Nov 2002. Review Flood Mitigation Project Cape Town Metro Informal Settlements Winters 2001 and 2002. Background. Winter of 2001 wettest in 40 years. Extensive flooding of informal settlements. Declaration of disaster by State President. Background (contd). - PowerPoint PPT Presentation
Citation preview
ReviewFlood Mitigation Project
Cape Town Metro Informal Settlements Winters 2001 and 2002
Nov 2002
Background
Winter of 2001 wettest in 40 years.
Extensive flooding of informal settlements.
Declaration of disaster by State President.
Background (contd)
National Ministerial task team established and inter-alia resolved:To institute immediate emergency relief measures.Not to establish temporary settlement areas. In the longer term to develop Greenfield sites to accommodate flood
victims
Provincial/City task Team established to develop strategy, manage and co-ordinate flood mitigation measures.
Strategy for Emergency Relief
Strategy developed by Provincial/City Task Team and endorsed by Council Exco.
Preparedness In-Situ relief measures Temporary settlement areas. Early warning systems. Emergency shelter and social relief
Strategy Emergency Relief (contd)
Flood reporting Response co-ordination Assessment of flooded areas Beneficiary registration Health and support services Safety and security
Financial : PAWC Allocation
PAWC Allocation R 6 486 730 Expenditure ®Aerial Photography 40 251Relocation 96 919Communication 103 803Sundries 92 325Consultants 480 726In-Situ Relief 2 809 505General 68 827Total R 3 694 356
In-Situ Relief Works
Works Comprised of: Filling of low lying flood affected areas Grading of access tracks Construction of drainage ditches Construction of Stormwater intakes and allied
pipework
Financial : In-Situ Relief Summary
Settlement Value (R)Millers Camp 320 000Mkhonto Square 190 000SBDC 250 000Joe Slovo 800 000Browns Farm 340 000Freedom Park Ottery 40 000Khayelitsha 300 000Mfuleni 10 000Wallacedene 225 000Various 334 505Total R 2 809 505
Greenfield Developments
Mfuleni
Fedsure (Phillipi)
Wallacedene
Greenfield Development Status1) Mfuleni (4461 sites)
ContractNo.
SitesStatus
Complete 4461Earthworks
Ph 1 Township Services 903541 sites handed overBal. due for handover mid-Dec 2002
Ph 2 Township Services 1096Contract awarded1st sites scheduled for handover 20 Jan 2003
Ph 3 Township Services 963Contract awarded1st sites scheduled for end Mar 2003
Ph 4 Township Services 527Contract awarded1st sites scheduled for early Mar 2003
Ph 5 Township Services 970 Tenders being adjudicated
Greenfield Development Status
2) Wallacedene (5 500 sites)
Blueridge Farm & Farm 20/3 acquired
Rezoning approvals now in place
Contract No. Sites Status
Farm 20/3 Bulk Services 620 Tenders advertised
Farm 20/3 Int. Services/Top Structures 620 To be advertised mid-Jan 2003
Ph 1 Blueridge Farm Bulk Services ± 3200 To be advertised mid-Jan 2004
Ph 1 Blueridge Farm Int. Services ± 3200 To be advertised end Jan 2003
Greenfield Development Status
3) Fedsure (± 1 063 sites)
Land acquired
Rezoning & subsidies approvals in place
ContractNo.
SitesStatus
Earthworks/Det Pond ±1000Works under wayScheduled for completion Feb 2003
Internal Services 1063 To be advertised 22 Nov 2003
Financial: Greenfield Development : Land Acquisition
Land Parcel
Funding Source
CCT (CLF) CCT (SDCF) DLA Total
Philipi Park R2,4m R 2,4m
Blue Ridge Farm R4,1m R8,0m R12,1m
Farm 20/3 R1,1m R 1,1m
Totals R3,5m R4,1m R8,0m R15,6m