sPHENIX Director’s Review

March 6-8, 2018

BNL

Irina Sourikova

Risk Mitigation, Risk Registry and

Plans for EVMS

sPHENIX Risk Management • Integral part of Project Management

• Aims at bringing attention to problem areas and developing risk mitigation plans in advance

• sPHENIX Risk Management Plan (RMP)

Defines roles and responsibilities

Describes risk management process

Outlines common risk mitigation strategies

Documents Risk Registry

Documents risk communications

• Risk Registry and Mitigation Plans Review on 1/30/2018 by

Diane Hatton, NPP Directorate

Erik Johnson, NSLS-II

Steve Hulbert, NSLS-II

Julian Adams, NSLS-II

• Comments from the review have been all implemented.

2 March 6, 2018 sPHENIX Director's Review

sPHENIX Risk Management (cont) • Risk Registry has been developed by breaking down risks by WBS structure and into categories:

– Cost

– Schedule

– Technical/Scope

• Risk analysis for all stages of the MIE and parallel activities:

– Design, R&D, Procurement, Production, Installation

• Infrastructure, Integration and Installation also considered

• Continuous risk reevaluation

– Last revision Feb 2018

– Five risks have been already retired

– Risk ranks have been reassigned a few times • Risk Registry has opportunities

3 March 6, 2018 sPHENIX Director's Review

• Risk attributes: – Unique ID

– Owner

– WBS

– Name

– Trigger

– Consequences

– Timeframe

– Probability

– Impact (cost in $, schedule in days, scope/technical)

– Weighted cost impact (calculated)

– Weighted schedule impact (calculated)

– Rank (function of probability and impact)

– Mitigation plan

– Status

– Retirement date

– Retirement comments

sPHENIX Risk Management Board (RMB)

4 March 6, 2018 sPHENIX Director's Review

• RMB will meet monthly after CD-1

• All types of risk will be tracked

– Cost

– Procurement

– ES&H

– Human resource coordination

– Schedule

– Scope

• Broad expertise will ensure timely problem resolution

Project Director,

chair Project

Manager

Business Ops Reps

ES&H Manager

Project Controls Manager

Co-spokespeople when needed

Resource coordinator

L2 managers

Federal Project Director

sPHENIX Risk Register: Risk Impact & Probability

5 March 6, 2018 sPHENIX Director's Review

SBMS example tailored for sPHENIX

sPHENIX Risk Register: Cost Summary

6 March 6, 2018 sPHENIX Director's Review

sPHENIX Risk Register: Risk Cost Summary

7 March 6, 2018 sPHENIX Director's Review

• Total weighted risk cost impact is $990,428 as of March 2018.

• The sum of risk cost and estimate uncertainty cost does not exceed sPHENIX contingency.

• Our biggest cost risk is the ‘unknown unknowns’ for which we allocated $408,838.

• Next on the list is the funding profile stretch with $250,000 weighted cost which we have to accept.

sPHENIX Risk Register: Schedule Summary

8 March 6, 2018 sPHENIX Director's Review

sPHENIX Risk Register: Schedule Risk Summary

9 March 6, 2018 sPHENIX Director's Review

• Currently the biggest schedule risk is funding profile stretching. Its weighted impact is 9 month .

• All other schedule risks could be absorbed by the schedule contingency.

sPHENIX Risk Register: Mitigation Plans 1

10 March 6, 2018 sPHENIX Director's Review

sPHENIX Risk Register: Mitigation Plans 2

11 March 6, 2018 sPHENIX Director's Review

sPHENIX Risk Register: Mitigation Plans 3

12 March 6, 2018 sPHENIX Director's Review

sPHENIX EVMS Plans

13 March 6, 2018 sPHENIX Director's Review

• sPHENIX will be managed under the DOE order 413.3 B and implement EVMS.

• sPHENIX experts in 413.3 B and EVMS include:

– Glenn Young

– Cathy Lavelle

– Rich Grubb

– Eric Menter

• sPHENIX PM and L2 managers (serving as CAMs) are all EVMS trained: – Sep 2015: Ed O’Brien, Eric Mannel, Jim Mills, John Lajoie, Irina Sourikova

– Jun 2017: Christine Aidala, Mickey Chiu, Ed Desmond, John Haggerty, Tom Hemmick, Jin Huang, Ming Liu, Sasha Milov, Rob Pisani, Martin Purschke, Julia Velkovska, Craig Woody

• Project Controls are P6 trained and PMP certified

• BSA Contractor Certification for BNL Site Received Sept 15, 2008

• DOE PARS-II Certification August 2010

• DOE Recertified EVMS Surveillance Review held December 2011

• Annual EVMS Internal Surveillance Reviews Conducted – May 2014

• Resulted in BSA EVMS Recertification May 2014

• Conducted Internal Review June 2015

• DOE Review Oct 2016

• Certification Apr 2017

March 6, 2018 sPHENIX Director's Review 14

BNL EVMS Certification

March 6, 2018 sPHENIX Director's Review 15

BNL Manages Projects with Proven Systems and Software

16 March 6, 2018 sPHENIX Director's Review

Monthly Reporting Calendar

Project Management Web-based Reporting Tools

• We plan to manage EVMS documents in IPD database.

March 6, 2018 sPHENIX Director's Review 17

• Baseline Change Control in Integrated Project Database (IPDv2)

• Configuration Management

• Externally directed changes

• Internal change process defined:

- Project Execution Plan

- Configuration Management Plan,

- Project Controls Manual

• Change Control Process

- Project Change Requests (PCRs) Approvals

- Change Control Logs

- Project Contingency/Management Reserve Logs

• Variance Analysis

- Thresholds for reporting variances

- Analysis, Approval and Reporting

March 6, 2018 sPHENIX Director's Review 18

Change Control & Variance Reporting in IPD

Thresholds defined in PEP/Sharepoint

19 March 6, 2018 sPHENIX Director's Review

Variance Analysis in IPD

• WBS – Work Breakdown Structure /Dictionary • Organization Chart • Responsibility Assignment Matrix (RAM) • Control Accounts defined • Work Authorization - Control Account Plans • Baseline Reports – Cobra/Primavera cost and schedule • EVMS Measurement and Reports/Graphs • CPR – Cost Performance Report • Variance Analysis • Schedules/Milestones • Estimates at Completion • Project Change Requests

March 6, 2018 sPHENIX Director's Review 20

CAM Notebook in IPD

• EVMS preparation is advanced • sPHENIX Management and L2 managers (serve as CAMs) are

trained in EVMS • RLS is in P6 • CAMs have strong ownership of their schedules • CAMs have been updated RLS status monthly since October 2017 • Established good working relationships with business ops

representative to pull PeopleSoft data • Most P6 codes are set up for EVMS reporting • Variance analysis and change control process will start after

sPHENIX is baselined, 3-4 month before CD-2

March 6, 2018 sPHENIX Director's Review 21

sPHENIX EVMS plans summary

• sPHENIX is a first EVMS project for all CAMs. • Unknown unknowns are always a risk and a concern.

March 6, 2018 sPHENIX Director's Review 22

Issues and concerns

Recommended