION.
STATUS 2
THE CONTRACTOR MAY PROCEED, BASED ON
MAKING REVISIONS AS NOTED AND RESUBMIT.
STATUS 3
REVISE AS NOTED AND RESUBMIT - HOLD
FABRICATION.
STATUS 4
CANCELED
STATUS 5
FOR INFORMATION ONLY
1.5 Contractor’s Exceptions
Any exceptions to this Standard shall be clearly indicated in the Proposal submittal
and specifically identified as an exception.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 5 of 34
2. QUALITY REQUIREMENTS
2.1 Documents submitted to the Purchaser shall be of such quality and with such
legibility that hard-copy reproductions may be prepared by the Purchaser with
every line, character and letter clearly legible.
2.2 Documents submitted to the Purchaser that do not conform to the requirements of
this Specification, shall be subject to rejection by the Purchaser and, upon request,
the Contractor shall resubmit conforming documents. The Contractor’s (or its
Subcontractors') failure to initially satisfy the legibility quality requirements herein
set forth, will not release the Contractor (or his Subcontractors) from meeting the
required schedule for submittal of drawings and data.
3. DATA FILES AND TRANSMITTALS
3.1 Document Transmittal Notice
3.1.1 A transmittal notice must accompany all Contractor's documents, as required in
the Specification. The transmittal notice shall be made on the official document
transmittal notice (example as Attachment # 1, available on EXCEL by request).
Each document for a part, component, assembly, sub-assembly or any other item
supplied in accordance with the Project Specification shall specify the location and
methods for identifying the item. Identification shall include at least the following:
o Name of Contractor
o Name of Project
o Plant name/Power station & Unit number
o IEC's Order number
o Contract number
o Issued for: Approval or Information
o Manufacturer
o Document number
o Revision number
o Title
o Paragraph in Annex "J"
o WBS/KKS (if applicable)
3.1.2 The document transmittal filename shall contain the wording: "TRANSMITTAL
NOTICE" and the Transmittal No. ________.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 6 of 34
3.1.3 The Transmittal should be submitted to IEC, in EXCEL format, with the following
parameters:
Values Size Data
e
Description
30 String Contractor
15 String Order No.
15 String Transmittal No.
DD/MM/YYYY Date Transmittal date
30 String Power Station
2 String Unit
10 String Contract Number / Specification
20 String Name of Project
A=Approval, I=Information 12 String Issued for
25 String Manufacturer / Sub-supplier
25 String Document/ Drawing No.
3 String Revision
4 String Number of sheets
90 String Title/Description
Value = 0 Drawing
Value = 1 Instruction
Value = 2 Manual
Value = 3 Other
2 String Document Type
(A0, A1, A2, A3, A4) 2 String Original Size
Value = E (Electrical)
Value = M (Mechanical)
Value = C (Civil)
2 String Department
20 String Paragraph in Annex “J”
20 String WBS/KKS
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 7 of 34
3.2 Document Formats
3.2.1 Documents, excluding: drawings, lists and technical data, included in the
Transmittal list, should be provided in a separate file, in its original size in PDF
format or as agreed upon with the Contractor.
3.2.2 All drawings included in the Transmittal list should be provided in a separate file, in
its original size in PDF format at least. In addition, the following shall apply:
3.2.2.1 Mechanical drawings shall be provided in PDF format. Other formats, such
as: Microsoft Excel, Word, Power Point, DXF, DWG or other files may be
submitted in addition. AUTOCAD format Drawings having VECTOR format
that IEC is currently utilizing.
3.2.2.2 Civil design drawings in PDF format shall be signed by responsive Civil
engineer and submitted in original size without scaling.
3.2.2.3 Civil design drawings should be provided additionally in AUTOCAD DWG
format. Instructions for AUTOCAD Drawings submitted to IEC detailed in
Attachment # 3 hereto.
3.2.2.4 Electrical design drawings should be provided in PDF format and in
AUTOCAD DWG format.
3.2.3 Three dimensional (3D) model and design information should be provided in the
applicable design software. The design software shall be the following:
3.2.3.1 Mechanical 3D design information should be provided in AVEVA PDMS
12.1® system format.
3.2.3.2 Civil 3D conceptual design information should be provided in AVEVA
PDMS 12.1® system format
3.2.3.3 Civil 3D detailed model of steel structures used for shop drawings
preparation shall be submitted as TEKLA model in format DB1.
3.2.3.4 Physical Electrical design information should be provided in AVEVA
PDMS 12.1® system format.
3.2.4 All software formats shall be the formats that currently utilized by IEC. The
Contractor is to be notified of any alteration and he should then update his version
accordingly.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 8 of 34
3.2.5 Technical data and lists, exampled in Attachment # 5 hereto, should be provided in
EXCEL or as agreed upon with the Contractor. The exact format and fields will be
determined between the Contractor and the Purchaser.
3.2.6 Both parties, the Contractor and the Purchaser, will designate each one at its site,
a person responsible for a smooth and timely data exchange session.
The Contractor and the Purchaser will agree upon the type, version and method of
data exchange.
3.2.7 Currently, IEC’s electrical design is done in COMOS. Therefore, information
exchange with the Contractor is highly preferred to be done in COMOS data base.
3.3 Dimensional System
The dimensions in all submittals shall be in the metric system. The English
equivalent of principal dimensions and tolerances may be indicated in adjacent
brackets.
3.4 Technical Document Revisions
Any change of a document after its release must be considered as a new revision
or as creating a new document. For revisions, the title should remain unchanged,
the document identification number and code has to remain. Revision should
Marked as follows:
o The first issue of a document will be marked with the number "00". Any
following revision will increase the number (e.g.: 01, 02, 03, etc.)
o Changes of a revision should mark with a “cloud”. As in the example:
o Mark inside a triangle signal indicating the revision of the change. As in the
example:
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 9 of 34
o Canceled, Deleted or Superseded drawings shall be marked with a stamp as
follows:
In these cases, the revision number shall be updated.
If applicable, the drawing shall contain the relevant identification (e.g. This
drawing is now superseded by____).
3.5 Documents Submittal
3.5.1 Documents shall be submitted by e-mail or digitally (as agreed upon with the
Contractor). The documents should be sent by one of the following ways:
E-Mail. Each E-Mail should not exceed the size of 10 MB.
IEC upload files service at the address: https://bellashim.iec.co.il (suitable
also for files exceed the size of 10 MB). Web Site home page attached as
Attachment # 6 hereto.
Secure File Exchange Service (SFE) - suitable for both small and large
files (required registration). Instruction for using SFE attached as /
Attachment # 7 hereto.
Other methods to be agreed upon.
3.5.2 Digital Signature
All official documents submitted to the Purchaser by E–Mail should be digitally
signed by the sender, in order to ascertain authenticity and the integrity of the
message contents.
The digital signature should utilize Public Key Infrastructure (PKI) technology of a
well-known commercial Certificate Authority (CA), preferably VeriSign.
The applied system should be supported by Microsoft Outlook 2002 ®.
The technical details should be coordinated by both parties (see para 3.2.6
above).
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 10 of 34
3.6 Drawing Changes
Identification of changes on all drawings from the previous issue shall be shown
on each drawing.
3.7 Drawing Number
Each separate drawing submitted to the Purchaser shall have a discrete drawing
number for correct identification. Duplicate pieces of equipment such as valves,
shall not be grouped on one drawing. They may utilize the same reference
drawing, but each valve shall have a discrete identification number.
3.8 Submittal Language
All submittals shall be in English or Hebrew (option of the Contractor).
3.9 WBS code (if applicable)
In case WBS code is applicable, following the first review of the documents, IEC
will provide the appropriate WBS (Work Breakdown Structure) code on digital
media for the relevant document.
The Contractor shall add the WBS code on the approval stamp. IEC's WBS code
is comprised of: Sub-Project Code, Content (Physical Breakdown) Code and
System Code. An example of how to indicate IEC's WBS Code is given below:
02 – S22 – XX (Sub-Project – Content – System).
3.10 KKS code (if applicable)
In case KKS code is applicable, following the first review of the documents, IEC
will provide to Contractor the appropriate IEC KKS dialect.
Relevant document: ED.077 9/14, Rev. 00-04/12/2014 (Not Included)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 11 of 34
4. MAILING OF DOCUMENTS
Shipment Method
All documents in all forms, as required by this Standard and the Technical
Specification, originating outside Israel, shall be submitted by E-mail, or other
method as agreed upon with the Contractor. In addition, hard-copies, if
required according to the Contract, shall be submitted and sent by a special
courier shipped Air-Freight. For materials originating in Israel, the manner of
shipment shall be coordinated with the Purchaser.
5. ATTACHMENTS
The following attachments are part of this Standard Specification.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 12 of 34
ATTACHMENT # 1
DOCUMENT TRANSMITTAL NOTICE
(Example)
Definition of Terms
Contractor: Contractor name (Originator of document delivery)
Submitted by: The name of the person responsible
IEC’s Order No. Order number issued by IEC
Transmittal No.: Contractor's transmittal number
Date: Date of supplied transmittal
Contractor Job No.: Contractor's job number (if any)
Subject: Power Station and Unit number
Contract no. / Specification: Equipment Specification / Contract code
Issued: Submitted for your: A= Approval; I= Information
Manufacturer / Sub-supplier: Name of Equipment manufacturer / Sub-supplier
Document / Drawing number: Contractor's document number
Rev.: Revision number
No. of Sheets: Number of Sheets
Title / Description: Document title (System name / Component name)
Doc. Type: Type of document.: 0 = Drawings, 1 = Instruction,
2 = Manual, 3 = Other.
Original Size: The original size of the document as submitted (e.g.: A0,
A1, A2, A3, A4)
Department: IEC's relevant Department (e.g. Electrical, Mechanical,
Civil,)
Paragraph in Annex "J": Correlation to Annexure “J” line item number
(Documentation Submission Schedule)
WBS/KKS (if applicable): appropriate WBS (Work Breakdown Structure) /
appropriate IEC KKS dialect
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 13 of 34
ATTACHMENT # 2
APPROVAL NOTICE STAMP
THE ISRAEL ELECTRIC CORP. LTD.
Engineering Division
APPROVAL NOTICE
REVIEWED FOR
__________________ POWER STATION
UNITS: ___________________________
□ Mechanical Department
□ Electrical Department
□ Civil Department
ST. 1 □ NO EXCEPTION TAKEN,
CONTRACTOR MAY
PROCEED WITH FABRICATION
OR CONSTRUCTION.
ST. 2 □ CONTRACTOR MAY PROCEED,
BASED ON MARKING REVISIONS
AS NOTED AND RESUBMIT.
ST. 3 □ HOLD FABRICATION, REVISE
AS NOTED AND RESUBMIT.
ST. 4 □ CANCELED.
ST. 5 □ FOR INFORMATION ONLY.
ANY ACTION SHOWN ABOVE IS SUBJECT
TO THE TERMS OF THE CONTRACT AND
DOES NOT RELEASE CONTRACTOR FROM
HIS OBLIGATIONS UNDER THE CONTRACT
INCLUDING DESIGN AND DETAILING.
SPEC. No. ___________________
SUB PROJECT No. ___________
CONTENT(PBS) _____________
SYSTEM ____________________
SIGNATURE _________________
DATE ______________________
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 14 of 34
ATTACHMENT # 3
INSTRUCTIONS FOR AUTOCAD DRAWINGS
SUBMITTED TO IEC
1. Unicode should not be used when indicating the measures on the drawing.
2. Standard definitions of Dimension Style and Text Style should not be changed.
3. The size of the drawing sheet should not be less than the minimal size
according to ISO (A4).
4. The drawing will be drawn using Decimal units. The English equivalent of
principal dimensions and tolerances may be indicated in adjacent brackets.
5. All types of dimensions used in the drawing should have a corresponding
"Dimension Style". If the dimensions have been determined by external
application (not by AUTOCAD internal work environment), take care to define
the corresponding "Dimension Style" correctly. If the "Dimension Style" could
not be defined, an "Explode" command should be given to these dimensions.
6. Only original AUTOCAD "Shape" files should be used.
7. "True Type Fonts" in Hebrew should not be used.
8. The original path of the AUTOCAD for the text font should be used when
defining the "Fonts Style".
9. Only IEC's Standard Hebrew Text Fonts should be used. IEC will provide the
Hebrew Fonts for AUTOCAD to the Contractor.
10. "Mline" line types should not be used.
11. Only AUTOCAD standard line types should be used.
12. Irrelevant entities should be deleted from the drawing before submitting it to
IEC.
13. The dimensions should not be included in other Blocks.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 15 of 34
14. If "Binding" of "Xref" is performed, the sign "$" should be removed from all
names (LayerName, TextStyle, LineStyle, etc.)
15. The following Files should be attached to each drawing:
"Text Fonts" files, used in the drawing
"Xref" files, if applicable.
"Color Map" (*.pcp) files, compatible to HP printers.
"Raster image" files, if applicable.
16. The names of the used "Color Map" should be saved in the same drawing
"Layout settings".
17. It is possible to use the following seven basic colors width (instead para 16):
Color Pen Number Width (mm)
Red 1 0.2
Yellow 2 0.6
Green 3 0.4
Cyan 4 0.3
Blue 5 0.7
Violet 6 0.5
White 7 0.2 (0.1)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 16 of 34
ATTACHMENT # 4
REQUIREMENTS FOR PDMS MODEL
AND
ITEMS TO BE AGREED UPON
ITEMS TO BE AGREED UPON DURING THE MEETING IN ORDER TO FACILITATE
THE USE OF PDMS
1. Power plant point of origin.
2. Direction of the North on the isometric drawings.
3. A naming system for the axes of the plant, used exclusively by the two parts.
4. Type naming of PDMS’ PIPE and VALVE.
5. Terminal points for customer connections will be given by a list which will
define the following items:
Three (3) D position of the leaving point of the nozzle.
Three (3) D Orientation of the leaving point of the nozzle.
Connection size.
Connection type.
THE REQUIRED FORMATS ARE AS FOLLOWS:
1. Three (3) Dimensional model elements (equipment, pipes, foundations, etc.)
will be as a PDMS Databases and PDMS system Databases with advanced
numbering agreement.
2. Two (2) Dimensional drawing originating in PDMS format will be supplied in
the following formats.
PDMS plot file format or AUTODESK AUTOCAD 2000 DXF® format.
DRAFT plot sheet file.
3. The Contractor’s piping specification used for creating the model piping will be
supplied in PDMS PARAGON Databases and PDMS system Databases
numbering as agreed upon.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 17 of 34
ATTACHMENT # 5
REQUIREMENTS FOR TECHNICAL DATA AND COMMERCIAL LISTS
The supplier should provide all types of list, each having its specific fields, as detailed
below, on a digital media such as EXCEL and ACCESS structured files, that IEC
currently utilizes so, that each field of the list may be processed by computer
programs.
The Data for each Project and Unit should be provided in separate files.
The records in each file should have a constant structure.
Records should not be split into several records and the content of a field should not
be split into several lines.
Cancelled records should not be deleted. Additional and adjacent field should be
utilized, in order to indicate on it that this record is canceled and not relevant any
more.
Empty fields should not be deleted.
The repeating fields in the different lists in the different files, such as: Project, Unit,
Drawing No., Item No., etc. should be identical.
Any data value should be indicated in the correct field, in such a way that only one
value will be indicated in one field.
The following marks should not appear at the beginning of the fields as they are
reserved marks used for computing infrastructure:
=, @, %, #, &, <, >, etc.
1. Commercial Lists
1.1 Equipment Shipment Report (ESR).
1.2 Packing List of Items.
1.3 Package Header
1.4 Package List
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 18 of 34
2. Technical Data Lists
2.1 Bill of Materials (BOM) / Parts List.
2.2 Instrument List.
2.3 Connection List.
2.4 Electrical Consumer List.
2.5 Cable List.
2.6 Materials and Electrical Equipment List.
2.7 Reserved.
2.8 List of Input and Output Signals (I/O List).
2.9 List of Tools and Equipment for Erection and Maintenance.
2.10 List of Field Work and Fabrication.
2.11 Insulation Bill of Materials.
2.12 Drawing List/Data Sheet List.
2.13 Sub-Suppliers List
2.14 List of all Components and Accessories Manufactured in Israel.
2.15 List of all Components and Accessories Manufactured in Countries
other than Israel.
2.16 List of Equipment Requiring Greasing and Lubricating Oil.
2.17 List of Pipes and Data.
2.18 Welding Points List and Data.
2.19 Supports List and Bills of Material.
2.20 Conversion List between IEC's Code and Supplier's Code.
2.21 List of Reinforcement Bar Schedule.
2.22 Embedded Parts List.
2.23 Design Calculation List.
2.24 Civil Design Criteria/ Load Data/ Instructions, Recommendations,
Specifications, Catalog data Sheets/ Erection and Construction Instructions/
Consultant Reports.
2.25 List of Valves (On/Off, Throttling, Safety, Combined, Modulating).
2.26 List of Pumps.
2.27 List of Address/IP (Sub-Stations)
2.28 List of IED – Intelligent Electronic Devices (Sub-Stations)
2.29 List of Switches (Sub-Stations)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 19 of 34
DEFINITION OF THE REQUIRED FIELDS FOR EACH LIST TYPE
The following defines the requirements of the fields for each list:
1. Commercial Lists
1.1 Equipment Shipment Report (ESR)
Project
Unit
Item Number (In the ESR)
Supplier's Item Code
IEC's Catalog Number
Description
Quantity
Unit of Measure
Mode of Delivery
Latest Date of Delivery
Revised Latest Date of Delivery
Related Milestone
Manufacturer's Country of Origin
Supplier
Identification Code of Item for Power Plants, such as KKS
(if applicable)
Attended by
Remarks/Open Points
1.2 Package List
Project
Unit
Delivery Number
Package Number
Description
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 20 of 34
1.3 Package Header
Project
Unit
Package Number
Contract Number
IEC's Order Number
Description
Type of Package
Storage Category
Notes
Gross Weight (Kg)
Net Weight (Kg)
Volume (m3)
Length (cm)
Width (cm)
Height (cm)
Pack Number of Sub-Supplier
1.4 Packing List of Items
Project
Unit
Package Number
Item Number (In the ESR)
Supplier's Item Code
Part Number (in the Drawing)
Drawing Number
Drawing revision
Quantity
Unit of Measure
Description
Designation
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 21 of 34
2. Technical Data Lists
2.1 Bill of Materials (BOM)/ Parts List
The BOM shall be submitted in the format of the product tree
Project
Unit
Order Number
Drawing Number
Drawing Revision
Part Number (In the Drawing)
Item Number (In the ESR)
Supplier's Item Code
Supplier's Name
Description
Designation
Quantity
Weight
Unit of Measure (ton, kg)
Dimensions
Identification Code of Item for Power Station such as KKS
(if applicable)
Conservation Code
IEC's Catalog Number
Material
Material ID Number
Characteristics
Storage Code
Erection Step Number
Dangerous Good Class
2.2. Instrument List
The Instrument List/Index shall include all field instruments, such as: Control
Valves, Solenoid Valves, Limit Switches, etc., as well as all control
instruments (if any), such as: Hand Switches, Recorders, Indicators, etc.
For each Instrument, at least the following data should be included:
Project
Unit
Contractor's/Manufacturer's Tag Number
IEC's Tag Number
Manufacturer
Model Number
Power Supply (if applicable)
Enclosure Protection (IP or NEMA)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 22 of 34
2.3 Connection List
The Contractor shall provide full data concerning instrumentation primary
point (take-off connections) including:
Project
Unit
Size
Type (SW, Flange, Screwed, etc.)
Material
Rating
2.4 Electrical Consumers List
The Contractor shall provide a list of electrical consumers sorted by type for
Motors, Actuators, Equipment, Cubicles, etc., including the following data:
Project
Unit
IEC's Tag Number of Consumer
Description
Manufacturer
Manufacturer's Tag Number
Power (KW)
Rated Voltage
Rated Current
Motor RPM
Quantity/Unit
Normal Operation Work/Stand-by
Operation hrs/day
Area Location
2.5 Cable List
The Contractor shall provide a list of all cables, including the following:
Project
Unit
Cable Type
Wire Size
Number of Conductors.
KKS Descriptive Number
Location of Starting and Ending Points
Word Description
Cable Length (if applicable)
IEC's Tag Number
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 23 of 34
Factory-Mounted or Installed and Wired by IEC
From Tag Number
To Tag Number
2.6 Materials and Electrical Equipment List
The Contractor shall furnish a complete list of materials and electrical
equipment with sufficient details to allow for complete identification of all
components of the assembly. The list will include the following:
Project
Unit
Part Identification
Type
Manufacturer's Identification
Description
Material Specification
Standard
Number of Similar Parts
General Remarks
2.7 Reserved.
2.8 List of Input and Output Signals (I/O List)
The Contractor shall provide a list of I/O signals in MS Excel or Access file
format, including:
Project
Unit
For the exchange signals:
KKS Tag Name
Description
Signal Designation (AI, DI, AO, DO)
Generic Name of the signal
Source/destination, field device Tag name
For the hardwired signals the following information shall also be included,
according to the signal type specification:
Analog signal type: 4-20 RTD, TC's or other
Analog signals loop/power definition (two wire, 4 – wire)
Digital signals type (Dry contact, Voltage, etc.)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 24 of 34
For the Transferred by Communication signals:
Signal source/destination network mode (PLC, computer) address
Signal address with the network mode (register, bit, etc.)
Scaling factor, for AI and AO, that has to be used when
coding/decoding the analog value to/from the corresponding digital
value
If more than one link is used for the connection with PCMS, each link
will then get a number/name. The database will clearly indicate for
each signal to which link it belongs
Separate lists (database files) with exactly the same attributes as defined
above, will be provided for signals between DCS and field or DCS and
systems other than DCS.
2.9 List of Tools and Equipment for Erection and Maintenance
The Contractor shall provide a complete list of general tools, special tool and
a separate complete list of maintenance equipment and tools including:
Project
Unit
Description
Purpose
Part Number
Manufacturer
2.10 List of Field Work and Fabrication
The Contractor shall provide comprehensive lists for all field work and field
fabrication work to be performed by IEC, such as:
Temporary work, Scaffolding, Blocking, Shoring, Hanging, Heating, Wiring,
Disassembling, Reassembling, Welding, Preheating, Stress relieving,
Cleaning, Checking, Inspecting, Insulating, Painting, Testing, etc, including:
Project
Unit
Erection Step Number
Description of Work/Erection Step Description
Approximately Time for performance
Subject
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 25 of 34
2.11 Insulation Bill of Materials
Project
Unit
Supplier's Item Code
Insulation Material
Description
Type of Insulation
Insulation Purpose
Minimum Insulation Thickness
Heat Loss
Specification
2.12 Drawing List/ Data Sheet List
The Contractor shall provide complete list of drawings, technical data sheet,
specifications, instructions, characteristics, curves, diagrams, calculations
and any other document, for each piece of equipment from the Contractor or
Sub-Contractor, including the following data. The Contractor should indicate
on the list which items are being purchased from Sub-Contractor.
Project
Unit
Contractor's Drawing Number
Sub-Contractor's Drawing Number
Revision
Title
Drawn By
Drawn Date
2.13 Sub-Suppliers List
Project
Unit
Sub-Supplier's Name
Type of Equipment Supplied
Address of Sub-Supplier
2.14 List of all Components and Accessories Manufactured in Israel
Project
Unit
Component/Accessory Description
Purpose
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 26 of 34
Part Number
Manufacturer
2.15 List of all Components and Accessories Manufactured in Countries other
than Israel
Project
Unit
Component/Accessory Description
Purpose
Part Number
Manufacturer
2.16 List of Equipment Requiring Greasing and/or Lubricating Oil
The Contractor should indicate the following data required for storage,
erection, start-up, and/or maintenance:
Project
Unit
Equipment Description
IEC's Tag Number (of equipment)
Manufacturer's Tag No. (of equipment)
Grease/Oil Specification
Quantity of grease/Lubricant
2.17 Pipes List and Data
Project
Unit
Identification of Item Code for Power Station such as KKS
Area
Description
Pipe Size
Pipe Schedule
Material
Max Flow (t/hr) at operating condition
Max Flow (m3/hr) at operating condition
Pressure at operating condition
Design Pressure
Test Pressure
Specific Volume at operating conditions
Calculated Velocity at operating conditions
Design Temperature
Design Code
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 27 of 34
Required Minimum Valve or Flange Rating
Piping Code
Insulation Material
Type of Insulation
Insulation Purpose
Cladding Thickness
Ambient Temperature
Minimum Insulation Thickness
Surface Temperature
Heat Loss
Piping Drawing
Revision
ISO Drawing reference
P&ID Drawing reference
2.18 Welding Points List and Data
Project
Unit
Weld Number
Pipe Number Identification (KKS)
NDE ASME Requirements
Radiation
Furnace Gases
Water or Steam
Location of Weld
Drawing Number
Pipe Size
Outer Diameter
Minimum Weight
Nominal Weight
Weld Size
DN
SCH
Ring Type and Number or Fillet Size
Material Specification
Maximum Carbon Content
Type of Joint
Jurisdiction
BP, BEP, NBEP
Design Temperature
Design Pressure
Weld Reference Drawing Number
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 28 of 34
2.19 Supports List and Bill of Materials
Project
Unit
Drawing Number
Revision
Item Number
Quantity
IEC's Tag Number
Supplier's Item Code
Description
Type
Material
Remarks
2.20 Conversion List between IEC's Codes and Supplier's Code
Equipment Identification
IEC's Code
Supplier's Code
Sub–Part Description
Type No. Drawing Number
2.21 Reinforcement Bar Schedule List
Project
Unit
Document Number
Title
Revision
Date
Contractor
Manufacturer
Manufacturer Type (M=Main Contractor, S=Sub-contractor)
Language
Document Format (PDF, RTF, XLS)
Page Size (A4, A3)
Number of Pages
Contract Code
Transmittal Number
Mode of Delivery
Remarks/Open Points
Reinforcement Grade
Total Mass
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 29 of 34
Reference Drawing Number
2.22 Embedded Parts List
Project
Unit
Document Number
Title
Rev.
Date
Contractor
Manufacturer
Manufacturer Type (M=Main Contractor, S=Sub-contractor)
Language
Document Format (PDF, RTF, XLS)
Page Size (A4, A3)
Number of Pages
Contract Code
Transmittal Number
Mode of Delivery
Remarks/Open Points
Steel Grade
Total Mass
Corrosion Protection such as:
o Hot dip galvanized
o Painting
o Epoxy coating
o Other
o No coating
Reference Drawing Number
2.23 Design Calculation List
Project
Unit
Document Number
Title
Revision
Date
Contractor
Manufacturer
Manufacturer Type (M=Main Contractor, S=Sub-contractor)
Language
Document Format (PDF, RTF, XLS)
Page Size (A4, A3)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 30 of 34
Number of Pages
Contract Code
Transmittal Number
Mode of Delivery
Remarks/Open Points
Finite Element Model (Program Name)
Analysis Type, such as:
o Static
o Modal
o Harmonic Response
o Response Spectrum
Load Combinations ( Yes/No)
2.24 Civil Design Criteria/ Load Data/Instructions, Recommendations,
Specifications, Catalogue data Sheets/ Erection and Construction
Instructions/ Consultant Reports
Project
Unit
Document Number
Title
Revision
Date
Contractor
Manufacturer
Manufacturer Type (M=Main Contractor, S=Sub-contractor)
Language
Document Format (PDF, RTF, XLS)
Page Size (A4, A3)
Number of Pages
Contract Code
Transmittal Number
Mode of Delivery
Remarks/Open Points
2.25 Valves List
Project
Unit
Identification of Item Code for Power Station such as KKS
IEC's Tag Number
Pipe Diameter (Input and Output)
Class
Fluid
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 31 of 34
Body Material
Type
Actuator Type
Type of Joint (Input and Output)
Pressure at operating condition
Temperature at operating condition
Pressure (barg) at Design condition
Temperature (ºC) at Design condition
Set point Pressure
P&ID Drawing number
Revision
Remarks
Number of pages
Page size (A4/A3)
2.26 Pumps List
Project
Unit
Identification of Item Code for Power Station such as KKS
IEC's Tag Number
Pump Type
Condition (Inlet / Outlet)
Fluid
Suc. Pressure at operating condition
Disc. Pressure at operating condition
Temperature at operating condition
Pressure (barg) at Design condition
Temperature (ºC) at Design condition
Pump material
P&ID Drawing number
Revision
Remarks
Number of pages
Page size (A4/A3)
2.27 Address/IP List (TBD)
2.28 IED List (TBD)
2.29 Switches List (TBD)
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 32 of 34
ATTACHMENT # 6
Upload files service - Web Site home page
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 33 of 34
ATTACHMENT # 7
Instruction for IEC SFE (Secure File Exchange) use
Secure File Exchange Service - SFE provides a secure service (based on Vault Technology infrastructure) to transfer files between IEC and external factors in a simple, via WEB, that does not require any end positions installations. It allows also transferring extremely large files. User instructions:
1. Sign in SFE service: 1.1. Enter to the address (preferably IE): https://files.iec.co.il/SFE 1.2. The following display will be shown:
1.3 The user must enter its e-mail address for Username, followed by Password. The
initial password shall be transmitted by the IEC’s IT department; the system will require changing this Password when connecting for the first time.
1.4 For additional support, please contact IEC contact person.
THE ISRAEL ELECTRIC CORPORATION LTD. ENGINNERING PROJECTS GROUP STANDARD 01-1E ENGINEERING DIVISION
STANDARD 01-1E rev.2017
Page 34 of 34
2. Using SFE Service after identification (user name and password):
2.1 To send a file to IEC, enter the SFE Outbox folder and perform a Send action for any attached file to be passed to IEC, or perform Download action for any file that has to be transferred or downloaded.
2.2 In order to download a file transferred from IEC to the external factor, one has to
enter the SFE Inbox folder and perform a Download. 2.3 It is possible to set a corresponding option, for an email automatic notification of
the relevant parties concerning a new file transfer.
3. Option to transfer large files (up to 40MB): To move a large file or in case of slow Internet communication, it is recommended to use the parameter My Transfer Manager (mark V) on the screen User Profile. This parameter will trigger a Java program which will allow the transfer the files transparently to the user.
Supported Browsers The following browsers support Secure File Exchange:
Internet Explorer 6.0 and 7.0 on Windows 2000, Windows XP, Windows 2003, Windows VISTA
Firefox 2.0 and Firefox 3.0 on Windows XP and Windows 2003
JRE (Java Runtime Environment) 1.5 update 16 or higher
– F I N A L –