SBS Program Management

John J. LeRose

SBS Collaboration Meeting October 18, 2012

2

Recent Events

• October 1: The “Program” started– Project 1: SBS Basic (WBS 1)– Project 2: Neutron Form Factor (WBS 2)

• October 15: Sent the 1st Monthly e-mail report to DOE– With Modified PMP• Personnel shifts• Schedule Shifts/Delays

3

WBS 1 (SBS basic)

• 48D48 Magnet transportation and modifications• 48D48 Magnet assembly and support platform• Magnet power supply and its associated infrastructure• Beam-line vacuum and shielding components• Beam-line steering magnets

WBS 1 Milestones

ID # Level Milestone Date

1.1-01M 1 Project start 10/1/2012

1.2-01M 2 Magnet delivered to JLab 4/30/2013

1.2-10M 2 Platform parts received 6/27/2014

1.2-20M 2 Magnet assembled on platform 3/19/2015

1.2-30M 2 Beam-line parts received 9/24/2015

1.1-10M 1 Project completion 1/29/2016

5

SBS Basic

2013 2014 2015 $-

$100

$200

$300

$400

$500

$600

$700

$800

$900

Basic Costs (AY $k)

contingencyoverheaddirect cost

6

WBS 2 (Neutron Form Factor)

• Gas Electron Multiplier (GEM) tracking detectors (UVa), 29 modules

• Front-end and data-acquisition electronics (UVa) to accompany these modules Electronics Hut, Detector Frames, and Materials needed to construct the Lead Tube Shielding, and the Lead Tube Platform for the beamline

• Coordinate Detector

WBS 2 MilestonesID # Level Milestone Date

2.1-01M 1 Project start 10/1/2012

2.2-01M 2 UVa receives GEM parts 7/22/2013

2.2-20M 2 UVa receives electronics parts 8/20/2014

2.2-10M

2

UVa GEM modules assembled and tested

10/17/2014

2.2-40M 2 Coordinate Detector Assembled 11/17/2014

2.2-30M

2

UVa front-end electronicsassembled and tested

2/2/2015

2.2-40M10

2

WBS 2.3 completed (ElectronicsHut Assembled etc.)

10/5/2015

2.1-10M 1 Project completion 1/29/2016

8

Neutron Form Factor

2013 2014 2015 $-

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

Neutron Form Factor Costs (AY $k)

contingencyoverheaddirect cost

9

• Gas Electron Multiplier (GEM) tracking detectors (UVa) (35 modules)

• Front-end and Data Acquisition Electronics to accompany these GEM modules (UVa)

• Trigger (RU)• Pole shims (JLab)• Exit field clamp (JLab)

WBS 3 (Proton Form Factor)

10

ID # Level Milestone Date

3.1-01M 1 Project start 10/1/2013

3.2-01M 2 UVa receives parts for GEM modules 8/20/2014

3.2-10M 2 UVa begins assembly of electronics 1/5/2015

3.2-50M 2 RU begins trigger design 1/6/2016

3.2-20M 2 UVa electronics assembly and tests completed 7/20/2016

3.2-30M 2 JLab receives pole shims 8/22/2016

3.2-40M 2 JLab receives exit field clamp 8/22/2016

3.2-70M 2 RU completes trigger 12/1/2016

3.2-60M 2 UVa GEM modules assembled (and tested) 2/2/2017

3.1-10M 1 Project completion 7/31/2017

WBS 3 Milestones

11

Proton Form Factor

2014 2015 2016 2017 $-

$100

$200

$300

$400

$500

$600

$700

$800

Proton Form Factor Costs (AY $k)

contingencyoverheaddirect cost

Communications with DOE!• The JLab SBS management team will provide a monthly status update

to the DOE SC Office of Nuclear Physics via e-mail.• Written status reports will be developed by the JLab Program Manager

on a quarterly basis and submitted to JLab senior management as well as the DOE-NP Instrumentation Program Manager.

• JLab, in coordination with the DOE SC Office of Nuclear Physics, will convene external review panels annually to evaluate progress. In the event of any serious problems in the interim, e.g., a detector performance issue, additional appropriate reviews would be convened by JLab.

• SBS Program Team meetings will be held regularly to keep collaborators informed of progress and problems.

The Monthly Report

• Executive summary of the “projects”• Management Highlights • WBS 1

– Work breakdown structure– Milestones (scheduled, expected, achieved)– Project oversight – WBS 1.1, 1.2, 1.3 progress problems– Costs

• WBS 2 (ditto)• WBS 3 (ditto) This year no progress, problems, or costs

October 15 report is already 7 pages (nothing really to report except that we started)

14

Summary• As a DOE “object”, we’ve just started.

– Ironing out how we report• Budgets are a challenge

– Moving targets• 2016 Ready for Neutron Form Factor expt.

– Budget willing!• 2017 Ready for Proton Form Factor expt.

– Budget willing!• As you will see today and tomorrow, there is much that is part of

SBS but not part of “The SBS Program”

15

Things that aren’t in “The SBS Program”

• BigBite• Gas Cerenkov• INFN GEM’s• Hcal• Ecal• Polarized 3He Target• …