RSRDC. UNIT- II, AJMER. ORGANISATION CHART OF RSRDC UNIT-II, AJMER. P.K.Arora. Vacant (Addl. Charge to Sh. Sunil jain. ARE. Sh. Lokesh Gupte Sh. Lalit Sharma. 3. Sh. Ashish Sharma 4. Sh. Harsh Rai. Financial Work Load in Unit. Rs. In Lacs. - PowerPoint PPT Presentation

Citation preview

RSRDC

UNIT- II, AJMER

ORGANISATION CHART OF RSRDC UNIT-II, AJMER

P.K.Arora

ARE1. Sh. Lokesh Gupte

2. Sh. Lalit Sharma

3. Sh. Ashish Sharma

4. Sh. Harsh Rai

Vacant(Addl. Charge to Sh. Sunil jain

Financial Work Load in UnitS.

No. Name of Work Client Deptt. A& F Sanction Expenditure till date

Balance Work

ARE – I Sh. Lokesh Gupta

1 Construction of ROB with approaches (Excluding railway portion) on Dholpur-Rajakhera road Km-3 on SH-2

PWD 1000.00 579.43 420.57

2 Construction of ROB with approaches at LC No. 472 (1305/6-8 Mania-Marena road) Jhansi-Agra Section.

PWD 1000.00 0.03 999.97

ARE – II Sh. Lalit Sharma

1 Construction of 2 lane ROB with approaches (excluding Railway portion) at MDR 37-A on Nagour-Basni Road in lieu of LC No. 63-C (On NH-89)

PWD 1300.00

ARE – II 600.00 191.45 408.55

ARE - IV 700.00 197.41 502.59

Rs. In Lacs

S. No. Name of Work Client

Deptt.A& F

SanctionExpenditure

till dateBalance

Work

ARE – III Sh. Ashish Sharma

1 Construction of ROB & approaches on Bhilwara -Chittorgarh BG Track at Bhilwara. (UIT Work)

UIT Bhilwara

2086.00 1327.31+

385.00(Rly.)

373.69

ARE – IV Sh. Harsh Rai

1 Construction of ROB & approaches on Phalodi-Mandal-Bhilwara road in lieu of LC No. 63-C

PWD 1000.00 870.32 129.68

2 Construction of ROB on Manglana - Makrana road in lieu of LC No. 36 Kuchaman city Makrana section SH-2B

PWD 1000.00 305.16 694.84

ARE – V Sh. Brijesh Mathur of Unit-I,Ajmer

1 Construction of ROB in Km. 70 of Kishangarh -Roopangarh road SH-07 in lieu of LC No. 28 NWR.

PWD 1000.00 843.67 156.33

2 Construction of ROB (excluding Railway portion) and approaches on Ajmer-Beawer road in lieu of LC No. 5A/2E

PWD 1000.00 783.28 216.72

Regional Pollution Control Board office, Bhilwara

Completion Cost – Rs. 23.97 lacs

Important Works Completed during last 5 years

Construction of ROB at Kishangarh, Ajmer

Total Cost : Rs. 10.00 Crores

Location : Kishangarh, Ajmer

Date of Start : 18.03.2007

Stipulated Date of Completion : 17.01.2008

Expenditure till Date : Rs. 843.96 Lacs

Likely Completion date : 30.6.2010 (Depends on Railway work)

Bottlenecks if any : Two nos span and finishing dependant on railway work

Status of railway work : Sub structure work completed. Idle since last six months due to finalisation of drawing & design of super structure.

Construction of ROB at Saradhna, Ajmer

Total Cost : Rs. 10.00 Crores

Location : Beawar road, Ajmer

Date of Start : 17.07.2007

Stipulated Date of Completion : 16.06.2008

Expenditure till Date : Rs. 783.56 Lacs

Likely Completion date : 31.12.2010 (Depends on Railway work)

Bottlenecks if any : Gap slab connecting rly. portion and finishing dependant on railway work

Status of railway work : Lay out & shifting of cable work in progress.

Construction of ROB at Bhilwara(UIT Work)

Total Cost : Rs. 20.86 Crores

Location : Bhilwara

Date of Start : 18.03.2007

Stipulated Date of Completion : 17.11.2007Expenditure till Date : Rs. 1327.31 lacs + Rs385.00 lacs (Rly.)Likely Completion date : 31.05.2010 (Depends on Railway work)

Bottlenecks if any : Two nos span and finishing dependant on railway work

Status of railway work : Sub structure work completed.

Super structure work in progress.

Construction of ROB at Mandal (Bhilwara)

Total Cost : Rs. 10.00 Crores

Location : Mandal, Bhilwara

Date of Start : 19.07.2007

Stipulated Date of Completion : 18.06.2008Expenditure till Date : Rs. 870.46 LacsLikely Completion date : 30.06.2010 (Depends on Railway work)

Bottlenecks if any : Two nos span and finishing dependant on railway work

Status of railway work : Sub structure work in progress.

Construction of ROB at Makrana Distt. - Nagour)

Total Cost : Rs. 10.00 Crores

Location : Makrana, (Distt.-Nagour)

Date of Start : 23.08.2008

Stipulated Date of Completion : 22.07.2009Expenditure till Date : Rs. 390.67 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)

Bottlenecks if any : Shifting of electric lines & encroachments.

Status of railway work : Work order placed. Work yet not started.

Construction of ROB at Nagour

Total Cost : Rs. 13.00 Crores

Location : Nagour

Date of Start : 21.08.2008

Stipulated Date of Completion : 20.07.2009Expenditure till Date : Rs. 405.45 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)

Bottlenecks if any : -

Status of railway work : Work order issued. Work yet not started.

Construction of ROB at Dholpur

Total Cost : Rs. 10.00 Crores

Location : Dholpur

Date of Start : 17.11.2007

Stipulated Date of Completion : 16.10.2008Expenditure till Date : Rs. 609.36 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)

Bottlenecks if any : -

Status of railway work : Work order issued. Work yet not started.

Construction of ROB at Mania-Marena Road

Total Cost : Rs. 10.00 Crores

Location : Mania, Dholpur

Date of Start : -

Stipulated Date of Completion : -Expenditure till Date : Rs. 0.03 lacs.Likely Completion date :

Bottlenecks if any : The present LC No. 472 is a part of Bye pass for ROB at LC No. 463. Hence traffic is to be bye passed at LC No. 473 which requires interlocking. Railway has agreed for interlocking & up gradation. Which shall be completed by Feb-2010. Revised A&F required amounting to Rs. 16.15 Crore Estimate Submitted to CE PWD through ACE Zone Bharatpur

Status of railway work : Revised GAD pending at Railway part for approval, likely to be received in Dec. 2009’

Proposed New WorksS. No. Name of Work Client Deptt. Mode Estimated Cost

1 Construction of Academic block at MLV Textile & Engineering College, Bhilwara

MLVT, Bhilwara Actual plus Rs. 350.00 lacs

2 Construction of Urban Co Operative bank at Shastri Nagar Bhilwara

BUCB Bhilwara Actual plus Rs. 50.00 Lacs